Montana Environmental Information Center v. Montana Department of Environmental Quality

2016 MT 9, 365 P.3d 454, 382 Mont. 102, 2016 Mont. LEXIS 6
CourtMontana Supreme Court
DecidedJanuary 12, 2016
DocketNo. DA 15-0208
StatusPublished
Cited by6 cases

This text of 2016 MT 9 (Montana Environmental Information Center v. Montana Department of Environmental Quality) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montana Environmental Information Center v. Montana Department of Environmental Quality, 2016 MT 9, 365 P.3d 454, 382 Mont. 102, 2016 Mont. LEXIS 6 (Mo. 2016).

Opinion

JUSTICE McKINNON

delivered the Opinion of the Court.

¶1 The Montana Environmental Information Center (MEIC) appeals from an order issued by the Fifth Judicial District Court, Jefferson County, granting summary judgment in favor of the Montana Department of Environmental Quality (DEQ) and Golden Sunlight Mines, Inc (GSM). We affirm.

¶2 In April 2014, MEIC filed suit in the Fifth Judicial District Court, challenging the DEQ’s decision to approve the expansion of GSM’s gold mine to include a smaller nearby pit. MEIC contended that the reclamation plan the DEQ chose to reclaim the nearby pit violated Article IX, Section 2 of the Montana Constitution and the Montana Metal Mine Reclamation Act (MMRA), § 82-4-301, MCA, et seq. MEIC argued that Article IX, Section 2 of the Montana Constitution and the MMRA require land disturbed by the taking of natural resources to be “fully reclaimed” to its previous condition, and that the reclamation plan the DEQ chose to reclaim the pit failed to do so. MEIC maintained that the DEQ must adopt a reclamation plan that requires GSM to completely backfill the pit after closure in order to comply with the Montana Constitution and the MMRA. MEIC also contended that the DEQ’s decision to select the particular reclamation plan was arbitrary and capricious because the criteria set forth in the MMRA were not satisfied.

¶3 In response, the Appellees asserted that MEIC should be collaterally estopped from relitigating whether the Montana Constitution and the MMRA require lands disturbed by a mining operation to be fully reclaimed. Appellees argued that, in connection with a reclamation plan for a different pit at GSM’s mine, this precise [104]*104question had already been litigated, with MEIC receiving an adverse ruling from the District Court. Alternatively, the Appellees argued that neither the Montana Constitution nor the MMRA require full reclamation of disturbed lands. The Appellees also maintained that the DEQ’s decision regarding its choice of reclamation plans was supported by substantial evidence under the criteria set forth in the MMRA.

¶4 The District Court agreed with the Appellees, concluding that MEIC’s constitutional and statutory arguments were collaterally estopped and the DEQ’s decision was supported by the evidence under the MMRA criteria. We áffirm the District Court’s decision regarding collateral estoppel and thus do not address the merits of whether Article IX, Section 2 of the Montana Constitution and the MMRA require land disturbed by the taking of natural resources to be fully reclaimed to its previous condition. We also affirm the District Court’s holding that the criteria under the MMRA were satisfied.

¶5 We address the following issues on appeal:

1. Whether MEIC is precluded from relitigating the issue of whether Article IX, Section 2 of the Montana Constitution requires land disturbed by the taking of natural resources to be fully reclaimed to its previous condition.
2. Whether MEIC is precluded from relitigating the issue of whether the Montana Metal Mine Reclamation Act requires land disturbed by the taking of natural resources to be fully reclaimed to its previous condition.
3. Whether the DEQ made a reasoned decision in selecting the Agency-Modified Alternative under the criteria set forth in the Montana Metal Mine Reclamation Act.

FACTUAL AND PROCEDURAL BACKGROUND

¶6 Golden Sunlight Mines operates an open pit gold mine on the southern edge of the Bull Mountains near Whitehall, Montana. In September 2012, GSM submitted an application to the DEQ to amend the operating permit for its mine, proposing to expand its mining operation to develop a smaller nearby pit that the parties refer to as the North Area Pit. The North Area Pit is estimated to cover approximately 49.4 acres. The expansion would allow GSM to mine an additional 4.2 million tons of gold ore and extend GSM’s current mining operation by about two years. GSM proposed mining the North Area Pit through the use of conventional open pit mining methods which would be consistent with its current mining operation. In order to obtain the gold ore beneath the North Area Pit, GSM proposed excavating below the natural water table and installing external [105]*105dewatering wells adjacent to the North Area Pit to lower the water table beneath the pit and allow for the mineral extraction.

¶7 As part of the proposed expansion, GSM submitted a reclamation plan for the North Area Pit to the DEQ. In 2013, the DEQ issued a draft Environmental Impact Statement (EIS) which discussed the impacts of four alternative reclamation plans for the North Area Pit: (1) the No Action Alternative; (2) the GSM Proposed Reclamation Alternative; (3) the Agency-Modified Alternative; and (4) the North Area Pit Backfill Alternative. The No Action Alternative reflects the current mining operation conducted under GSM’s existing permit with no management plan for an additional disturbance at the North Area Pit. Under the GSM Proposed Reclamation Alternative, the approximately 52.6 million tons of non-ore waste rock that will be generated from the North Area Pit will be primarily placed in an expansion area on the east side of the mine. The GSM Proposed Reclamation Alternative requires GSM to continue to operate its external dewatering wells after closure of the mine to prevent contamination of local groundwater. In addition, GSM must install an underground in-pit sump to protect against local groundwater contamination in the event that one of the external dewatering wells fails. The Agency-Modified Alternative is the same as the GSM Proposed Reclamation Alternative with the exception of various additional modifications developed by the DEQ to further mitigate environmental impacts associated with the mining. These modifications include: (1) the implementation of closure geodetic and ground-movement monitoring for the North Area Pit to ensure safe access and to keep reclamation systems working, and (2) the preparation of a detailed bat and raptor habitat plan for the North Area Pit to provide habitat and add utility to the North Area Pit highwall. Lastly, the fourth proposed reclamation plan identified as the North Area Pit Backfill Alternative requires GSM to use 9.2 million tons of waste rock from the mine to backfill the North Area Pit. Like the GSM Proposed Reclamation Alternative and the Agency-Modified Alternative, the Backfill Alternative requires GSM to continue to operate the external dewatering wells after closure. However, unlike the other alternatives, the Backfill Alternative does not allow for the installation of an in-pit sump to protect against contamination of local groundwater in the event of an external dewatering well failure. In the draft EIS, the DEQ extensively analyzed the advantages and disadvantages associated with these four alternatives and evaluated the alternatives in light of the criteria set forth in the MMRA.

¶8 Following a public hearing and comments, the DEQ issued a final [106]*106EIS identifying the Agency-Modified Alternative as the preferred alternative. In rejecting the Backfill Alternative, the DEQ recognized several benefits associated with the Backfill Alternative, including better structural stability, increased wildlife habitat, and added aesthetic value.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

MEIC v. Montana DEQ
2025 MT 3 (Montana Supreme Court, 2025)
Wangerin v. DOR
2022 MT 236 (Montana Supreme Court, 2022)
Park Co. Environmental v. DEQ
2020 MT 303 (Montana Supreme Court, 2020)
MEIC v. DEQ
2020 MT 288 (Montana Supreme Court, 2020)
State v. Huffine
2018 MT 175 (Montana Supreme Court, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2016 MT 9, 365 P.3d 454, 382 Mont. 102, 2016 Mont. LEXIS 6, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montana-environmental-information-center-v-montana-department-of-mont-2016.