Mechanical Air Engineering Co. v. Totem Construction Co.

801 P.2d 426, 166 Ariz. 191, 34 Ariz. Adv. Rep. 32, 1989 WL 49119, 1989 Ariz. App. LEXIS 129
CourtCourt of Appeals of Arizona
DecidedMay 9, 1989
DocketNo. 1 CA-CIV 9924
StatusPublished
Cited by4 cases

This text of 801 P.2d 426 (Mechanical Air Engineering Co. v. Totem Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arizona primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mechanical Air Engineering Co. v. Totem Construction Co., 801 P.2d 426, 166 Ariz. 191, 34 Ariz. Adv. Rep. 32, 1989 WL 49119, 1989 Ariz. App. LEXIS 129 (Ark. Ct. App. 1989).

Opinion

OPINION

GRANT, Chief Judge.

This appeal raises a question of first impression: whether a liquidated damage provision in a contract is enforceable only upon a showing of actual damages. The appeal is taken from a partial summary judgment on the liquidated damage issue, an arbitration award and an award of attorney’s fees.

FACTS

Totem Construction Company (Totem) was the general contractor on some remodeling and construction at Glendale Commu[192]*192nity College. Mechanical Air Engineering Company (MAECO) was a subcontractor, furnishing labor and materials for heating, ventilating, air conditioning, sheet metal, and plumbing work. The parties agreed in paragraph 19 of their contract to damages in the amount of $350 for each day of MAECO’s delay:

The SUBCONTRACTOR will cooperate with the CONTRACTOR and other SUBCONTRACTORS whose work might interface with the SUBCONTRACTOR’S work and will participate in the coordination of such interface as required, specifically, noting and advising the CONTRACTOR of any interference. The CONTRACTOR, however, will not be liable to the SUBCONTRACTOR for any delays in scheduling the work to be performed by the SUBCONTRACTOR, or any damages arising from such delays. SUBCONTRACTOR and CONTRACTOR agree that if the SUBCONTRACTOR fails to perform within the time specified on the progress schedule posted at the project site, that damages will occur to the CONTRACTOR but that such damages while capable of calculation are not capable of being specifically known at this time. Therefore in lieu of proof of such damages SUBCONTRACTOR and CONTRACTOR agree that a reasonable sum for such damages (and not as a penalty) is the sum of $350.00 per calendar days in excess of the time specifically and that such shall constitute liquidated damages agreed to.

MAECO sued Totem alleging that $16,-000 was owed on its subcontracts and change orders. Totem counterclaimed, alleging that MAECO caused 46 days of delay and seeking $16,100 under the stipulated damage clause.

MAECO moved for summary judgment on the counterclaim, arguing that the damage clause was unenforceable because Totem suffered no actual loss as a result of any delay in completion of construction. In support of its motion, MAECO attached Totem’s response to interrogatories indicating that Totem had been paid the general contract price on the project, $634,198 by Glendale Community College, and that no damages, back charges, or offsets had been assessed against Totem as a result of any construction delays.

Totem filed a cross-motion for summary judgment, arguing that it was immaterial whether it had been assessed any damage under its general contract. MAECO claims that Totem provided no evidence that it had incurred any actual loss as a result of MAECO’s delay or that its actual loss was difficult to prove.

The trial court granted MAECO’s motion for partial summary judgment because Totem failed to show any loss:

THE COURT: Gentlemen, I think that the way I understand the law, the liquidated damage provision is enforceable if there is some showing of damages. I don’t see any.
I’m going to grant the motion of Mae-co and deny the motion of Totem. I am setting it forth on the record on that specific issue. I may be wrong. I think there has to be some showing of some damage to trigger the concept that it would be difficult to assess the value of that damage.

The trial court entered judgment in favor of MAECO for $16,101.63. The trial court also awarded MAECO $10,000 of the $16,-854.50 requested attorney’s fees.

ISSUES
Totem raises two arguments on appeal:
(1) That the liquidated damage clause was enforceable regardless of whether any evidence of actual loss was provided; and
(2) That Totem offered some evidence of actual loss.

LIQUIDATED DAMAGE CLAUSE

We hold that a contract’s liquidated damage clause is enforceable despite no showing of an amount of actual damage. We do so based on general contract principles and law interpreting liquidated damage clauses specifically.

First, it is a general principle of contract law that when parties bind themselves by a [193]*193lawful contract, a court must give effect to that contract as written if the terms are clear and unambiguous. Estes Co. v. Aztec Const., Inc., 139 Ariz. 166, 168, 677 P.2d 939, 941 (App.1983). Paragraph 19 imposes no specific requirement that Totem show actual damages. On the other hand, MAE-CO argues that the clause does not say that no damages whatsoever need be shown.

Even though those specific words are not included, we cannot impose such a requirement on Totem. To require Totem to show an amount of actual damages would be to require Totem to do precisely what the parties agreed Totem need not do. Imposing such a requirement would not give effect to the contract’s clear and unambiguous terms.

Second, we hold that the liquidated damage clause is reasonable even though it contains no requirement that the party enforcing the clause show actual damages.

When a court concludes that a liquidated damage clause is a penalty, it will refuse to enforce the clause as void and against public policy. Instead, it will limit recovery to the actual loss. However, when a court concludes that the clause is for liquidated damages, it will enforce the clause.

This distinction was developed by the courts of equity, which refused to enforce penal bonds. In order to coerce performance, a penal bond required the promisor to pay a stipulated amount upon breach. Later courts concluded that when actual loss could not be easily calculated, a liquidated damage clause was a valid alternative. See generally Comment, Liquidated Damages: A Comparison of the Common Law and the Uniform Commercial Code, 45 Ford-ham L.Rev. 1349, 1349-50 (1977). A liquidated damage clause serves a useful purpose when it would be difficult to prove the amount of loss with the degree of certainty required by law. 5 Corbin on Contracts § 1062 at 357-58, 361. A liquidated damage clause promotes enterprise by increasing certainty and by decreasing risk-exposure, proof problems, and litigation costs. See D. Dobbs, Law of Remedies § 12.5 at 823 (1973).

If a liquidated damage clause meets the following two conditions, Arizona courts will conclude that the clause is not a penalty and will enforce it:

(1) The liquidated amount must be a reasonable forecast of just compensation for the harm caused by a breach; and
(2) The harm caused by a breach must be one that is incapable or very difficult to accurately estimate.

Larson-Hegstrom & Associates, Inc. v. Jeffries, 145 Ariz. 329, 333, 701 P.2d 587, 591 (App.1985) (citing Restatement (Second) of Contracts § 356 and Restatement of Contracts § 339). Arizona courts have not analyzed whether a liquidated damage clause is reasonable when there is no proof of an actual loss.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Dobson Bay Club II DD, LLC v. La Sonrisa De Siena, LLC
366 P.3d 1022 (Court of Appeals of Arizona, 2016)
BMW of North America, LLC v. Mini Works, LLC
166 F. Supp. 3d 976 (D. Arizona, 2010)
In Re Vantage Investments, Inc.
328 B.R. 137 (W.D. Missouri, 2005)
MECHANICAL AIR ENGINEER. v. Totem Const.
801 P.2d 426 (Court of Appeals of Arizona, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
801 P.2d 426, 166 Ariz. 191, 34 Ariz. Adv. Rep. 32, 1989 WL 49119, 1989 Ariz. App. LEXIS 129, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mechanical-air-engineering-co-v-totem-construction-co-arizctapp-1989.