Metrostar Systems, LLC v. United States

CourtUnited States Court of Federal Claims
DecidedApril 28, 2026
Docket25-2047
StatusPublished

This text of Metrostar Systems, LLC v. United States (Metrostar Systems, LLC v. United States) is published on Counsel Stack Legal Research, covering United States Court of Federal Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metrostar Systems, LLC v. United States, (uscfc 2026).

Opinion

In the United States Court of Federal Claims No. 25-2047C (Filed Under Seal: April 13, 2026) (Reissued: April 28, 2028) FOR PUBLICATION *************************************** METROSTAR SYSTEMS, LLC, * * Plaintiff, * * v. * * THE UNITED STATES, * * Defendant. * * *************************************** James Y. Boland, Venable LLP, Tysons, VA, for Plaintiff. Also on the briefs were Lindsay M. Reed, Venable LLP, Washington, D.C.; Emily R. Marcy and Timothy S. Iversen, Venable LLP, Tysons, VA. Brendan D. Jordan, Trial Attorney, Commercial Litigation Branch, Civil Division, United States Department of Justice, Washington, D.C., for Defendant. Also on the briefs were Brett A. Shumate, Assistant Attorney General; Patricia M. McCarthy, Director, and Corinne A. Niosi, Assistant Director, Commercial Litigation Branch, Civil Division, United States Department of Justice; and Lisa L. Baker, Counsel, Marine Corps Systems Command. OPINION AND ORDER Plaintiff MetroStar Systems, LLC (“MetroStar”) protests the decision of the Marine Corps Systems Command to cancel a solicitation after MetroStar submitted a proposal. See Compl. (ECF 1). The parties have filed cross-motions for judgment on the administrative record, see Pl.’s Mot. for J. on the Admin. R. (“Pl.’s MJAR”) (ECF 26); Def.’s Cross-Mot. for J. on the Admin. R. & Resp. (“Def.’s Cross-MJAR”) (ECF 30); Pl.’s Resp. & Reply to Def.’s Cross-MJAR (“Pl.’s Reply”) (ECF 32); Def.’s Reply (ECF 33), and I have heard oral argument. I conclude that cancellation was not

 Pursuant to the protective order in this case, the Court initially filed this opinion under seal on April 13, 2026, for the parties to propose redactions of confidential or proprietary information. The parties were directed to propose redactions by April 27, 2026. Proposed redactions were received from the Parties and a supporting joint memorandum. The Court has incorporated the proposed redactions and makes them with bracketed ellipses (“[. . .]” below. arbitrary or capricious under the circumstances. The government’s motion is therefore GRANTED, MetroStar’s motion is DENIED, and the case is DISMISSED.

BACKGROUND Solicitation M6785424R7603 sought proposals for support services for the Marine Corps’ Global Combat Support System. See Admin. R. (“AR”) at 163. The Solicitation contemplated award after a two-step evaluation process. In that process, the Marine Corps would first identify the offerors with the best past performance and work experience, then perform a more detailed review of those offerors’ proposals. See AR 228. The Solicitation provided that the awardee would be responsible for preparing “change requests,” defined as “any change made to the Global Combat Support System that is generated, planned, and executed outside of the Engineering Change Proposal process.” AR 187. But the Solicitation did not provide any guidance on how many change requests a contractor could anticipate needing to make. That omission led to a dilemma. The Corps’ initial review identified MetroStar and CACI (the incumbent) as the offerors with sufficient past work experience. AR 2030, 2050. But at the second step of review, it turned out that MetroStar and CACI had very different expectations about how many change requests would be required. MetroStar expected about [. . .], based on a Marine Corps briefing that had disclosed the number of change requests in a recent year. AR 2380. But CACI expected between [. . .], based on its experience as the incumbent. AR 2380. The offerors’ different expectations contributed to a wide difference in pricing. Compare AR 1577 (CACI proposal), with AR 1839 (MetroStar proposal); see also AR 2380. The Marine Corps believed that both MetroStar and CACI had reasonably estimated change requests, given the information available. AR 2380–81. But the Corps was concerned that CACI, as the incumbent, may have had an unfair informational advantage. AR 2381. To make matters even more complicated, the Corps also believed that “[a]s a practical matter, neither offeror’s interpretation would serve to properly address the entirety of the Marine Corps requirement for Change Requests.” AR 2380 (emphasis added). Those considerations diminished the Corps’ confidence that an award to either offeror would obtain best value, while increasing the risk of post-award litigation and management conflict. AR 2382. The Marine Corps therefore decided to cancel the Solicitation and start over. Id. The Corps noted that although the ambiguity about change requests “was the primary driver” for the cancellation, several other benefits were likely to result. AR

