MICHAEL AVERSANO VS. ENERGY SMARTS MECHANICAL, LLC (DC-000363-16, HUNTERDON COUNTY AND STATEWIDE)

New Jersey Superior Court Appellate Division·Decided June 11, 2019·No. A-5086-17T3·Unpublished

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION This opinion shall not "constitute precedent or be binding upon any court." Although it is posted on the internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-5086-17T3

MICHAEL AVERSANO and KAREN AVERSANO, husband and wife,

Plaintiffs-Appellants,

v.

ENERGY SMARTS MECHANICAL, LLC,

Defendant-Respondent.

Argued May 21, 2019 – Decided June 11, 2019 Before Judges Geiger and Enright.

On appeal from Superior Court of New Jersey, Law Division, Hunterdon County, Docket No. DC-000363-

16.

Joseph F. Trinity argued the cause for appellants (Trinity & Farsiou, attorneys; Joseph F. Trinity, on the briefs).

John R. Lanza argued the cause for respondents (Lanza & Lanza, LLP, attorneys; John R. Lanza, of counsel;

Monica Alayne Hoopes, on the brief).

PER CURIUM Plaintiffs, Michael and Karen Aversano, appeal from a summary judgment order entered in favor of defendant, Energy Smarts Mechanical, LLC (ESM). Additionally, they appeal from an order denying their application to reopen discovery. We affirm both rulings.

Plaintiffs claim ESM negligently installed a geothermal heating and cooling (HVAC) system in their home. They filed suit on March 24, 2016, alleging ESM was liable for breach of contract, breach of implied covenant, negligent construction, unjust enrichment and violations of the Consumer Fraud Act (CFA). After ESM filed its Answer, the case was listed for trial on August 8, 2016. Neither party appeared for trial so the case was dismissed. The trial court later acknowledged this trial date was premature, as the original discovery end date would have been September 7, 2016.

Unaware the case had been dismissed, neither party requested an extension of the original discovery end date and the parties continued to exchange discovery. In August and September 2016, plaintiffs identified a first and second liability expert. Then, in December 2017, well over a year following the dismissal of their case, plaintiffs moved to reinstate their case, advising neither party had received notice of the initial trial date. When they moved for

A-5086-17T3

reinstatement, plaintiffs did not seek to reopen discovery nor did they disclose an intention to name a third liability expert, namely, Al Jarvis. Their motion to reinstate was granted and a new trial date of January 22, 2018 was fixed.

Just three days after the new trial date was set, ESM moved for summary judgment and to disqualify plaintiffs' second liability expert. In response, plaintiffs served ESM with two expert reports from Jarvis. ESM then moved to bar Jarvis from testifying as an expert. The motion judge denied ESM's requests for summary judgment and to bar Jarvis from testifying but granted its request to bar plaintiffs' second expert from testifying. The parties were given another trial date of February 12, 2018, but that date was adjourned to April 30, 2018 to give ESM time to review Jarvis's reports.

ESM quickly responded to Jarvis' reports by serving plaintiffs with its own liability expert report. Then, ESM filed a second motion for summary judgment or alternatively, to disqualify Jarvis as an expert witness. ESM asserted, in part, that dismissal of plaintiffs' non-negligence claims was appropriate because they had signed an "Energy Star Certificate of Completion" form when ESM had concluded its work. That form specifically stated that if "any of the work had not been completed or if there were concerns in regards to any aspect of the work performed, the customer and contractor MUST resolve

A-5086-17T3

any such issues BEFORE signing this form." Thus, ESM argued plaintiffs should not be able to take a position contrary to the representations they made in the form. ESM also contended plaintiffs' completion of the form resulted in their receipt of a $5000 government rebate, along with a $10,000 interest -free loan so they should not be able to "double-dip" by suing ESM.

In response to the summary judgment motion, plaintiffs sought to reo pen discovery to obtain a new expert, advising Jarvis no longer wished to be involved in the case. Although the trial date was postponed to May 8, 2018, it did not proceed on that date. Rather, on May 25, 2018, the trial court denied plaintiffs' request for an extension of discovery and granted summary judgment in favor of ESM. The trial judge found plaintiffs could not prove their claims without expert testimony, that they needed competent proof of an "ascertainable loss" as a prerequisite to recovery under the CFA and that their non-negligence claims were subject to dismissal based on the plain language of the Certificate of Completion. Lastly, as Jarvis already had declined to serve as plaintiffs ' expert, the court deemed the application to disqualify him as moot. Plaintiffs appeal from the order granting summary judgment and denying their application to reopen discovery.

