Michael L. Calvin v. Mark E. Martin and Christine Choate
This text of Michael L. Calvin v. Mark E. Martin and Christine Choate (Michael L. Calvin v. Mark E. Martin and Christine Choate) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
M E M O R A N D U M O P I N I O N
Margaret Schmucker filed suit against Michael L. Calvin for breach of a residential sales contract. Calvin then filed a common-law negligence cross-action, from which this appeal arises, against appellees Mark E. Martin and Christine Choate seeking indemnification for any damages that Calvin may owe Schmucker. The trial court granted summary judgment in favor of appellees. In one issue, Calvin contends that the trial court erred in granting appellees' motions for summary judgment. We affirm the judgment.
FACTUAL AND PROCEDURAL BACKGROUND
On April 5, 2004, Calvin and Schmucker entered into a contract for Calvin to purchase Schmucker's home. Martin, a real estate agent, acted as Calvin's agent. Choate was Martin's employer and served as Calvin's real estate broker.
The parties modified the contract to reflect that Schmucker, at Schmucker's expense, would make repairs agreed upon by the parties in a forthcoming inspection report. A separate provision of the contract, entitled "Termination Option," was checked and Calvin thereby reserved the right to terminate the contract within ten days of its execution. As the effective date of the contract was April 5, the termination period expired at midnight on April 15. The contract informed the parties that all notices from one party to the other had to be in writing.
A residential inspector inspected the property and delivered a report to Martin on April 14, the day before the termination option would expire. After conferring with Calvin about the nature and extent of the needed repairs, Martin prepared and faxed a one-page contract amendment to Schmucker's agent on April 15, listing the repairs Calvin wanted made before he would close. Later that day, Schmucker rejected several of Calvin's requested repairs, making the purchase unacceptable to Calvin.
At approximately 2:35 p.m. on April 15, Calvin directed Martin to terminate the contract. Approximately four minutes later, at 2:39 p.m., an associate of Martin sent two e-mails to Calvin, the first containing a termination of contract form and the second a form for the release of Calvin's earnest money deposit. Calvin opened the e-mails at approximately 7:30 p.m., when he arrived at home from his office. Neither e-mail contained any instructions, directions, or comments. On the morning of April 16, Calvin signed both documents and faxed them to Martin's office. Calvin then received the following e-mail from Martin:
I am very hopeful that the realtor will not throw a fit. Yesterday was the end of the option period, at midnight, as I told you on the phone yesterday. They should have been faxed yesterday as I instructed you, but we'll work it out. . . .
Calvin replied:
You've got to be kidding me. You gave me no time limit instructions on when to fax this document . . . and I clearly would have been at a fax machine before midnight had I known the option period expired then as I don't have the ability to throw away $1,000 of earnest money!
Martin delivered the papers to Schmucker on April 20 or 21, 2004.
Schmucker filed suit against Calvin for breach of a residential sales contract. Calvin then filed a common-law negligence cross-action against appellees Martin and Choate, seeking indemnification for any damages that Calvin may owe Schmucker. The trial court granted summary judgment in favor of appellees without specifying the grounds on which it relied. Calvin filed this appeal.
ANALYSIS
In one issue, Calvin contends that the trial court erred in granting summary judgment for appellees because material fact issues remain concerning the law of agent and principal, the plain meaning of the contract, and the course of dealings between Calvin and Martin during the contract negotiations.
Appellees respond that Calvin's knowledge of the contract terms, whether actual or constructive, conclusively negates the proximate cause element that is essential to recovery on his negligence claim. Appellees further respond that Calvin has waived his claims as to Choate by failing to brief the issues as they pertain to her.
Standard of Review
The standards for reviewing a motion for summary judgment are well established: the movants for summary judgment have the burden of showing that no genuine issue of material fact exists and that they are entitled to judgment as a matter of law; in deciding whether there is a disputed material fact issue precluding summary judgment, evidence favorable to the non-movant will be taken as true; and every reasonable inference must be indulged in favor of the non-movant and any doubts resolved in the non-movant's favor. Nixon v. Mr. Prop. Mgmt. Co., 690 S.W.2d 546, 548-49 (Tex. 1985); see Tex. R. Civ. P. 166a(c).
Summary judgment in a negligence claim in favor of a defendant is proper when the defendant negates at least one element of the plaintiff's theory of recovery. See Science Spectrum, Inc. v. Martinez, 941 S.W.2d 910, 911 (Tex. 1997). The essential elements of actionable negligence are: the existence of a legal duty owed by one person to another to protect the latter against injury; a breach of that duty, and damages proximately caused by the breach. IHS Cedars Treatment Ctr. of Desoto, Tex., Inc. v. Mason, 143 S.W.3d 794, 798 (Tex. 2004); Firestone Steel Prods. Co. v. Barajas, 927 S.W.2d 608, 613 (Tex. 1996).
Agent-Principal
Calvin contends that Martin, upon learning that Calvin wanted to terminate the contract, had a duty as agent and fiduciary to inform Calvin of the urgency with which the termination forms had to be executed and delivered to the seller and to provide the name and contact information of the seller. Calvin claims that Martin acted negligently by not doing so.
As recited, an essential element of actionable negligence is proximate cause. IHS Cedars, 143 S.W.3d at 798; Firestone Steel, 927 S.W.2d at 613. The two elements of proximate cause are cause in fact (or substantial factor) and foreseeability. IHS Cedars, 143 S.W.3d at 798.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
Michael L. Calvin v. Mark E. Martin and Christine Choate, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-l-calvin-v-mark-e-martin-and-christine-cho-texapp-2006.