BAZELON, Chief Judge:
MG-TV Broadcasting Company appeals from an order of, the Federal Communications Commission returning as unacceptable its application for a construction permit for UHF Channel 23 in Philadelphia, and granting an extension and permitting assignment of a previously-issued permit for that station. The permit was originally granted to Bernard Rappaport on November 30, 1961. It required that construction be commenced by January 30, 1962, and completed by July 30, 1962, and provided that it would be “automatically forfeited if the station is not ready for operation within the time specified or within such further time as the Commission may allow, unless completion of the station is prevented by causes not under the control of the permittee.” 1
In June of 1962, Rappaport filed with the Commission an application for a six-month extension of the deadline for completing construction, to January 30, 1963. The application recited that installation of equipment had not begun and that no equipment had been delivered or even ordered. Rappaport attributed the delay to the fact that
[D]uring the first part of this year I was suffering from general ill health, because of which I did not feel up to the task of establishing a new television station. However, I now feel that I am well enough to commence construction of the station.
The Commission granted the extension, but warned Rappaport in its letter of notification that
[A]ny further request for extension of time will not be granted without hearing unless a substantial showing of progress can be made. Mere paper negotiations would not constitute a substantial showing; the purchase and delivery of equipment and the actual construction of facilities would be the type [of] showing required.
The Commission’s letter also requested a report within sixty days of “actual progress toward the completion of construction.” 2
On January 28, 1963, two days before his extension expired, Rappaport submitted a second application for extension of the completion date, to July 30, 1963. At the same time, he filed an application for permission to assign the construction permit to New Jersey Television Broadcasting Corp., together with a copy of the contract providing for assignment of the permit contingent upon Commission approval.
In a letter attached as an exhibit to the extension application, Rappaport explained that following the earlier grant of an extension by the Commission and “before I could undertake further plans to construct following recovery from my illness,” a representative of New Jersey offered to purchase the permit, and that [1260]*1260an agreement had been signed on December 22, 1962. The new extension was requested “to enable me to conclude the proposed transfer and to enable [New Jersey] * *' * to proceed with its construction plans for Channel 23.” According to the application, no equipment had been delivered or installed, and apparently none had been ordered. Neither ill health nor any other reason beyond Rappaport’s control was given for the failure to begin construction.3
The assignment application was the subject of “an avalanche of pleadings, charges and countercharges from various parties, as well as inquiries from the Commission,” all centering around the qualifications of the proposed assignee, New Jersey; and for over three and one-half years no action on the application was taken by the Commission. On October 24, 1966, Rappaport notified the Commission that the agreement with New Jersey had been terminated; that an agreement assigning the permit to Seven Arts Broadcasting Corp., subject to Commission approval, had been signed on September 26, 1966; and that he was in the process of preparing an application for assignment of the permit to Seven Arts. Accordingly, on November 1, 1966, the Commission dismissed the pending application for assignment to New Jersey.
The application for assignment to Seven Arts was filed November 25, 1966. The contract with Seven Arts provided for payment of between $12,000 and $20,-000 as consideration for the transfer, all of which, Rappaport alleged, represented “expenses which have been incurred in connection with preparation, filing, and prosecution of various materials and pleadings which pertain to my construction permit. * * * ”4
On January 3, 1967, MG-TV tendered for filing an application for a construction permit for Channel 23 and a petition requesting filing and processing of the application. The petition also contained the following notation:
This Petition is filed pursuant to Section 309 of the Communications Act. To the extent that favorable action on this Petition may require denial or dismissal of Application BAPCT 393 [the application for assignment to Seven Arts], the Commission may construe this pleading as a Petition to Deny pursuant to Section 309(d) of the Communications Act.
The petition contained no allegation that Seven Arts was unqualified for a permit to construct and operate the station. Instead, it argued (1) that because of the failure to observe the conditions set forth by the Commission in granting the earlier extension, the permit had “lapsed by its own terms” and the channel was thus vacant; and (2) that approval of the application for extension and assignment would be inconsistent with the public interest and an abuse of discretion.