-2- 2381. The Corps anticipated (among other things) that drawing up a new solicitation would enable it to account for recent political developments; to correct potential problems in the evaluation and selection teams’ membership; and to expand the scope of work to take advantage of an opportunity for technological upgrades. AR 2381–82. While the Marine Corps based its cancellation on the need to resolve the ambiguity, it also cited a regulation governing situations where cancellation is required. AR 2382. That regulation provides that a contracting officer “shall cancel the original solicitation and issue a new one” when “an amendment proposed for issuance … is so substantial as to exceed what prospective offerors reasonably could have anticipated, so that additional sources likely would have submitted offers had the substance of the amendment been known to them[.]” FAR § 15.206(e) (codified at 48 C.F.R. § 15.206(e)). The Corps did not explicitly discuss and reject options other than cancellation. The Marine Corps accordingly cancelled the Solicitation, and MetroStar sued.

DISCUSSION I. Jurisdiction To reach the merits of the case, I must first determine that the Court has jurisdiction over MetroStar’s claims. See Steel Co. v. Citizens for a Better Env’t, 523 U.S. 83, 94 (1998). This Court’s jurisdiction in pre-award bid protests is derived from the Tucker Act, as amended by the Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, § 12(a)–(b), 110 Stat. 3870, 3874–75 (codified at 28 U.S.C. § 1491(b)). See Dyonyx, L.P. v. United States, 83 Fed. Cl. 460, 464–65 (2008). The Tucker Act now grants this Court “jurisdiction to render judgment on an action by an interested party objecting to ... the award of a contract or any alleged violation of statute or regulation in connection with a procurement[.]” 28 U.S.C. § 1491(b)(1). This Court is empowered under the statute to “award any relief that the court considers proper, including declaratory and injunctive relief[.]” 28 U.S.C. § 1491(b)(2). To establish that it has statutory standing as an interested party, see 28 U.S.C. § 1491(b)(1); CACI, Inc.-Fed. v. United States, 67 F.4th 1145, 1151 (Fed. Cir. 2023), a plaintiff must show (1) that it “is an actual or prospective bidder” and (2) that it “possesses the requisite direct economic interest.” Rex Serv. Corp. v. United States, 448 F.3d 1305, 1307 (Fed. Cir. 2006) (citing Myers Investigative & Sec. Servs., Inc. v. United States, 275 F.3d 1366, 1369–70 (Fed. Cir. 2002) (itself citing Lujan v. Defs. of Wildlife,

Related

Lujan v. Defenders of Wildlife
504 U.S. 555 (Supreme Court, 1992)
Weeks Marine, Inc. v. United States
575 F.3d 1352 (Federal Circuit, 2009)
Baystate Technologies, Inc. v. Bowers
283 F. App'x 808 (Federal Circuit, 2008)
Rex Service Corp. v. United States
448 F.3d 1305 (Federal Circuit, 2006)
Nucor Corp. v. United States
414 F.3d 1331 (Federal Circuit, 2005)
Parcel 49c Limited Partnership v. United States
31 F.3d 1147 (Federal Circuit, 1994)
Bannum, Inc. v. United States
404 F.3d 1346 (Federal Circuit, 2005)
Young v. United States
497 F. App'x 53 (Federal Circuit, 2012)
The McVey Company, Inc. v. United States
111 Fed. Cl. 387 (Federal Claims, 2013)
Croman Corp. v. United States
724 F.3d 1357 (Federal Circuit, 2013)
Knutson v. UGS CORP.
526 F.3d 339 (Seventh Circuit, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
Metrostar Systems, LLC v. United States, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metrostar-systems-llc-v-united-states-uscfc-2026.