Metro. Dade Cty. v. Frank J. Rooney

627 So. 2d 1248, 1993 Fla. App. LEXIS 12097, 1993 WL 500884
CourtDistrict Court of Appeal of Florida
DecidedDecember 7, 1993
Docket92-2613
StatusPublished
Cited by4 cases

This text of 627 So. 2d 1248 (Metro. Dade Cty. v. Frank J. Rooney) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Metro. Dade Cty. v. Frank J. Rooney, 627 So. 2d 1248, 1993 Fla. App. LEXIS 12097, 1993 WL 500884 (Fla. Ct. App. 1993).

Opinion

627 So.2d 1248 (1993)

METROPOLITAN DADE COUNTY, APPELLANT,
v.
FRANK J. ROONEY, INC., Appellee.

No. 92-2613.

District Court of Appeal of Florida, Third District.

December 7, 1993.

Robert A. Ginsburg, County Atty., and Murray Greenberg and Cecilia M. Altonaga and Eric K. Gressman, Asst. County Attys., for appellant.

James E. Glass and Linda Dickhaus Agnant, Miami, for appellee.

Before BARKDULL, JORGENSON and LEVY, JJ.

PER CURIAM.

This appeal questions the propriety of an order granting a motion for new trial which reads in part as follows:

*1249 The COUNTY prepared and furnished to all qualified bidders a bid package for the construction of the "Stockade Pretrial Detention Facility" (the "Project") in Dade County, Florida. The Project was to be constructed pursuant to the plans and specifications prepared by the COUNTY's Architect/Engineer (hereafter "COUNTY's Architect"). ROONEY was the successful bidder and on December 17, 1985, entered into Proposal Agreement Between Dade County and Contractor (the "Contract") for the contract sum of $39,010,000.00, which required ROONEY to complete construction of the Project within 730 calendar days.
The Contract had two provisions relating to what is known in the industry as "delay damages". One provision, usually called a "No Damage for Delay" clause, sought to limit the COUNTY's liability to ROONEY to $1,000/day for delay to the Project not caused by ROONEY. The other provision, a "Liquidated Damages" clause, assessed damages of $2,500/day against ROONEY in favor of the COUNTY for each day the Project was delayed by ROONEY.
ROONEY commenced construction in January of 1986 and immediately encountered problems with the plans and specifications. The first major problem encountered was the pilings. The COUNTY's Architect designed piles to support the building. Under the Contract, ROONEY was to install the piles and have them tested to see if the piles as designed by COUNTY's Architect would support the building. The tests failed and the COUNTY's Architect had to redesign the piles, which caused a delay to the Project.
As a result of the piles being redesigned, the COUNTY's Architect had to redesign the pile caps, then the columns, the sheerwalls, and the beams — these elements constitute the basic superstructure of the Project. Suffice it to say that the COUNTY's Architect's original design was altogether inadequate and that each stage of redesign by the COUNTY's Architect further delayed construction by ROONEY.
* * * * * *
During construction, the COUNTY did not grant time extensions to ROONEY for these delays. The few "time extensions" the COUNTY offered were contingent upon limiting ROONEY to $1,000/day for its costs associated with the delay, rather than the actual substantial costs incurred by ROONEY and its subcontractors as a result of the COUNTY's Architect redesigning the structure while ROONEY was trying to build it. Additionally, during the Project, ROONEY and its subcontractors were required to perform additional work and make changes to the work for which they claimed compensation, which the COUNTY denied. At the conclusion of the Project, the COUNTY did not pay ROONEY its contract balance of approximately $2,500,000.00, which included sums owed to ROONEY's subcontractors — many of whom were small operators — caught up in the cross-fire between the principal combatants.

Procedural History

ROONEY, for itself and for the use and benefit of its subcontractors, instituted this action against the COUNTY to recover (1) the contract balance, (2) the cost associated with the many changes to the Contract [called Requests for Change Order (RCO's)] and (3) damages for delay. ROONEY's subcontractors were not in direct privity with the COUNTY and therefore had no direct right of action against the COUNTY. As a general contractor, ROONEY was entitled to pursue its own claim and those of its subcontractors against the COUNTY. Public Health Trust of Dade County v. Harrison, 454 So.2d 659 (Fla. 3d DCA 1984).
ROONEY's Complaint pled facts which as a matter of law made the No Damage for Delay provision limiting damages for delay to $1,000/day unenforceable. The COUNTY sought to limit ROONEY to $1,000/day and filed a Motion for Summary Judgment which was heard by the Honorable John A. Tanksley, the fourth judge to whom the case was assigned. Judge Tanksley denied the motion as follows:
*1250 `This motion sought to limit the contractor's claim for delay damages to $1,000.00 per day in accordance with the contract limitation as a matter of law. The Court, having heard argument of counsel and being otherwise duly advised in the premises for the reasons articulated by the Court at the hearing, it is hereupon ORDERED and ADJUDGED that the Motion for Partial Summary Judgment be and the same is hereby denied.'
The `reasons articulated by the Court at the hearing' were:
`THE COURT: My concern really is resolving something on a summary where there has been long delays, which in effect keeps these people on much longer than the contract required, and whether that was an unreasonable delay and a knowing delay because of failure to properly have everything available for them to build the building as it ultimately was put up. I will deny it. They are entitled to it.'
The parties then proceeded with massive discovery and various judges (some 9 judges presided over this case at one time or another) entered various orders. The trial was finally scheduled to commence at `a time certain' on September 21, 1991, and the COUNTY was ordered to itemize its damages. The COUNTY presented a `Summary' of over $11 million, the bulk of which was the COUNTY's alleged `actual' damages for delay in construction completion. For example, the COUNTY sought approximately $7 million for `temporary jail facilities', etc., that the COUNTY claimed it had to build because of the delay in completing the Project.
ROONEY filed Motion for Partial Summary Judgment on the Liquidated Damages provision to obtain a proper legal determination of the right of the COUNTY to claim `actual damages' in view of the specific Liquidated Damages set by the COUNTY in the Contract. ROONEY subsequently filed a Motion in Limine to preclude the COUNTY from offering its highly prejudicial evidence of `actual damages', on the basis that there simply exists no legal authority that would allow the COUNTY to recover its actual damages. The COUNTY offered no legal authority to support the COUNTY's argument that it had a right to recover actual damages, the Liquidated Damages provision notwithstanding.
* * * * * *
This procedural history is necessary to understand that at the time this action came before this Court for trial, the action had been assigned to numerous judges, and this Court was confronted with a number of seemingly inconsistent and confusing pretrial orders which tended to suggest that the Jury should determine everything, even legal questions about the Contract such as whether the COUNTY could recover actual damages irrespective of the Liquidated Damages provision.
* * * * * *
Several times during the trial, the Court considered declaring a mistrial but refrained from so doing because of the time and expense involved to the parties and the public.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shinal, M., et ux, Aplts. v. Toms M.D., S.
162 A.3d 429 (Supreme Court of Pennsylvania, 2017)
McHugh v. Proctor Gamble Paper Products Co.
776 A.2d 266 (Superior Court of Pennsylvania, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
627 So. 2d 1248, 1993 Fla. App. LEXIS 12097, 1993 WL 500884, Counsel Stack Legal Research, https://law.counselstack.com/opinion/metro-dade-cty-v-frank-j-rooney-fladistctapp-1993.