Petitions to deny the assignment application were filed by New Jersey Broadcasting Corp., and by WIBF Broadcasting Co., a permittee of Station WIBF — TV (Channel 29), Philadelphia. [1261]*1261The primary grounds advanced related to Rappaport’s alleged lack of financial qualifications, and his failure to keep his application up to date in that he neglected to notify the Commission of a drastic change in his net worth.5 WIBF also alleged that, since Seven Arts produced and supplied films to independent television stations, it (WIBF) would be deprived of a potential supplier of film productions if Seven Arts were permitted to enter the broadcast field.
The Commission granted both Rappa-port’s applications without a hearing. Its opinion discusses the petitions to deny filed by New Jersey and WIBF, concluding that both petitioners lacked standing as “parties in interest” and, in addition, rejecting their arguments on the merits. But there is no discussion of appellant’s contentions, or of its standing to challenge the applications. The Commission simply notes that “since the assignment application will be granted, MG-TV Broadcasting • Company’s tendered application for a new construction permit for Channel 23 Philadelphia will be returned, and its petition dismissed.” The only other mention of appellant’s pleadings appears at the end of the opinion, where it is ordered that “the application for a new construction permit for Channel 23, Philadelphia, Pennsylvania, tendered for filing by MG-TV Broadcasting Company is returned as unacceptable.” Appellant now appeals this order.6
We reject appellant’s contention that the Rappaport permit had “lapsed by its own terms” ; that the station was thus left vacant; and that the Commission therefore had no choice but to give consideration to the MG-TV application in a comparative proceeding.7
Free access — add to your briefcase to read the full text and ask questions with AI
BAZELON, Chief Judge:
MG-TV Broadcasting Company appeals from an order of, the Federal Communications Commission returning as unacceptable its application for a construction permit for UHF Channel 23 in Philadelphia, and granting an extension and permitting assignment of a previously-issued permit for that station. The permit was originally granted to Bernard Rappaport on November 30, 1961. It required that construction be commenced by January 30, 1962, and completed by July 30, 1962, and provided that it would be “automatically forfeited if the station is not ready for operation within the time specified or within such further time as the Commission may allow, unless completion of the station is prevented by causes not under the control of the permittee.” 1
In June of 1962, Rappaport filed with the Commission an application for a six-month extension of the deadline for completing construction, to January 30, 1963. The application recited that installation of equipment had not begun and that no equipment had been delivered or even ordered. Rappaport attributed the delay to the fact that
[D]uring the first part of this year I was suffering from general ill health, because of which I did not feel up to the task of establishing a new television station. However, I now feel that I am well enough to commence construction of the station.
The Commission granted the extension, but warned Rappaport in its letter of notification that
[A]ny further request for extension of time will not be granted without hearing unless a substantial showing of progress can be made. Mere paper negotiations would not constitute a substantial showing; the purchase and delivery of equipment and the actual construction of facilities would be the type [of] showing required.
The Commission’s letter also requested a report within sixty days of “actual progress toward the completion of construction.” 2
On January 28, 1963, two days before his extension expired, Rappaport submitted a second application for extension of the completion date, to July 30, 1963. At the same time, he filed an application for permission to assign the construction permit to New Jersey Television Broadcasting Corp., together with a copy of the contract providing for assignment of the permit contingent upon Commission approval.
In a letter attached as an exhibit to the extension application, Rappaport explained that following the earlier grant of an extension by the Commission and “before I could undertake further plans to construct following recovery from my illness,” a representative of New Jersey offered to purchase the permit, and that [1260]*1260an agreement had been signed on December 22, 1962. The new extension was requested “to enable me to conclude the proposed transfer and to enable [New Jersey] * *' * to proceed with its construction plans for Channel 23.” According to the application, no equipment had been delivered or installed, and apparently none had been ordered. Neither ill health nor any other reason beyond Rappaport’s control was given for the failure to begin construction.3
The assignment application was the subject of “an avalanche of pleadings, charges and countercharges from various parties, as well as inquiries from the Commission,” all centering around the qualifications of the proposed assignee, New Jersey; and for over three and one-half years no action on the application was taken by the Commission. On October 24, 1966, Rappaport notified the Commission that the agreement with New Jersey had been terminated; that an agreement assigning the permit to Seven Arts Broadcasting Corp., subject to Commission approval, had been signed on September 26, 1966; and that he was in the process of preparing an application for assignment of the permit to Seven Arts. Accordingly, on November 1, 1966, the Commission dismissed the pending application for assignment to New Jersey.
