Meic v. Deq

2016 MT 9
CourtMontana Supreme Court
DecidedJanuary 12, 2016
Docket15-0208
StatusPublished
Cited by1 cases

This text of 2016 MT 9 (Meic v. Deq) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Meic v. Deq, 2016 MT 9 (Mo. 2016).

Opinion

January 12 2016

DA 15-0208 Case Number: DA 15-0208

IN THE SUPREME COURT OF THE STATE OF MONTANA

2016 MT 9

MONTANA ENVIRONMENTAL INFORMATION CENTER,

Plaintiff and Appellant,

v.

MONTANA DEPARTMENT OF ENVIRONMENTAL QUALITY and GOLDEN SUNLIGHT MINES, INC.,

Defendants and Appellees,

JEFFERSON COUNTY, a Political subdivision of the State of Montana,

Defendant and Intervenor.

APPEAL FROM: District Court of the Fifth Judicial District, In and For the County of Jefferson, Cause No. DV 2014-36 Honorable Loren Tucker, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

David K. W. Wilson, Jr., Morrison, Sherwood, Wilson & Deola, PLLP, Helena, Montana

Elizabeth A. Brennan, Brennan Law & Mediation, PLLC, Missoula, Montana

For Appellees:

KD Feeback, Toole & Feeback, PLLC, Lincoln, Montana

R. Timothy McCrum, Thomas R. Lundquist, Crowell & Moring LLP, Washington, DC (Attorneys for Golden Sunlight Mines, Inc.) John North, Ed Hayes, Department of Environmental Quality, Helena, Montana

Mathew Johnson, Jefferson County Attorney, Steven C. Haddon, Deputy County Attorney, Boulder, Montana

Submitted on Briefs: November 4, 2015 Decided: January 12, 2016

Filed:

__________________________________________ Clerk

2 Justice Laurie McKinnon delivered the Opinion of the Court.

¶1 The Montana Environmental Information Center (MEIC) appeals from an order

issued by the Fifth Judicial District Court, Jefferson County, granting summary judgment

in favor of the Montana Department of Environmental Quality (DEQ) and Golden

Sunlight Mines, Inc (GSM). We affirm.

¶2 In April 2014, MEIC filed suit in the Fifth Judicial District Court, challenging the

DEQ’s decision to approve the expansion of GSM’s gold mine to include a smaller

nearby pit. MEIC contended that the reclamation plan the DEQ chose to reclaim the

nearby pit violated Article IX, Section 2 of the Montana Constitution and the Montana

Metal Mine Reclamation Act (MMRA), § 82-4-301, MCA, et seq. MEIC argued that

Article IX, Section 2 of the Montana Constitution and the MMRA require land disturbed

by the taking of natural resources to be “fully reclaimed” to its previous condition, and

that the reclamation plan the DEQ chose to reclaim the pit failed to do so. MEIC

maintained that the DEQ must adopt a reclamation plan that requires GSM to completely

backfill the pit after closure in order to comply with the Montana Constitution and the

MMRA. MEIC also contended that the DEQ’s decision to select the particular

reclamation plan was arbitrary and capricious because the criteria set forth in the MMRA

were not satisfied.

¶3 In response, the Appellees asserted that MEIC should be collaterally estopped

from relitigating whether the Montana Constitution and the MMRA require lands

disturbed by a mining operation to be fully reclaimed. Appellees argued that, in

3 connection with a reclamation plan for a different pit at GSM’s mine, this precise

question had already been litigated, with MEIC receiving an adverse ruling from the

District Court. Alternatively, the Appellees argued that neither the Montana Constitution

nor the MMRA require full reclamation of disturbed lands. The Appellees also

maintained that the DEQ’s decision regarding its choice of reclamation plans was

supported by substantial evidence under the criteria set forth in the MMRA.

¶4 The District Court agreed with the Appellees, concluding that MEIC’s

constitutional and statutory arguments were collaterally estopped and the DEQ’s decision

was supported by the evidence under the MMRA criteria. We affirm the District Court’s

decision regarding collateral estoppel and thus do not address the merits of whether

Article IX, Section 2 of the Montana Constitution and the MMRA require land disturbed

by the taking of natural resources to be fully reclaimed to its previous condition. We also

affirm the District Court’s holding that the criteria under the MMRA were satisfied.

¶5 We address the following issues on appeal:

1. Whether MEIC is precluded from relitigating the issue of whether Article IX, Section 2 of the Montana Constitution requires land disturbed by the taking of natural resources to be fully reclaimed to its previous condition.

2. Whether MEIC is precluded from relitigating the issue of whether the Montana Metal Mine Reclamation Act requires land disturbed by the taking of natural resources to be fully reclaimed to its previous condition.

3. Whether the DEQ made a reasoned decision in selecting the Agency-Modified Alternative under the criteria set forth in the Montana Metal Mine Reclamation Act.

4 FACTUAL AND PROCEDURAL BACKGROUND

¶6 Golden Sunlight Mines operates an open pit gold mine on the southern edge of the

Bull Mountains near Whitehall, Montana. In September 2012, GSM submitted an

application to the DEQ to amend the operating permit for its mine, proposing to expand

its mining operation to develop a smaller nearby pit that the parties refer to as the North

Area Pit. The North Area Pit is estimated to cover approximately 49.4 acres. The

expansion would allow GSM to mine an additional 4.2 million tons of gold ore and

extend GSM’s current mining operation by about two years. GSM proposed mining the

North Area Pit through the use of conventional open pit mining methods which would be

consistent with its current mining operation. In order to obtain the gold ore beneath the

North Area Pit, GSM proposed excavating below the natural water table and installing

external dewatering wells adjacent to the North Area Pit to lower the water table beneath

the pit and allow for the mineral extraction.

¶7 As part of the proposed expansion, GSM submitted a reclamation plan for the

North Area Pit to the DEQ. In 2013, the DEQ issued a draft Environmental Impact

Statement (EIS) which discussed the impacts of four alternative reclamation plans for the

North Area Pit: (1) the No Action Alternative; (2) the GSM Proposed Reclamation

Alternative; (3) the Agency-Modified Alternative; and (4) the North Area Pit Backfill

Alternative. The No Action Alternative reflects the current mining operation conducted

under GSM’s existing permit with no management plan for an additional disturbance at

the North Area Pit. Under the GSM Proposed Reclamation Alternative, the

5 approximately 52.6 million tons of non-ore waste rock that will be generated from the

North Area Pit will be primarily placed in an expansion area on the east side of the mine.

The GSM Proposed Reclamation Alternative requires GSM to continue to operate its

external dewatering wells after closure of the mine to prevent contamination of local

groundwater. In addition, GSM must install an underground in-pit sump to protect

against local groundwater contamination in the event that one of the external dewatering

wells fails. The Agency-Modified Alternative is the same as the GSM Proposed

Reclamation Alternative with the exception of various additional modifications

developed by the DEQ to further mitigate environmental impacts associated with the

mining. These modifications include: (1) the implementation of closure geodetic and

ground-movement monitoring for the North Area Pit to ensure safe access and to keep

reclamation systems working, and (2) the preparation of a detailed bat and raptor habitat

plan for the North Area Pit to provide habitat and add utility to the North Area Pit

highwall.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MEIC v. DEQ
2020 MT 288 (Montana Supreme Court, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 9, Counsel Stack Legal Research, https://law.counselstack.com/opinion/meic-v-deq-mont-2016.