Miami Valley Contractors, Inc. v. Town of Sunman

960 F. Supp. 1366, 1997 U.S. Dist. LEXIS 5937, 1997 WL 219137
CourtDistrict Court, S.D. Indiana
DecidedApril 23, 1997
DocketIP 95-997-C-B/S
StatusPublished
Cited by2 cases

This text of 960 F. Supp. 1366 (Miami Valley Contractors, Inc. v. Town of Sunman) is published on Counsel Stack Legal Research, covering District Court, S.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Miami Valley Contractors, Inc. v. Town of Sunman, 960 F. Supp. 1366, 1997 U.S. Dist. LEXIS 5937, 1997 WL 219137 (S.D. Ind. 1997).

Opinion

ENTRY DENYING MOTION FOR PARTIAL SUMMARY JUDGMENT

BARKER, Chief Judge.

Plaintiff, Miami Valley Contractors, Inc. (MVC), brings its motion for partial summary judgment on the ground that the Defendant, Town of Sunman, Indiana (Sunman), has waived its right to seek liquidated damages relating to the completion of the first phase of the construction contract between them. MVC also maintains that the liquidated damages provisions in the contract impose unenforceable penalties, but that, even if enforceable, they should not be invoked because MVC substantially completed its work under the contract. For the reasons discussed below, MVC’s motion for partial summary judgment is dented.

I. STATEMENT OF FACTS

In January 1991, Sunman entered into an Agreed Order with the Commissioner of the Indiana Department of Environmental Management (IDEM) in which Sunman acknowledged that it had violated the Indiana Environmental Management Act by failing properly to treat wastewater. MVC Motion Ex. § at 1-2. As required by the Agreed Order, Sunman solicited bids and ultimately *1369 hired MVC to construct a wastewater treatment facility. MVC Motion Ex. 0.

Funding for the facility came from different sources, including the Department of Commerce (DOC). DOC committed to give $500, 000 to Sunman, provided the Town could obligate the entire amount by December 31, 1993. MVC Motion Ex. C, Tinkle Dep. at 27. It was primarily because of this deadline that the construction of the sewerage plant was separated into two phases in the contract between Sunman and MVC. Phase I called for the completion of seven items, including “polishing ponds,” and was to be completed by the DOC-imposed December 31, 1993 deadline; Phase II provided for the balance of the work and required completion within 365 days after the project was officially commenced. MVC Ex. A. Because Sunman’s damages would be different, depending on whether MVC failed to complete one of the Phases of construction or the other by its respective deadline, the Agreement provided for liquidated damages of $l,000-per-day if Phase I was not timely completed, and $500-per-day if Phase II was not timely completed. Sunman Ex. H at 1-2.

Largely because of poor weather conditions, DOC extended its grant-eligibility deadline to March 31, 1994. MVC Motion Ex. P. At some point before the March 31st deadline, Sunman reduced the amount of work to be completed as part of Phase I, it having become clear that only three items— an equalizations tank, aerobic digester, and sludge beds-needed to be completed in order to obligate the entirety of DOC monies. MVC Motion Ex. B, Tinkle Dep. at 29-30. The parties did not modify the contract in writing, notwithstanding that the contract required all modifications to occur by written change order. MVC Motion Ex. M at GC-7, 1Í13.1. Thus, although the final agreement provided that the polishing ponds did not need to be completed by the DOC deadline in order for Sunman to receive DOC funds, the written version of the Sunman-MVC contract still required the ponds to be constructed as a part of Phase I.

II. LEGAL ANALYSIS

A. Summary Judgment Standards

Summary judgment is appropriate if “the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Fed.R.Civ.Pro. 56(c). A genuine issue of material fact exists if there is sufficient evidence for a jury to return a verdict in favor of the non-moving party on the particular issue. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 2510, 91 L.Ed.2d 202 (1986); Methodist Med’l Ctr. v. American Med’l Sec., Inc., 38 F.3d 316, 319 (7th Cir.1994).

On a motion for summary judgment, the burden rests on the moving party to demonstrate “that there is an absence of evidence to support the nonmoving party’s case.” Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 2553, 91 L.Ed.2d 265 (1986). After the moving party demonstrates the absence of a genuine issue for trial, the responsibility shifts to the non-movants to “go beyond the pleadings” and point to evidence of a genuine factual dispute precluding summary judgment. Celotex, 477 U.S. at 322-23, 106 S.Ct. at 2552-53. In considering a motion for summary judgment, a court must draw all reasonable inferences in the light most favorable to the non-movants. Spraying Sys. Co. v. Delavan, Inc., 975 F.2d 387, 392 (7th Cir.1992). Thus, if genuine doubts remain, and a reasonable fact-finder could find for the party opposing the motion, summary judgment is inappropriate. Shields Enters., Inc. v. First Chicago Corp., 975 F.2d 1290, 1294 (7th Cir.1992); Wolf v. City of Fitchburg, 870 F.2d 1327, 1330 (7th Cir.1989).

Nevertheless, only issues of fact that could affect the outcome of a ease are “genuine” such that they may save a case from summary judgment. Anderson, 477 U.S. at 248, 106 S.Ct. at 2510; Tolle v. Carroll Touch, Inc., 23 F.3d 174, 178 (7th Cir.1994). And, “[sjummary judgment is appropriate in a matter of contract interpretation where no issues of fact exist because the language of the contract is unambiguous.” Grundstad v. Ritt et al., 106 F.3d 201, 205 (7th Cir.1997).

B. Submissions Without Leave

In its Opening Brief, MVC argues, first and foremost, that Sunman waived its right *1370 to liquidated damages from Phase I and, thus, it is foreclosed from seeking them in reference to the polishing ponds. Fundamental to MVC’s argument is its contention that the polishing ponds are Phase I items.

In its Response to MVC’s motion, Sunman rejoins that the polishing ponds were “de facto” Phase II items and therefore it is not foreclosed from seeking liquidated damages relating to them. Sunman cited three letters as evidence that the ponds were regarded as Phase II items. Surprisingly, Sunman made no meaningful attempt to argue that the contract had been modified, citing no legal authority to support the occurrence of a de facto modification.

Naturally, in its Reply, MVC pounced, noting that the contract by its very terms required a written change order if it were to be modified. MVC Motion Ex. M at GC-7, ¶ 13.1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Taylor v. Lifetouch National School Studios, Inc.
490 F. Supp. 2d 944 (N.D. Indiana, 2007)
Goltz v. University of Notre Dame Du Lac
177 F.R.D. 638 (N.D. Indiana, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
960 F. Supp. 1366, 1997 U.S. Dist. LEXIS 5937, 1997 WL 219137, Counsel Stack Legal Research, https://law.counselstack.com/opinion/miami-valley-contractors-inc-v-town-of-sunman-insd-1997.