The application for assignment to Seven Arts was filed November 25, 1966. The contract with Seven Arts provided for payment of between $12,000 and $20,-000 as consideration for the transfer, all of which, Rappaport alleged, represented “expenses which have been incurred in connection with preparation, filing, and prosecution of various materials and pleadings which pertain to my construction permit. * * * ”4
On January 3, 1967, MG-TV tendered for filing an application for a construction permit for Channel 23 and a petition requesting filing and processing of the application. The petition also contained the following notation:
This Petition is filed pursuant to Section 309 of the Communications Act. To the extent that favorable action on this Petition may require denial or dismissal of Application BAPCT 393 [the application for assignment to Seven Arts], the Commission may construe this pleading as a Petition to Deny pursuant to Section 309(d) of the Communications Act.
The petition contained no allegation that Seven Arts was unqualified for a permit to construct and operate the station. Instead, it argued (1) that because of the failure to observe the conditions set forth by the Commission in granting the earlier extension, the permit had “lapsed by its own terms” and the channel was thus vacant; and (2) that approval of the application for extension and assignment would be inconsistent with the public interest and an abuse of discretion.
Petitions to deny the assignment application were filed by New Jersey Broadcasting Corp., and by WIBF Broadcasting Co., a permittee of Station WIBF — TV (Channel 29), Philadelphia. [1261]*1261The primary grounds advanced related to Rappaport’s alleged lack of financial qualifications, and his failure to keep his application up to date in that he neglected to notify the Commission of a drastic change in his net worth.5 WIBF also alleged that, since Seven Arts produced and supplied films to independent television stations, it (WIBF) would be deprived of a potential supplier of film productions if Seven Arts were permitted to enter the broadcast field.
The Commission granted both Rappa-port’s applications without a hearing. Its opinion discusses the petitions to deny filed by New Jersey and WIBF, concluding that both petitioners lacked standing as “parties in interest” and, in addition, rejecting their arguments on the merits. But there is no discussion of appellant’s contentions, or of its standing to challenge the applications. The Commission simply notes that “since the assignment application will be granted, MG-TV Broadcasting • Company’s tendered application for a new construction permit for Channel 23 Philadelphia will be returned, and its petition dismissed.” The only other mention of appellant’s pleadings appears at the end of the opinion, where it is ordered that “the application for a new construction permit for Channel 23, Philadelphia, Pennsylvania, tendered for filing by MG-TV Broadcasting Company is returned as unacceptable.” Appellant now appeals this order.6
We reject appellant’s contention that the Rappaport permit had “lapsed by its own terms” ; that the station was thus left vacant; and that the Commission therefore had no choice but to give consideration to the MG-TV application in a comparative proceeding.7 Appellant’s argument is premised on the provision in the original permit that it would be “automatically forfeited” if the construction deadline were not met, and on the Commission’s statement in granting the earlier extension, to January 30, 1963, that no further extension would be granted absent a “substantial showing of progress.” However, it is well settled that a construction permit does not “lapse,” notwithstanding a failure to abide by its terms, until the Commission declares it forfeited.8 Therefore, if the Commission acted properly in granting the extension sought by Rappa-port, it was correct in returning appellant’s application without consideration.
The Commission recognized that “undoubtedly” it could have denied the extension and required surrender of Rappaport’s permit, since it made no finding that the failure to construct was due to causes “not under the control of” Rappaport.9 Thus, the question is whether the Commission committed legal error or abused its discretion by granting the extension to enable assignment of the permit to Seven Arts, rather than declaring the station vacant and holding a comparative hearing looking toward the grant of a new construction permit.
