Michael D'acci, Carol D'acci, Ardon McCarthy, Jason Monast, Melanie Monast, Linda Westgate, Gary Westgate, Brandon Empey, Krystile Empey, and Melissa Bessey v. Massachusetts Department of Environmental Protection

CourtMassachusetts Superior Court
DecidedMarch 27, 2024
Docket2384CV00244-C
StatusPublished

This text of Michael D'acci, Carol D'acci, Ardon McCarthy, Jason Monast, Melanie Monast, Linda Westgate, Gary Westgate, Brandon Empey, Krystile Empey, and Melissa Bessey v. Massachusetts Department of Environmental Protection (Michael D'acci, Carol D'acci, Ardon McCarthy, Jason Monast, Melanie Monast, Linda Westgate, Gary Westgate, Brandon Empey, Krystile Empey, and Melissa Bessey v. Massachusetts Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Michael D'acci, Carol D'acci, Ardon McCarthy, Jason Monast, Melanie Monast, Linda Westgate, Gary Westgate, Brandon Empey, Krystile Empey, and Melissa Bessey v. Massachusetts Department of Environmental Protection, (Mass. Ct. App. 2024).

Opinion

SUPERIOR COURT

MICHAEL D’ACCI, CAROL D’ACCI, ARDON MCCARTHY, JASON MONAST, MELANIE MONAST, LINDA WESTGATE, GARY WESTGATE, BRANDON EMPEY, KRYSTILE EMPEY, and MELISSA BESSEY v. MASSACHUSETTS DEPARTMENT OF ENVIRONMENTAL PROTECTION

Docket: 2384CV00244-C
Dates: March 21, 2024
Present: Robert B. Gordon
County: SUFFOLK
Keywords: MEMORANDUM OF DECISION AND ORDER ON PARTIES’ CROSS-MOTIONS FOR JUDGMENT ON THE PLEADINGS

            Plaintiffs are a Ten Citizen Group (“Plaintiffs”) who have challenged a final decision of the Office of Appeals and Dispute Resolution of the Massachusetts Department of Environmental Protection (“MassDEP” or the “agency”). The gravamen of Plaintiffs’ action, which they bring pursuant to the appeals provisions of the Commonwealth’s Administrative Procedure Act, G.L. c. 30A, § 14, is the contention that MassDEP improperly dismissed their appeal of the Final Air Quality Plan Approval (the “Air Permit”) that issued to Defendants Lorusso Corporation (“Lorusso”) and Bristol Asphalt Company (“Bristol”) in connection with their proposed construction and operation of an industrial asphalt plant. MassDEP dismissed Plaintiffs’ appeal of the Air Permit on the stated ground (inter alia) that Plaintiffs lacked standing to contest the agency’s failure to take sufficient measures to address the problem of

                                                                        -1-

odor associated with the approved plant, because Plaintiffs had not raised the particular issue of odor during the public comment phase of the permitting process.

HISTORY OF BRISTOL/LORUSSO’S AIR PERMIT APPLICATION

            In November, 2019, Bristol and Lorusso (the “Applicants”) filed a Non-Major Comprehensive Plan Application to construct and operate an asphalt plant in an industrial zone of Rochester, Massachusetts. The Applicants submitted an Air Quality Modeling Report in support of their application in January, 2021; and on April 27, 2021, MassDEP issued a draft Air Quality Plan Approval for the project and initiated a 30-day public comment period.

            On May 27, 2021, Plaintiffs filed written comments with MassDEP, addressed to the Applicants’ project as provisionally approved by the agency. These comments included letters expressing criticisms of the air modeling performed in support of the proposed plant. In particular, the criticisms cited the Applicants’ failure to “place sensitive receptors at the residential homes which are located adjacent to the edge of” the site for the plant, where “elevated pollutant concentrations” might be. In this same vein, the filed comments criticized the “air emissions modeling conducted by [the Applicants] for failing to assess the “regional impacts the proposed facility would have on abutting property owners.” Nowhere, however, did Plaintiffs’ filed comments raise or address any concerns regarding the matter of odor; and, indeed, the terms “odor,” “smell,” and “olfactory” do not appear anywhere therein.

            On July 28, 2021, in response to Plaintiffs’ filed public comments,[1] MassDEP directed the Applicants to supplement their submission by conducting additional air quality dispersion modeling. The Applicants thereupon conducted the additional air quality dispersion modeling study demanded by the agency, and in August, 2021 filed a revised Air Quality Modeling

--------------------------------------------

[1] There were no others.

