Mercury Masonry Corp. v. Terminal Construction Corp. (In re Mercury Masonry Corp.)

118 B.R. 228, 1990 Bankr. LEXIS 1772
CourtDistrict Court, S.D. New York
DecidedAugust 20, 1990
DocketBankruptcy No. 87-B-20425-6; No. 90 ADV. 6024
StatusPublished

This text of 118 B.R. 228 (Mercury Masonry Corp. v. Terminal Construction Corp. (In re Mercury Masonry Corp.)) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mercury Masonry Corp. v. Terminal Construction Corp. (In re Mercury Masonry Corp.), 118 B.R. 228, 1990 Bankr. LEXIS 1772 (S.D.N.Y. 1990).

Opinion

DECISION ON MOTION FOR SUMMARY JUDGMENT AND CROSS-MOTION FOR PARTIAL SUMMARY JUDGMENT

HOWARD SCHWARTZBERG, Bankruptcy Judge.

Terminal Construction Corporation (“Terminal”), a defendant in an adversary proceeding commenced by the Chapter 11 debtor, Mercury Masonry Corporation (“Mercury”), has moved for summary judgment dismissing the debtor’s complaint on the basis of signed, notarized releases issued by the debtor as a precondition to the receipt of 22 periodic partial payments which the debtor received from Terminal. The debtor opposes Terminal’s motion for summary judgment on the ground that it executed the partial payment releases with the intention that it released Terminal only from claims relating to each partial payment, except for retainages held by Terminal, and that the debtor did not release Terminal from all other claims related to the construction contract between the parties. The debtor argues that summary judgment is inappropriate because there exist questions of fact as to the intent of the parties in signing the releases and whether the releases were signed as a result of fraud or duress.

The debtor cross-moved for partial summary judgment as to the retained percentages which Terminal withheld from each partial payment to the debtor. Terminal opposes the debtor’s motion as to the re-tainages on the ground that the debtor is not entitled to recover any retainages withheld by Terminal unless the debtor completes its work under the construction contract between the parties, pays its suppliers and full payment is received by Terminal for the construction work.

Factual Background

On November 7,1983, the debtor, Mercury, entered into a subcontract with Terminal, a general contractor, for the construction of a new Federal Office Building located in Jamaica, New York. Mercury agreed under the subcontract with Terminal to provide labor and materials for the installation of certain masonry and brick work for the project.

The subcontract between the debtor and Terminal provides that Terminal “agrees to make monthly partial payments of approximate estimates of the amount of work completed and materials, equipment and services furnished each month less 10 per cent retainage to insure the faithful completion of this Agreement ...”.

The payment provision in paragraph # 23 of the agreement also provides:

As a condition precedent to any payment due the Subcontractor, it shall deliver to the Contractor a release from all of its Subcontractors and Materialmen, in form satisfactory to the contractor, as well as an affidavit as to all unpaid mate-rialmen, labor, etc. incurred or to be incurred by the Subcontractor, the entire work being subject to final approval and inspection of the Contractor and the Owner upon completion; pursuant to the prime contract documents.

(Emphasis added).

In paragraph # 24 the contract provides that because acceptance occurred in the State of New Jersey, where the Contractor was located, the laws of the State of New Jersey shall control the enforcement of the contract.

For the period from May 22, 1986 through August 4, 1987, inclusive, Terminal made 22 partial payments of approximate estimates of the amount of work completed and materials, equipment and servic[230]*230es furnished periodically by the debtor, to-talling $4,012,285.82. The contract price called for a total payment from Terminal to the debtor in the sum of $5,250,000.00.

In exchange for each periodic progress payment made to the debtor by Terminal, the debtor executed a notarized release on a printed form furnished by Terminal which reads in pertinent part as follows:

KNOW ALL MEN BY THESE PRESENTS THAT Mercury Masonry Corporation Subcontractor furnishing material and performing work for the Masonry, Cast Stone Caulking, etc, on the Construction of New Federal Building being constructed by TERMINAL CONSTRUCTION CORPORATION, as General Contractor, for Bldgs. Serv., Washington, D.C. at Jamaica, Queens, New York hereby acknowledges receipt of the sum of $_being the partial payment due on its Agreement No. S£7 dated Nov. 7, 1983, including all extras, and does hereby release the said TERMINAL CONSTRUCTION CORPORATION and/or Entire Mechanical Co., Inc. from all claims of any kind, directly, indirectly or otherwise, arising out of the contract and/or of the work performed up to the date hereof, releasing the said TERMINAL CONSTRUCTION CORPORATION and/or Entire Mechanical Co., Inc. from all manner of debts, sums of money, liens, claims, and demands of whatsoever kind, which it has up to the date hereof, except only the right to receive the retained percentages, if any; and,
The said Subcontractor additionally releases its right against the building and land upon which the work has been done so that the owner of the premises, its successors and assigns, shall be freed and discharged by any claims, and so that the owner of the said lands and premises may hold and enjoy the buildings and lands free of any lien, claim and demand which the Releasor now has or might or could have on or against the same up to the date hereof, if these presents had not been made.

On September 10, 1987, Mercury and its affiliated company, LaSala Enterprises, Inc., filed with this court petitions for relief under Chapter 11 of the Bankruptcy Code, and continued to manage their properties and operate their businesses as debtors in possession pursuant to 11 U.S.C. §§ 1107 and 1108.

By motion dated November 20,1987, Terminal sought to require the debtor to assume or reject the construction subcontract which the parties executed on November 7, 1983 with respect to the Federal Office building in Jamaica, New York. After a hearing, this court directed the debtor to move to assume or reject the construction subcontract with Terminal on or before January 10, 1988. Thereafter, the debtor moved to assume the contract, which motion was subsequently withdrawn by the debtor. The court then entered an order on February 23, 1988 deeming the subcontract rejected to the extent that it had not already been terminated by conduct of the parties.

Prior to the deemed rejection of the construction subcontract, Terminal filed a proof of claim in the amount of $5 million against the debtor for breach of contract.

In its adversary complaint dated March 2, 1990, the debtor alleges that at the time of the deemed rejection of the contract, the debtor had completed in excess of 90% of the contracted services under the construction subcontract with Terminal and had the ability to fully complete the contract. The debtor alleges that Terminal failed to pay the balance of $1,237,714.18 due and owing under the construction subcontract and owes the debtor for extra labor and materials furnished in the amount of $2,398,-663.00, for a total amount of compensatory damages of at least $3,636,377.18.

On June 1, 1990, Terminal filed its answer to the debtor’s complaint which contained various denials, fourteen affirmative defenses, three counterclaims and a jury demand. Some of the affirmative defenses allege waiver, estoppel, election of remedies, release, and the application of a contractual forum selection clause. The three counterclaims are for breach of contract [231]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Cartel Capital Corp. v. Fireco of New Jersey
410 A.2d 674 (Supreme Court of New Jersey, 1980)
Goncalvez v. Patuto
458 A.2d 146 (New Jersey Superior Court App Division, 1983)
Bilotti v. Accurate Forming Corp.
188 A.2d 24 (Supreme Court of New Jersey, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
118 B.R. 228, 1990 Bankr. LEXIS 1772, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mercury-masonry-corp-v-terminal-construction-corp-in-re-mercury-masonry-nysd-1990.