Appellant argues that the record reveals no public interest basis for the Commission’s action, stressing Rappa-port’s failure to commence construction, the absence of any satisfactory explanation, and the fact that extension of the permit was being sought solely to enable him to sell it. Appellant makes no claim that the Commission is forbidden to ex[1262]*1262tend the life of a “bare” permit, or that extension may never be granted for purposes of assignment. Rather, it contends that given all the circumstances presented here, and in the absence of adequate findings and reasons, the Commission’s action cannot be sustained. We agree.
Although it did not so state in its opinion, the Commission now maintains on appeal that its action is supported by a policy of fostering development of UHF broadcasting. In its brief the Commission states that it has been “purposefully lenient” in granting extensions of UHF permits, and that “this has been especially true when assignments have been in the offing.” The history and rationale of this policy are elaborated in a supplemental memorandum filed by the Commission following oral argument. In the early days of UHF, the Commission states, extensions were “almost automatically granted upon the mere allegation that it was economically unfeasible to construct at the time.” With improving economic conditions, and the passage in 1962 of the all-channel receiver legislation,10 the Commission decided that it would no longer accept the excuse of economic unfeasibility alone.11 Nevertheless, it continued to grant extensions “where a reason was advanced which looked toward the actual inception of service,” including assignment of the permit to a person “willing to commence broadcasting.” 12
Whatever the merits of the Commission's liberal-extension policy in general, we think the record reveals a need for further exploration of its applicability to the circumstances presented here. Manifestly this was not a situation in which the Commission could assume that no qualified person other than the proposed assignee would be willing to undertake construction.13 Appellant had tendered its application, and without a comparative hearing there was no reason to believe it was less well qualified than Seven Arts.
It may be, of course, that the Commission viewed the assignment to Seven Arts not as the only means of putting the station in operation, but as the most expeditious. Certainly that might have been the case had Rappaport already undertaken partial construction. However, as we read the record no significant progress toward construction had been made. Thus the only time saved by the assignment appears to be that which would be consumed in a comparative proceeding to assess the qualifications of other applicants besides Seven Arts.14 ¿This marginal shortening of a purely administrative delay must be weighed against the public interest in having service provided by the best qualified applicant available.15 “The basic teaching of the Ashbacker case is that comparative consideration by the Commission and competition between the ap[1263]*1263plicants is the process most likely to serve the public.”16
Conceivably, the Commission could have been motivated here by a desire to permit Rappaport to recoup his “equity,” as a means of encouraging other investors to develop UHF facilities. But Rappaport’s investment in the station was limited to the legal fees and other expenses incurred in securing and preserving the permit. In these circumstances the Commission’s action could hardly serve as encouragement to other permittees to undertake construction17— and indeed it could well have the opposite effect, thus defeating the plain intent of Congress that stations for which construction permits ■ have been granted should begin operation without undue delay.18
In the absence of countervailing public interest considerations, Rappaport’s “equity” might be sufficient to support the Commission’s decision. But his bona fides is hardly apparent on the face of the record. Without explanation of the Commission’s decision, we cannot discern its implications for the public interest. More is at stake than the relatively trifling sums Rappaport stands to receive. Just as “trafficking” in broadcast licenses is inimical to the public interest, so may an unnecessarily lenient policy toward assignments of construction permits, especially where construction was never even begun, encourage a kindred evil. Such a policy may carry the risk of attracting applications from speculators who may have neither adequate finances nor a firm intention to undertake actual broadcasting: if they succeed in putting together a going operation, they may strike it rich; if they fail, they can recoup their expenses.
We do not say that the Commission’s decision was necessarily wrong, or that the Commission abused its concededly broad discretion. We do say that the questions appellant has raised are substantial enough to require at least a reasoned answer.
Intervenor contends that appellant’s position in this case constitutes a “calculated effort to leap-frog” section 310(b) of the Communications Act. That section provides that in disposing of applications to transfer construction permits or licenses the Commission “may not consider whether the public interest, convenience, and necessity might be served by the transfer * * * of the permit or license to a person other than the proposed transferee or assignee.”19 The legislative history makes clear that this [1264]*1264provision was designed to “annul the so-called AVCO procedure,” whereby the Commission subjected assignment applications to the type of comparative consideration employed in passing on initial applications for permits or licenses.20 Thus, where permission is sought to assign a valid existing permit, the only ¡ question is whether the proposed assignee \ possesses the minimum qualifications 'consistent with the “public interest, convenience and necessity.”
