Merkur Steel Supply, Inc v. City of Detroit

680 N.W.2d 485, 261 Mich. App. 116
CourtMichigan Court of Appeals
DecidedMay 26, 2004
DocketDocket 241950
StatusPublished
Cited by57 cases

This text of 680 N.W.2d 485 (Merkur Steel Supply, Inc v. City of Detroit) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merkur Steel Supply, Inc v. City of Detroit, 680 N.W.2d 485, 261 Mich. App. 116 (Mich. Ct. App. 2004).

Opinion

GAGE, J.

Plaintiff Merkur Steel Supply, Inc., leases a parcel of property of approximately eleven acres in the city of Detroit. The property is adjacent to Detroit City Airport. The property contains a 188,000 square foot building and several acres of the property are vacant. For approximately ten years before this lawsuit, plaintiff attempted to expand its operations to no avail. The plans for expansion were repeatedly thwarted by city action.

Plaintiff initiated the present action against defendant city of Detroit for inverse condemnation. A jury *119 trial resulted in a verdict in favor of plaintiff for approximately $7 million. The city now appeals as of right. We affirm.

I. FACTUAL BACKGROUND

To fully understand the nature of the cause of action, we must thoroughly review the relationship between the parties before us and the allegations set forth against the city.

Sometime in 1987, the city started its efforts to expand Detroit City Airport. In that year, the city signed an agreement with Southwest Airlines for Southwest to provide jet service to the airport. The agreement obligated the city to undertake a capital improvement at the airport. Apparently during this time, the city was not complying with existing Federal Aviation Administration (FAA) regulations, as some of the buildings near the airport, including plaintiffs, were too close to the existing runway. However, it appears the FAA granted temporary waivers to the city for the noncompliance.

Beginning in 1988, the city accepted grant money from the FAA and the state of Michigan to maintain and expand the airport. The grants all contained the condition that the city agree to prohibit the construction of new improvements and remove any existing hazards on the property near the airport. 1

Around 1989, Karl Thomas and Hein Rusen, owners of plaintiff company, began contemplating constructing a 40,000 square foot addition to the existing building on their property in order to expand their business. The *120 addition would be located on five acres that are vacant. In June 1990, plaintiff filed a notice of construction with the FAA. On December 19, 1990, the director of Detroit City Airport wrote a letter to the FAA objecting to plaintiffs building of the proposed structure. But in January 1991, the FAA issued a determination that construction of the proposed addition would not be a hazard to aviation; this determination was set to expire on August 24, 1992. In the meantime, the city filed an airport layout plan in April 1992, which put plaintiffs property directly in the way of the proposed airport expansion. In July 1992, plaintiff applied to the FAA for an extension determination, but in August 1992, the FAA revoked its “no hazard” determination because of the city’s airport layout plan. Also during this time plaintiff applied for a building permit from the city, but it was denied.

In 1996, the city filed a revised layout plan showing the new airport runway going right through plaintiffs property. Apparently, because the city took no further action to condemn plaintiffs property, in September 1997, plaintiff wrote to then City Airport Director Suzette Robinson to inform her that it wished to proceed with its development. After receiving no response, plaintiff sent Robinson a second letter in October 1997, informing her that it would proceed with construction unless the city advised it that no building would be approved. Plaintiff again received no response. Thereafter, in November 1997, plaintiff hired an architectural firm to prepare plans for construction.

On July 2, 1999, the FAA issued a determination that the new building would be a hazard to aviation. On July 26,1999, the Michigan Aeronautics Bureau issued a tall structure permit to plaintiff but attached certain conditions. The permit recognized that while the forty-foot *121 building would not interfere with aviation, it could interfere with the city’s plans to expand the airport. It issued the permit with the condition that the proponent or any subsequent owners of the proposed building would not receive reimbursement for the building or any businesses associated with the building if the property was acquired for expansion. At this point, plaintiff alleges it considered its project dead.

Plaintiff filed the present lawsuit for inverse condemnation against the city in September 1999. In part, plaintiff alleged that the city’s filing of an airport layout plan constituted a taking of plaintiffs property without just compensation. The city filed a motion for summary disposition, arguing that plaintiffs complaint failed to state a claim on which relief could be granted and that the complaint stated claims against the state and federal governments that were beyond the circuit court’s jurisdiction. The trial court denied the motion for summary disposition on September 5, 2001.

Trial was bifurcated into two phases, liability and damages. At the conclusion of plaintiffs proofs, the city filed a motion for a directed verdict, arguing in part that the filing of an airport layout plan could not constitute a taking per se; that there was no evidence that any regulation imposed by the airport layout plan denied plaintiff all economically viable use of its land; that the court must apply a balancing test to determine whether a taking occurred; and that it was improper to segment the property and determine whether only the five acres on which plaintiff planned to build was taken. The trial court denied the motion.

At the conclusion of the liability phase of trial, the jury was asked to decide whether the city inversely condemned plaintiffs property and, if so, on what date the inverse condemnation occurred. The jury deter *122 mined that the city’s conduct amounted to a taking and that the taking occurred in December 1990. During the damages phase of trial, the jury was asked to determine: (1) whether plaintiff suffered damages, (2) the amount of just compensation to which plaintiff is entitled to date from January 1, 1991, (3) plaintiffs future damages, and (4) the amount of just compensation each month for which plaintiff is entitled to in the future. Following this phase of trial, the city again sought a directed verdict, arguing that plaintiff failed to establish the value of its property. The trial court denied the motion.

On March 7, 2002, the jury determined that plaintiff had suffered damages in the amount of $6.8 million and would continue to suffer damages in the amount of $3,800 each month. The city filed a motion for judgment notwithstanding the verdict (JNOV) or, in the alternative, a new trial. The trial court again denied the motion.

II. STANDARD OF REVIEW

The city raises issues dealing with the trial court’s rulings on several motions below as well as various other aspects of the trial. In its brief on appeal, the city erroneously states that the standard of review for this case is the plain error standard set forth in People v Carines, 460 Mich 750; 597 NW2d 130 (1999). Despite the city’s erroneous assertion, we will lay out the appropriate standards of review for the issues raised.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
680 N.W.2d 485, 261 Mich. App. 116, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merkur-steel-supply-inc-v-city-of-detroit-michctapp-2004.