Metropolitan Utilities District v. Aquila, Inc.

712 N.W.2d 280, 271 Neb. 454, 2006 Neb. LEXIS 62
CourtNebraska Supreme Court
DecidedApril 21, 2006
DocketS-05-127
StatusPublished
Cited by34 cases

This text of 712 N.W.2d 280 (Metropolitan Utilities District v. Aquila, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metropolitan Utilities District v. Aquila, Inc., 712 N.W.2d 280, 271 Neb. 454, 2006 Neb. LEXIS 62 (Neb. 2006).

Opinion

Connolly, J.

Metropolitan Utilities District of Omaha (MUD) appeals the district court’s order affirming a decision of the Nebraska Public Service Commission (PSC). The PSC ordered MUD to cease and desist construction of a gas main extension. Aquila, Inc., MUD’s competitor, filed a formal complaint with the PSC for a determination that MUD’s proposed extension was not in the public interest as required by Neb. Rev. Stat. § 57-1303 (Reissue 2004). The PSC found that MUD’s extension was not in the public interest and ordered MUD to cease and desist construction. Applying the factors set out in § 57-1303, the court found that the proposed extension was not in the public interest and affirmed the PSC’s order. On appeal, MUD contends that the PSC lacked jurisdiction over the matter or, in the alternative, that the extension is in the public interest. Because the record reflects competent evidence to support the district court’s finding, we affirm.

I. BACKGROUND

1. Terms and General Background

MUD is a political subdivision operating as a natural gas and water utility in the city of Omaha and in Sarpy County, Nebraska. Aquila, an investor-owned natural gas utility, operates in areas of Sarpy County. Aquila and MUD are distributors of natural gas and have contracts with Northern Natural Gas (Northern), which supplies natural gas to distributors in the area.

Northern transfers the natural gas to each of its distributors at a servicing town border station (TBS). Each TBS serves only one distributor and is designed to supply a specific amount of natural gas. TBS’s operate independently of each other and are designed and used by MUD, but are owned by Northern.

*456 According to MUD, urban encroachment around a TBS can create safety issues. MUD prefers to have its TBS’s equally spaced around the perimeter of its service area and in undeveloped areas. When it builds a TBS, it considers the current customer load and the potential for new customers. According to MUD, it oversizes its TBS’s so that the zones of influence of each TBS overlap if there is a loss of service from any particular TBS.

2. Disputed Issue

At issue is a new TBS built at 174th Street and Fairview Road in Sarpy County (Fairview TBS) for extension of three separate gas mains to connect MUD’s southwest service area to the Fairview TBS. MUD has added 8,000 customers in the area in the past 3 years and expects to add about 3,000 more each year.

In 2002, MUD’s board of directors authorized the extension of its gas mains along U.S. Highway 50 from 1,500 feet south of U.S. Highway 370 to Fairview Road and along Fairview Road from Highway 50 to 174th Street. It also authorized the construction of the Fairview TBS. MUD decided on the site for the Fairview TBS because it is located 5'A miles south of MUD’s existing service border. MUD previously considered six other areas, but they were rejected for varying reasons, such as objections by Aquila, proximity to a school, proximity to a planned business park, and future grade changes to the road.

MUD and Northern then entered into a contribution agreement which provided, among other things: (1) a contribution by Northern of $4.35 million in aid of construction to MUD payable in September 2002, with Northern retaining ownership of the branch line; (2) realignment of an amount of natural gas flow from a TBS located at 84th and Center Streets (Center Street TBS) to other mutually agreed-upon MUD delivery points to give Northern the ability to lower the branch line pressure; and (3) reimbursement to Northern for the cost of the Fairview TBS up to $500,000 by MUD. Because of the contribution agreement, the amount of natural gas per day at the Center Street TBS was reduced and a portion moved to a TBS located at 175th and Center Streets.

*457 In May 2003, Aquila filed a formal complaint with the PSC seeking an order that MUD’s proposed gasline extension under the contribution agreement violated Neb. Rev. Stat. §§ 57-1301 to 57-1307 (Reissue 2004) because it was not in the public interest. The PSC ultimately determined that the extension was not in the public interest and entered an order to cease and desist additional construction. MUD appealed to the district court and made the PSC a party to the appeal. The PSC unsuccessfully sought to be dismissed from the action.

The district court affirmed. The court first rejected an argument that it lacked jurisdiction. The court next applied the public interest factors under § 57-1303 and concluded that MUD failed to show that the extension was in the public interest. MUD appeals, and the PSC cross-appeals.

II. ASSIGNMENTS OF ERROR

MUD assigns, rephrased and consolidated, that the district court erred by (1) determining that it had jurisdiction and (2) affirming the cease and desist order. On cross-appeal, the PSC assigns that the district court erred by not dismissing it from the action.

III. STANDARD OF REVIEW

The question of jurisdiction is a question of law, upon which an appellate court reaches a conclusion independent of the trial court. Gabel v. Polk Cty. Bd. of Comrs., 269 Neb. 714, 695 N.W.2d 433 (2005). In addition, the meaning of a statute is a question of law. In re Petition of SID No. 1, 270 Neb. 856, 708 N.W.2d 809 (2006).

A final order entered by a district court in a judicial review under the Administrative Procedure Act may be reversed, vacated, or modified by an appellate court for errors appearing on the record. Gracey v. Zwonechek, 263 Neb. 796, 643 N.W.2d 381 (2002).

In an appeal under the Administrative Procedure Act, an appellate court will not substitute its factual findings for those of the district court where competent evidence supports the district court’s findings. Tyson Fresh Meats v. State, 270 Neb. 535, 704 N.W.2d 788 (2005).

*458 IV. ANALYSIS

1. Jurisdiction

MUD first argues that the PSC lacked jurisdiction over the dispute because the extension’s purpose was operationally driven to maintain and enhance MUD’s subsystem reliability and capacity and was not for the extension of service to new customers. According to MUD, § 57-1303 applies only to extensions of services to new customers. We disagree.

Section 57-1303 provides in part:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Omaha Expo. & Racing v. Nebraska State Racing Comm.
307 Neb. 172 (Nebraska Supreme Court, 2020)
McDougle v. State ex rel. Bruning
289 Neb. 19 (Nebraska Supreme Court, 2014)
City of Omaha v. C.A. Howell, Inc.
832 N.W.2d 30 (Nebraska Court of Appeals, 2013)
Livengood v. Nebraska State Patrol Retirement System
729 N.W.2d 55 (Nebraska Supreme Court, 2007)
Opinion No. (2007)
Nebraska Attorney General Reports, 2007
Turco v. Schuning
716 N.W.2d 415 (Nebraska Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
712 N.W.2d 280, 271 Neb. 454, 2006 Neb. LEXIS 62, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metropolitan-utilities-district-v-aquila-inc-neb-2006.