                                                                        -2-

Report. The revised Report thus submitted addressed the Plaintiffs’ articulated concerns regarding air pollution emissions, but did not address the matter of odor.

            On August 25, 2021, MassDEP issued a memorandum which reviewed and responded to the particular criticisms that had been levelled against the project during the public comment period, and specifically approved the revised emissions modeling that had been carried out by the Applicants. Then, on August 26, 2021, MassDEP issued the Air Permit to the Applicants, effectively green-lighting their construction of the proposed asphalt plant. By this permitting, MassDEP determined that the Applicants’ project was “administratively and technically complete” and “in conformance with the [Air Pollution Control Regulations] and current air pollution control engineering practice.”

PLAINTIFFS’ APPEAL TO MassDEP

            On or about September 15, 2021, Plaintiffs filed a Notice of Claim for an Adjudicatory Hearing (the “Notice of Claim”). In this Notice, Plaintiffs the first time asserted that issuance of the Air Permit was inconsistent with governing air pollution control law and regulations, see

G.L. c. 111, § § 142A-J, because it “fails to adequately assess odor” potentially affecting their residences.

            Following a pre-hearing conference that identified the issues for adjudicative resolution, the Applicants moved to dismiss Plaintiffs’ Notice of Claim. Grounds for this motion included (among others) the contention that, by failing to raise the issue of odor in their public comments, Plaintiffs had waived the issue and were thereby precluded as a matter of standing from arguing it in an adjudicatory hearing pursuant to 310 Code Mass. Regs. § 7.51(1)(i)2. Plaintiffs opposed this motion, maintaining that their broadly worded comments on “air pollutants,” “contaminants”

                                                                        -3-

and “emissions” sufficiently raised the issue of odor to preserve their right to challenge the Air Permit on this ground.

            On March 1, 2022, the Presiding Officer of the agency provisionally denied the Applicants’ motion to dismiss. The order of denial, however, specifically stated that, “on a more developed record, perhaps with more evidence to support the moving parties’ arguments regarding the applicability of [§] 7.51(1)(i)2 to the facts of this case, a different conclusion may be drawn.”

            Plaintiffs and the Applicants thereupon filed written testimony and memoranda of law with MassDEP. After reviewing these submissions, the agency’s Presiding Officer issued a procedural order on March 18, 2022. In that order, the Presiding Officer directed Plaintiffs to show cause why a decision should not issue recommending that MassDEP’s Commissioner dismiss their appeal and affirm the previously approved Air Permit. In this connection, and as it forecast it might do after reviewing the case on a more developed record, the show cause order expressly stated that “based on the evidence presented by [Plaintiffs,] they do not have a reasonable likelihood of prevailing on their claim of standing to bring this appeal ….”

            On April 5, 2022, Plaintiffs responded to the show cause order, renewing the contention that, regardless of the vocabulary used, their public comments did adequately raise the issue of odor. On December 16, 2022, the Presiding Officer issued a Recommended Final Decision, recommending to MassDEP’s Commissioner that Plaintiffs’ appeal be dismissed and the Applicants’ Air Permit affirmed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Flint v. Commissioner of Public Welfare
589 N.E.2d 1224 (Massachusetts Supreme Judicial Court, 1992)
Navy Yard Four Associates, LLC v. Department of Environmental Protection
37 N.E.3d 46 (Massachusetts Appeals Court, 2015)
Energy Express, Inc. v. Department of Public Utilities
80 N.E.3d 309 (Massachusetts Supreme Judicial Court, 2017)
Box Pond Ass'n v. Energy Facilities Siting Board
435 Mass. 408 (Massachusetts Supreme Judicial Court, 2001)
City Council of Agawam v. Energy Facilities Siting Board
776 N.E.2d 1002 (Massachusetts Supreme Judicial Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
Michael D'acci, Carol D'acci, Ardon McCarthy, Jason Monast, Melanie Monast, Linda Westgate, Gary Westgate, Brandon Empey, Krystile Empey, and Melissa Bessey v. Massachusetts Department of Environmental Protection, Counsel Stack Legal Research, https://law.counselstack.com/opinion/michael-dacci-carol-dacci-ardon-mccarthy-jason-monast-melanie-monast-masssuperct-2024.