Merchants National Bank & Trust Co. of Fargo v. City of Grand Forks

130 N.W.2d 212, 1964 N.D. LEXIS 130
CourtNorth Dakota Supreme Court
DecidedSeptember 11, 1964
Docket8045
StatusPublished
Cited by8 cases

This text of 130 N.W.2d 212 (Merchants National Bank & Trust Co. of Fargo v. City of Grand Forks) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Merchants National Bank & Trust Co. of Fargo v. City of Grand Forks, 130 N.W.2d 212, 1964 N.D. LEXIS 130 (N.D. 1964).

Opinion

BURKE, Judge.

The City of Grand Forks has appealed from a judgment entered against it in an action upon implied contract for materials and labor furnished in the repair of a damaged installation in the city water plant. The City has demanded a trial de novo in this court.

In June 1956, the City of Grand Forks entered into a contract with Eickhof Construction Company for the construction of improvements to the municipal waterworks of the city. Eickhof Construction sublet the electrical installation to John M. Schroeder Inc. Part of this work included the placement of switchgear, by means of which high voltage electric current was received from the power plant and delivered to the several water plant uses at proper voltages. The work was completed in March or April 1958. Upon completion, the City took possession of the installation and used it to operate motorized equipment within the plant. The switchgear contained several circuit breakers, one of which was used to operate the No. 1 high service pump and another of which was used to operate the No. 2 high service pump. These circuit breakers rested on rails and they could be pulled out from the switchgear cabinet in the same manner that a filing drawer can be pulled out of a filing cabinet. Upon each circuit breaker was a latch mechanism which held the circuit breaker in place when it had been placed in operating position within the cabinet. Between the time the City took over the operation of the switchgear in March or April 1958, and July 1959, difficulties developed upon several occasions in the latching mechanism upon one of the circuit breakers. On these occasions repairs were made by an employee of the installing contractor.

On the morning of July 1, 1959, Mr. Hoban, the city engineer, received a telephone call from the chief operator of the water plant, who told him that there was trouble with the No. 1 circuit breaker. After the call Mr. Hoban, went to the plant, *214 and according to his testimony he and the chief operator “removed the starter and seen that the contacts were gone and there was nothing that we could do with it so we just closed the door and left it.” Mr. Hoban also testified that the contacts were burnt and some of them were broken.

Immediately after the circuit breaker had been replaced in its operating position it caught fire, and as a result it was damaged beyond repair. The connecting wires to the outside power source were also destroyed. After the fire had been put out, Mr. Hoban instructed the chief operator, Ostlie, to call the installing contractor, John Schroeder, to come and make repairs.

When Mr. Schroeder arrived at the plant, he spoke first to Mr. Jenson, the plant superintendent. Mr. Webster, the city manager, came in shortly thereafter and the three of them “talked about the damage, the extent of it, how long it would take to put the gear back in operation, how much water was on hand, how soon we would be getting into an emergency situation, if the gear wasn’t at least partially placed in service.” The water plant superintendent and the city manager told him, “that if we could have the gear back in service by 6:00 o’clock that evening, at least on a partial operation basis, we could avoid an emergency situation.” They told him “to get it fixed.”

As a protective equipment for the circuit breaker, there were placed within it arc chutes or arc quenchers. These were plates made of asbestos cement, the function of which was to shield inflammable parts within the breaker from any arcing that might take place upon the opening or closing of the breaker. These arc quenchers were not in the equipment at the time of the fire. When Mr. Schroeder arrived upon the scene they were lying on the floor beside the switchgear cabinet.

As a result of the fire, circuit breaker No. 1 was completely destroyed and it was considered that some damage had been done to the circuit breaker No. 2. The City has a spare circuit breaker on hand. This-was installed in the compartment of the No. 1 circuit breaker. An engineer of the manufacturing company was flown to-Grand Forks to inspect the installation before it was placed in service. The work was completed by the six o’clock p. m. deadline fixed by the city officials. Circuit breaker No. 2 was removed and sent to the manufacturer for inspection, adjustment and repair and a new circuit breaker was-ordered to be shipped by air express to replace the one which had been destroyed. Upon receipt of the new circuit breaker' and the repaired circuit breaker, the John M. Schroeder Company installed them in the switchgear cabinet. Thereafter, it presented its bill for materials and services and', the bill was rejected by the City. The testimony that the reasonable value of the materials and services was $3,263.68 is undisputed.

The City disclaims liability upon the-ground that it had not, at the time of the fire, accepted the improvements to the water plant from the building contractor, Eickhof Construction, and that therefore the liability was that of the contractor. The City also-urges that because certain procedural prerequisites were not followed in authorizing-the work, that the City has no power to-pay the bill. '

The record shows that the switchgear and pump installation was completed in March or April 1958, and that the City took over the operation of this equipment at that time. The fire occurred July 1, 1959, some fifteen months later. Final acceptance of all of the improvement to the city water plant took place in the fall of 1959.

Paragraph FC-22 of the City’s contract with the prime contractor provides:

“The Purchaser shall have the right to take possession of and use any completed or partially completed portions of the work, notwithstanding the time for completing the entire work or such portions as may not have expired; but such taking possession and use shall *215 not be deemed an acceptance of any work not completed in accordance with the Contract Documents. If such prior use increases the cost of, or delays the work, the Contractor shall be entitled to such extra compensation or extension of time, or both, as the Engineer may determine.”

As we interpret the above contract paragraph, it provides that the taking possession of, and the use of, a completed part of the work constitutes an acceptance of that part of the work subject only to the reservation of the right to claim that the work was not completed according to contract. Since the City accepted and operated the switchgear and pumps, the contractor was relieved of liability for any subsequent damage thereto, other than damage which might result from the fact that the installation had not been completed according to contract.

In its answer the City had alleged that the No. 1 and No. 2 circuit breakers were defective. It offered proof, that latching catches which held the circuit breakers in place when they were in the operating position were defective. With respect to this proof there was a conflict in the evidence. The city engineer testified that the defective latches were on the No. 1 circuit breaker in which the fire occurred while the electrician who made the repairs on the latches stated that it was the No. 2 circuit breaker which was defective. No proof was offered that the fire was caused by the defective latches. The city electrician testified that in his opinion the fire would not have occurred had the circuit breakers been properly fused.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sykeston Township v. Wells County
356 N.W.2d 136 (North Dakota Supreme Court, 1984)
Northern Improvement Company v. State
213 N.W.2d 885 (North Dakota Supreme Court, 1973)
Bak v. Jones County
210 N.W.2d 65 (South Dakota Supreme Court, 1973)
Brusegaard v. Schroeder
201 N.W.2d 899 (North Dakota Supreme Court, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
130 N.W.2d 212, 1964 N.D. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/merchants-national-bank-trust-co-of-fargo-v-city-of-grand-forks-nd-1964.