But of course nothing in section 310(b) forbids the Commission to consider whether the assignor’s permit is valid. Rappaport sought not only permission to assign, but also extension of a permit whose terms precluded extension under the apparent circumstances of this case. The statute denies appellant any right to consideration as a competing applicant for assignment of the Rappaport permit, if the permit continues to be valid. But appellant’s whole argument was that the Commission should deny the application for extension and declare the permit forfeited. The Commission’s opinion totally fails to confront this substantial contention, and Section 310(b) in no wise excuses the failure.21
Nor do we think the Commission’s failure to come to grips with the substance of appellant’s contentions is excused by the procedural posture in which they were presented. Appellant filed two pleadings before the Commission. One was its application for a construction permit, the other was its “petition.” The petition sought filing and processing of the application. Probably because it recognized the weakness of its argument that the permit had “lapsed by it own terms” irrespective of any Commission action on the applications for assignment and extension, appellant also requested that its petition be construed as a “petition to deny” those applications pursuant to section 309 of the Act.22
It is clear that a petition to deny may not be filed in opposition to an application for extension of a construction permit.23 However, a “party in interest” 24 may file a petition to deny an application to assign a construction permit.25 Thus, appellant’s petition, on its face, was properly before the Commission.
Appellant argued that the assignment application should be denied because the permit should not be extended. The only question is whether, by refusing to authorize petitions to deny an extension, [1265]*1265Congress implicitly also precluded petitions to deny an assignment based on arguments against an extensión which is essential to the validity of the assignment.26 We see no reason to read such a prohibition into the statute. Sections 309(b) and (d) state the general rule permitting petitions to deny and requiring hearings. Section 309(c) makes a few relatively minor exceptions from this policy, apparently in the interests of expedition. Where a permit-holder has encountered delays and seeks an extension to complete construction, elaborate procedural requirements might well only compound the injury to the public interest from the failure to construct on time. Accordingly, one of the exceptions excludes petitions to deny an extension. But where an assignor seeks extension in order to give up construction altogether, additional public interests intrude. Absent a clear expression of intent, we should not assume that Congress meant to preclude direct challenges to extensions of this sort. As this case illustrates, such extensions may raise important questions of substantive policy.
The alternative means of presenting these questions is by a post-decision petition for reconsideration. We do not think appellant was obliged to take this circuitous route. But even if it was, its failure to do so did not authorize the Commission to close its eyes to the public interest considerations raised by the petition.27 Even if the technical nature of the pleadings was not crystal clear, the thrust of the substantive argument was unmistakable. Issues brought to the Commission’s attention may not be so cavalierly disregarded.28
A separate question is whether, even though appellant’s petition to deny was properly before the Commission, it was obliged to file a petition for rehearing as a prerequisite to obtaining judicial review. Under Section 405 of the Communications Act, such a petition is required only if “the party seeking such review (1) was not a party to the proceedings resulting in” the “order, decision * * * or action” complained of, or “(2) relies on questions * * * upon which the Commission * * * has been afforded no opportunity to pass.” The second of these contingencies is plainly not applicable. As to the first, the Communications Act does not say who is a “party” to a proceeding that does not entail a hearing. In the present case, the Commission decided the assignment issue without looking beyond the papers filed. Since appellant’s papers were among those properly filed, we think appellant was a “party to the proceeding resulting in” the challenged order granting the assignment application.29 This result ap[1266]*1266cords with what appears to be the purpose of the party requirement of Section 405 — to forbid appeals by strangers to the proceedings where the Commission has not had an opportunity to consider their objections.
In sum, then, it would appear that appellant’s contentions are substantial. If the Commission does not accept them, we think it should at least address itself to them, either by answering them or by explaining why an answer is unnecessary.30
The case is reversed and remanded for further proceedings not inconsistent with this opinion.
So ordered.