A-5086-17T3

Plaintiffs first complain the trial court erred by failing to provide them "with all legitimate inferences" as to the evidence before it. Additionally, they argue the motion judge mistakenly found the circumstances regarding their retention of an expert were not "clearly beyond the control" of plaintiffs and their attorney. Plaintiffs also assert the motion judge erred by opining that legal fees and costs assessed against them could exceed the face amount of their damages claim and that their execution of a Certificate of Completion constituted a waiver. Lastly, they claim any prejudice to ESM in proceeding to trial is far outweighed by prejudice plaintiffs will suffer if they cannot proceed to trial.

We first address the order denying plaintiffs' application to reopen discovery. Ordinarily, "we decline to interfere with discretionary rulings involving discovery unless it appears that an injustice has been done." Cunningham v. Rummel, 223 N.J. Super. 15, 19 (App. Div. 1988). "[W]e apply an abuse of discretion standard to decisions made by . . . trial courts relating to matters of discovery." Pomerantz Paper Corp. v. New Cmty. Corp., 207 N.J. 344, 371 (2011) (citing Bender v. Adelson, 187 N.J. 411, 428 (2006)). "As it relates to extensions of time for discovery, appellate courts . . . have likewise

A-5086-17T3

generally applied a deferential standard in reviewing the decisions of trial courts." Ibid.

We note plaintiffs sought an extension of discovery after a number of trial dates had been set. Therefore, their motion to extend discovery was governed by Rule 4:24-1(c), which provides that "[n]o extension of the discovery period may be permitted after an arbitration or trial date is fixed, unless exceptional circumstances are shown." To demonstrate exceptional circumstances, we generally require a showing that the attorney diligently pursued the information sought during the discovery period but was frustrated from obtaining the discovery by circumstances largely beyond counsel's control. Bender, 187 N.J. at 429. Specifically, the moving party must show:

(1) why discovery has not been completed within time and counsel's diligence in pursuing discovery during that time; (2) the additional discovery or disclosure sought is essential; (3) an explanation for counsel's failure to request an extension of the time for discovery within the original time period; and (4) the circumstances presented were clearly beyond the control of the attorney and litigant seeking the extension of time.

[Castello v. Wohler, 446 N.J. Super. 1, 25 (App. Div.

2016) (quoting Rivers v. LSC Partnership, 378 N.J.

Super. 68, 79 (App. Div. 2015)).]

A-5086-17T3

Free access — add to your briefcase to read the full text and ask questions with AI

MICHAEL AVERSANO VS. ENERGY SMARTS MECHANICAL, LLC (DC-000363-16, HUNTERDON COUNTY AND STATEWIDE), (N.J. Ct. App. 2019).

MICHAEL AVERSANO VS. ENERGY SMARTS MECHANICAL, LLC (DC-000363-16, HUNTERDON COUNTY AND STATEWIDE) (MICHAEL AVERSANO VS. ENERGY SMARTS MECHANICAL, LLC (DC-000363-16, HUNTERDON COUNTY AND STATEWIDE)) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anthony D'agostino v. Ricardo Maldonado (068940)
78 A.3d 527 (Supreme Court of New Jersey, 2013)
State v. Robinson
974 A.2d 1057 (Supreme Court of New Jersey, 2009)
Kalogeras v. 239 Broad Avenue, L.L.C.
997 A.2d 943 (Supreme Court of New Jersey, 2010)
Khan v. Singh
975 A.2d 389 (Supreme Court of New Jersey, 2009)
Palmucci v. Brunswick Corp.
710 A.2d 1045 (New Jersey Superior Court App Division, 1998)
Siddons v. Cook
887 A.2d 689 (New Jersey Superior Court App Division, 2005)
Rivers v. LSC PARTNERSHIP
874 A.2d 597 (New Jersey Superior Court App Division, 2005)
VRG Corp. v. GKN Realty Corp.
641 A.2d 519 (Supreme Court of New Jersey, 1994)
Cunningham v. Rummel
537 A.2d 1314 (New Jersey Superior Court App Division, 1988)
Gilleski v. Community Med. Center
765 A.2d 1103 (New Jersey Superior Court App Division, 2001)
Sons of Thunder, Inc. v. Borden, Inc.
690 A.2d 575 (Supreme Court of New Jersey, 1997)
Manalapan Realty v. Township Committee of the Township of Manalapan
658 A.2d 1230 (Supreme Court of New Jersey, 1995)
Bender v. Adelson
901 A.2d 907 (Supreme Court of New Jersey, 2006)
Butler v. Acme Markets, Inc.
445 A.2d 1141 (Supreme Court of New Jersey, 1982)
Wilson v. Amerada Hess Corp.
773 A.2d 1121 (Supreme Court of New Jersey, 2001)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
Robbins v. City of Jersey
128 A.2d 673 (Supreme Court of New Jersey, 1957)
Brill v. Guardian Life Insurance Co. of America
666 A.2d 146 (Supreme Court of New Jersey, 1995)
Talalai v. Cooper Tire & Rubber Co.
823 A.2d 888 (New Jersey Superior Court App Division, 2001)