Mervin v. Magney Construction Co.

399 N.W.2d 579
CourtCourt of Appeals of Minnesota
DecidedMarch 18, 1987
DocketC2-86-837
StatusPublished
Cited by4 cases

This text of 399 N.W.2d 579 (Mervin v. Magney Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mervin v. Magney Construction Co., 399 N.W.2d 579 (Mich. Ct. App. 1987).

Opinion

OPINION

SEDGWICK, Judge.

Respondent Mervin brought this negligence suit for injuries sustained in a fall from a ladder. Appellants were building a floodwall under a federal contract, and respondent was injured while acting as the government’s representative on the project.

The jury found both respondent and appellants negligent, but that only appellants’ negligence caused the accident. Respondent was awarded $750,000 in damages. This appeal is from the judgment and the order denying appellants’ motion for a new trial.

FACTS

In April 1977, appellant Magney Construction Company (“Magney Construction”) contracted with the United States Army Corps of Engineers to construct a flood wall along the Minnesota River near North Mankato. Appellant C.W. Scheurer & Sons Construction, Inc. (“Scheurer Construction”) subcontracted with Magney Construction to do excavating and related work. Construction began in the spring of 1977 and was completed in the spring of 1978. .

Respondent Arnold Mervin was the Corps of Engineers’ construction representative on the site. His responsibility was to monitor the project and ensure that the *581 contractors were complying with the contract’s construction requirements.

The floodwall ranged from six to eleven feet in height, depending on the terrain, and from twelve to eighteen inches in width. It was one mile long when completed. Large rocks, called “riprap,” were placed along the river side of the floodwall to prevent soil erosion.

In the summer of 1977, after several sections of the floodwall had been constructed, it became inconvenient to walk around the wall to get from one side to the other, so the construction workers and government inspectors began using ladders to go over it.

The ladders were set up in pairs. One ladder would be placed against one side of the floodwall, another placed on the other side, and they would cross over the top of the wall, forming an “X”. At the top, a side rail of one ladder would be tied by rope to a side rail of the other ladder. The ladders would be set where the riprap was completed so they would not be in the way of riprap placement, and they would be moved from station to station along the floodwall as the riprap was laid. There was conflicting testimony about whether the bottoms of the ladders were ever staked to the ground.

The accident occurred on April 14, 1978. Mervin, Daniel Scheurer, a co-owner and employee of Scheurer Construction, and Larry Lapoint, Mervin’s supervisor, were inspecting the project. They used the ladders to cross from the land side to the river side of the wall without difficulty. The accident occurred on the return trip.

First Scheurer and then Lapoint climbed up the river side ladder ahead of Mervin. When Mervin reached the top of the wall, Lapoint was at the bottom of the land side ladder, completing his descent. Mervin stepped onto the top of the wall, turned around and began to mount the road side ladder, using the rails of the river side ladder for support. He had placed one foot on the road side ladder when the river side ladder came loose, causing him to lose his balance and fall. As Mervin fell, the river side ladder came over the wall, and both ladders landed on him.

After the fall, Lapoint determined that the ladders had not been staked to the ground. He told Scheurer that in the future all ladders should be staked; all ladders were subsequently staked to the ground on both sides of the wall.

Mervin continued working the day of the accident. He began suffering from neck and back pains, however, and eventually stopped working on the advice of a physician. Mervin ended his employment with the Corps of Engineers in November 1979 based on a disability, and began receiving federal workers’ compensation benefits. He has not worked since then.

Pursuant to a federal regulation, the construction contract required Magney Construction and its subcontractors to comply with the provisions of a Corps of Engineers safety manual (the “Manual”). One section of the Manual required that ladders be secured to the ground, and the trial court instructed the jury that an unexcused violation of this requirement was negligence per se.

The jury found by special verdict that Mervin and appellants were negligent, but that only appellants’ negligence was a direct cause of the accident. They awarded Mervin $410,000 as compensation for lost wages and $340,000 for pain and suffering.

ISSUES

1. Did the trial court err by instructing the jury that an unexcused violation of the Manual is negligence per se?
2. Did the trial court err by not applying the simple tool doctrine?
3. Is respondent’s claim barred by the election of remedies provisions of Minn. Stat. § 176.061?
4. Are the damages excessive as a matter of law?

ANALYSIS

I. Negligence Per Se.

Section 30B.10 of the Manual provides:

*582 Ladders shall be secured by top, bottom, and sufficient intermediate fastenings to hold them rigidly in place and to support the loads which will be imposed upon them.

Army Corps of Engineers, General Safety Requirements Manual, EM 385-1-1 (1977).

Appellants argue that it was error to give a negligence per se instruction based on this provision because the Manual lacks the force and effect of law, and because this provision does not apply to “portable” ladders such as the ones at issue.

The Restatement (Second) of Torts provides that courts may adopt the requirements of legislative enactments or administrative regulations as defining the standard of care, the violation of which is negligence per se. See Restatement (Second) of Torts §§ 285-86, 288B (1965).

The Manual has never been enacted as a regulation or a statute. A federal regulation, however, required that the construction contract provide that “the Contractor shall comply with all pertinent provisions” of the Manual. 32 C.F.R. § 7-602.42 (1979). Mervin contends that the Manual was thereby incorporated by reference into the regulation and can therefore be the basis of a negligence per se instruction.

Mervin relies primarily on Raymond v. Baehr, 282 Minn. 109, 163 N.W.2d 51 (1968). In Raymond, tenants in a building damaged by fire had sought to introduce in evidence a building code and an ordinance which provided that all buildings had to conform to the building code. The trial court excluded the building code because it had never been published as required by the city charter for the enactment of ordinances.

The supreme court reversed. It noted that certain laws could be enacted through the doctrine of incorporation by reference. Id. at 111, 163 N.W.2d at 53. Valid use of the doctrine is limited to incorporation of statutes, ordinances, and public records. The Raymond

Free access — add to your briefcase to read the full text and ask questions with AI

Related

ZumBerge v. Northern States Power Co.
481 N.W.2d 103 (Court of Appeals of Minnesota, 1992)
Michael Manning v. Lunda Construction Company
953 F.2d 1090 (Eighth Circuit, 1992)
Mervin v. Magney Construction Co.
416 N.W.2d 121 (Supreme Court of Minnesota, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
399 N.W.2d 579, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mervin-v-magney-construction-co-minnctapp-1987.