Merritt v. Crane Co.

126 Ill. App. 337, 1906 Ill. App. LEXIS 499
CourtAppellate Court of Illinois
DecidedApril 24, 1906
DocketGen. No. 12,342
StatusPublished
Cited by4 cases

This text of 126 Ill. App. 337 (Merritt v. Crane Co.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merritt v. Crane Co., 126 Ill. App. 337, 1906 Ill. App. LEXIS 499 (Ill. Ct. App. 1906).

Opinion

Mr. Presiding Justice Smith

delivered the opinion of the court.

It is urged on behalf of appellants that the liens must fail and the decree must be reversed, because the principal contract does not provide a time for completion within three years, or for payment within one year after the completion thereof, in compliance with section 6 of the Lien Act.

The provisions of the contract between W. H. Merritt & Co., appellants, and the Western Engineering & Construction Company, relating to the time of completion and of payment, are as follows: “ And the said party of the second part agrees to commence work on said elevator within five (5) days from the signing of this contract and to complete the same on or before the first day of December, A. D. 1899.” Then follow provisions for a penalty for delay, and for payments on the work which are stated in substance in the statement preceding this opinion. The contract then provides:

“Upon the receipt of the certificate of the inspector that the said elevator has been completed in full compliance with the terms of this contract and is in first-class working order, and that there have been made good such defects as may have been found during the period of ten (10) days’ trial provided for in the specifications, and upon the receipt of satisfactory evidence that all claims for material, labor and supplies of every kind furnished for this work have been fully paid and satisfied, and that the plant is free from incumbrances, the party of the first part agrees to accept the said elevator and to pay to the party of the second part the balance that is payable under the terms of the contract.”

It is contended that these provisions do not require the elevator to be completed by December 1, 1899, including the test and curing of defects, and does not require final payment within thirty days thereafter; that the contract means that the test and curing of defects shall proceed to completion at once after December 1, 1899, or, in other words, as expeditiously as their nature permits, which is, in effect, within a reasonable time after December 1,1899, and payment thirty days later.

In our opinion, the true construction of the contract must be and is that it was the duty of the inspector to issue the certificate specified in the contract immediately upon the final completion of the work, and that the work would not be completed in accordance with the specifications and plans so long as there were defects, or, in other words, particulars in which the work did not comply with the plans and specifications. It follows then that the ten days’ test was to be made before December 1, 1899, for if it was not made before that date the- contract work would not be completed on that date, within the meaning of the contract. We find no ambiguity in the language of the contract. It would be a strained construction of the language, we think, to hold that it does not require the completion of the work by December 1,1S99; and that the ten days’ test and curing of defects should proceed after December 1, 1899, with no fixed time, and therefore a reasonable time thereafter, for the completion thereof. The contract does not express that intention and its terms will not bear that construction. We think, therefore, that the principal contract provided a time for its completion within three years, and for payment within one year after the completion. It follows that this contention of appellants cannot be sustained.

Appellants further claim that there is a fatal variance between the pleadings and proofs in that it is alleged that the title to the premises on which the liens are sought to be established was in William H. Merritt and Eugene L. Merritt, as copartners, whereas the proof is that the title is in the Merritts as tenants in common.

We think that for the purpose contemplated by the lien statute the allegation of ownership was sufficiently accurate and that the proof supports it. The decree declares in legal effect that the principal contract was made with the Merritts for the erection of a certain grain elevator on land owned by William H. Merritt and Eugene L. Merritt. The clause following the names—“copartners doing business as W. H. Merritt & Co.,” is mere desoriptio personae, and does, not describe the estate. There is no fatal inconsistency between the petition, proof and decree. Springer v. Kroeschell, 161 Ill. 358.

The evidence shows that appellants expended in the erection of the elevator and plant a sum many thousands of dollars in excess of the contract price of $120,000. It appears that all of this money went into the building. It is contended by appellants upon this state of facts that the petitioners failed to establish the existence of a debt from the owners to the original contractor, and that money paid, even after the service of lien notice, is not money wrongfully paid within the meaning of the Lien Act. Simonton v. Cicero Lumber Co., 108 Ill. App. 481, is cited in support of this proposition. In that case the original contractor abandoned the work. In the case at bar the contractor completed his contract under an agreement with appellants that they would advance the money necessary to complete the work. In the Simonton case the court held that the statement furnished by the contractor was in compliance with section 5 of the Lien Act of 1895, and that accordingly section 33 of the Act did not apply to payments made by the owner to subcontractors named in the statement furnished by the contractor. We do not perceive that the Simonton case has any application to the case before us.

We are unable to agree with this view of the case. The evidence is not very full upon this point, but we think it establishes the fact that all of the $130,000 was paid by the owners to the principal contractor under the contract in question. It is to be presumed that the money was not paid, and would not have been paid before it was due, and there is no showing as to what part of the $130,000 was for extras and what part was paid on the original contract price. The language of the Lien Act is broad. Section 25 provided that upon service of the subcontractor’s notice his claim should be a lien as against the owner from the date of the service of such notice, tó the extent that the owner may be indebted to the contractor at that time, or may become indebted to him as such contractor thereafter. The evidence also shows that some of the moneys paid after February 24th were for the pay roll of the construction company in direct compliance with the terms of the contract. Under the evidence we conclude that an indebtedness existed from appellants to the construction company at the date of the service of the subcontractor’s notice or was to become due under the terms of the contract within the intent of sections 25 and 28 of the'Lien Act.

It is urged that the decree is erroneous in that it allowed interest on the subcontractor’s claims. Sections 1 and 22 of the Lien Act of 1895 provide for the allowance of interest. Murphy v. Cicero Lumber Co., 97 Ill. App. 510. It was not necessary for appellees, under the provisions of this Act, to show unreasonable or vexatious delay of payment.

Appellants contend as against the Crane Company, appellee, that the court erred in including in the decree the extras aggregating $48.77, claimed by the Crane Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago Brick Co. v. McLester
165 Ill. App. 114 (Appellate Court of Illinois, 1911)
South Side Lumber Co. v. Date
156 Ill. App. 430 (Appellate Court of Illinois, 1910)
Elkins v. Schillinger
151 Ill. App. 571 (Appellate Court of Illinois, 1909)
Miller v. Benson
146 Ill. App. 132 (Appellate Court of Illinois, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
126 Ill. App. 337, 1906 Ill. App. LEXIS 499, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merritt-v-crane-co-illappct-1906.