Meier's Trucking Co. v. United Construction Co.

704 P.2d 2, 237 Kan. 692, 1985 Kan. LEXIS 436
CourtSupreme Court of Kansas
DecidedJuly 26, 1985
Docket56,877
StatusPublished
Cited by6 cases

This text of 704 P.2d 2 (Meier's Trucking Co. v. United Construction Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meier's Trucking Co. v. United Construction Co., 704 P.2d 2, 237 Kan. 692, 1985 Kan. LEXIS 436 (kan 1985).

Opinions

The opinion of the court was delivered by

McFarland, J.:

This is a dispute between a subcontractor (Meier’s Trucking Company) and the general contractor (United Construction Company, Inc.) involving a highway construction project. Meier’s three-count petition claims: (1) it is owed money for work performed; (2) it is owed damages arising from United’s breach of its contract; and (3) United is guilty of civil conspiracy. The case was called for jury trial. At the conclusion of plaintiff Meier’s case in chief, the trial court: (a) entered judgment in favor of Meier’s on count No. 1 in the amount of $24,029.43 (this claim was not disputed by United); (b) directed a verdict in favor of United on count No. 2, finding no breach of contract had occurred; and (c) dismissed count No. 3. Meier’s appeals, contending the trial court erred in not submitting claims 2 and 3 to the jury. United’s cross-appeal involves the rationale utilized by the trial court in dismissing count No. 3. The trial court held that the failure of Meier’s to establish a breach of contract under count No. 2 was fatal to the count No. 3 conspiracy claim. The issue on the cross-appeal is submitted for consideration only in the event the directed verdict on count No. 2 is reversed. There is no issue before us relative to the $24,029.43 judgment entered on count No. 1.

[693]*693The key issue in the appeal is whether or not the trial court erred in ruling, as a matter of law, that United did not breach the parties’ contract. Meier’s contends that a certain change order, greatly reducing the amount of work to be performed by Meier’s, constituted a breach of contract. In order to determine this issue the complex factual situation from which this litigation arose must be set forth in considerable detail.

As anyone familiar with the area knows, many substantial alterations in the topography of Johnson County have occurred in recent years and continue to occur as a result of highway construction. Looking forward to the future construction of the interchange of 1-435 and 1-35 (said interchange known as the Maltese Cross), certain contracts were let in 1979 by the Kansas Department of Transportation (KDOT) for the area. United was awarded a contract for what was known as the 1-435 project. This was characterized as a “heavy grading project” for the construction of the roadway and building of bridges. Final surfacing was not included. The work was to be performed in an area bounded roughly by 87th Street, Lackman Road, 103rd Street, and Renner Road.

At about the same time, KDOT awarded two other heavy grading projects of similar nature to Clarkson Construction Company. These projects were commonly referred to as the K-12 project, with the work to be performed in an area bounded roughly by 95th Street, Renner Road, 111th Street, and Lone Elm Road. The Clarkson and United work areas abutted each other and each involved hauling a portion of the excavated materials to common stockpiles situated near the future site of the Maltese Cross intersection for use in construction thereof. Otherwise the K-12 and 1-435 projects were considered to be independent of each other.

The United contract called for the excavation of an estimated 810,524 cubic yards (c.y.) of common, or earth, and 1,699,983 c.y. of rock. The contract price was $6,477,108.06. As previously stated, a portion of this material was to be hauled to the Maltese Cross stockpiles. United entered into a subcontract with Meier’s wherein Meier’s was to haul an estimated 245,432 c.y. of common excavation at a unit price of 1.39/c.y. and 316,668 c.y. of rock excavation at a unit price of 1.64/c.y. to the stockpiles for a total contract price of $860,486.00. Excavation was commenced by [694]*694United and Meier’s began hauling material to the stockpiles under the subcontract. United became concerned that there was a substantial shortfall between the estimated amount of material to be excavated and the actual quantities. United sought to renegotiate the per c.y. price it was to receive from KDOT based upon the shortfall. KDOT checked into the matter and denied there was a shortfall. On April 26, 1980, United advised Eugene Meier (a partner in the firm) to discontinue hauling as a result of the shortfall dispute it had with KDOT. On May 2,1980, Eugene Meier conferred with officials of United in the latter’s Kansas City office as to when hauling would resume. Meier stated he needed an idea of the time frame involved in the interruption as he was looking at some other construction projects. United offered to let him out of the subcontract. Meier stated he neither accepted nor rejected the offer. United officials believed Meier had accepted the offer and sent him a letter confirming the same on May 5, 1980. (For purposes of determining the propriety of the directed verdict, we accept Meier’s version). At the time work under the subcontract ceased, Meier had hauled 72,264 c.y. of material.

It is necessary at this point to turn our attention to the Clarkson K-12 project. Santa Fe railroad tracks bisect the Clarkson work area from north to south. The Clarkson project was bid on the basis that the contractor would be able to move, by vehicles, large quantities of excavation across the tracks. Santa Fe refused to agree to this. Clarkson was faced with greatly increased costs as it would have to build an expensive conveyor system over the tracks. Clarkson believed this increased cost factor should be borne by KDOT, who did not agree. To fortify its position, Clarkson contacted other bidders on the K-12 project to see if they, too, had understood vehicle passage over the tracks would be afforded and had bid with that understanding. United had been one of the unsuccessful bidders on the K-12 project and was thus contacted. The individual contacted was James Supica, United’s president. The telephone call occurred sometime in the late spring or early summer of 1980. Clarkson was unable to negotiate a settlement of its problem with KDOT and filed a multi-million dollar damage suit against KDOT.

James Supica testified he became concerned over the Clarkson lawsuit and the possible chilling effect it might have on future [695]*695highway construction projects in Johnson County. The actions of Mr. Supica at this point are the basis of Meier’s claim of breach of contract. In reviewing the propriety of a directed verdict, an appellate court is required to resolve all facts and inferences in favor of the party against whom the judgment was entered. (Stair v. Gaylord, 232 Kan. 765, 659 P.2d 178 [1983]). We will, therefore, include herein the version of subsequent events which is contained in Meier’s brief before this court as follows:

“After Clarkson filed a lawsuit against KDOT regarding the K-12 project, James Supica of United inquired of Dean Testa of KDOT whether the State had ever considered looking at the K-12 project of Clarkson and the 1-435 project of United as one area rather than two separate contracts. No one else ever made this same suggestion to Dean Testa. After James Supica made this suggestion, Dean Testa reviewed the plans for the two separate projects to see if some unified solution could be made which would eliminate the Clarkson lawsuit. In July of 1980 a meeting was held with James Supica, William Clarkson and representatives of KDOT in attendance. The intent of the parties at this meeting was to reach an agreement to modify both the Clarkson K-12 project and the United 1-435 project in an acceptable manner to both parties and to KDOT and remove the Clarkson litigation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Premier Realty, LLC v. I.T.J. Investments, Inc.
209 P.3d 741 (Court of Appeals of Kansas, 2009)
CIT Group/Sales Financing, Inc. v. E-Z Pay Used Cars, Inc.
32 P.3d 1197 (Court of Appeals of Kansas, 2001)
Meier's Trucking Co. v. United Construction Co.
704 P.2d 2 (Supreme Court of Kansas, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
704 P.2d 2, 237 Kan. 692, 1985 Kan. LEXIS 436, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meiers-trucking-co-v-united-construction-co-kan-1985.