Mears Park Holding Corp. v. Morse/Diesel, Inc.

426 N.W.2d 214, 1988 Minn. App. LEXIS 596, 1988 WL 61163
CourtCourt of Appeals of Minnesota
DecidedJune 21, 1988
DocketC3-88-88
StatusPublished
Cited by3 cases

This text of 426 N.W.2d 214 (Mears Park Holding Corp. v. Morse/Diesel, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mears Park Holding Corp. v. Morse/Diesel, Inc., 426 N.W.2d 214, 1988 Minn. App. LEXIS 596, 1988 WL 61163 (Mich. Ct. App. 1988).

Opinion

OPINION

HAROLD W. SCHULTZ, Acting Judge.

Appellants Mears Park Holding Corporation and Chemical Bank appeal from a judgment entered pursuant to Minn.R.Civ. P. 54.02 in Ramsey County District Court on a trial court’s order granting respondent Morse/Diesel $29,663.10 in attorney fees and costs. Appellants allege that the court erred in imposing attorney fees pursuant to Minn.Stat. § 549.21 (1986) and Minn.R.Civ. P. 11, and that the court erred in finding they maintained a position unfounded in fact and law for the purpose of delaying the ordinary course of the proceedings.

FACTS

Mears Park Development Company (Development) was the developer and part owner of the Galtier Plaza Construction *216 project in downtown St. Paul. Respondent Morse/Diesel was construction manager of the project, and entered into a standard form AIA construction management (CM) contract with Development in 1982. The CM contract contained an arbitration clause which provided:

All claims, disputes and other matters in question between the parties to this Agreement arising out of or relating to this Agreement or the breach thereof may, at the election of either party, be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association then obtaining, but only if such claims, disputes or other matters have not been resolved pursuant to the procedures set forth in Sections 16.19.2(a) and (b) hereof.

The contract also contained a clause binding each of the parties, their successors and assigns to all the covenants of the contract.

On March 16, 1987, Development brought an action in state court against respondent and two other contractors involved in the project claiming, in part, breach of contract, negligence and breach of fiduciary duty. Two weeks later, on March 30, Development terminated respondent as construction manager of the project. The next day, Development assigned its interests in the project to appellant Mears Park Holding Corporation, a wholly-owned subsidiary of appellant Chemical Bank, the project lender.

The state court action was removed to federal district court on April 8, 1987, and on April 10, respondent served a demand for arbitration on appellants to resolve claims respondent had asserted for $250,-000. On April 15, respondent brought a motion to stay the federal action pending arbitration pursuant to the Federal Arbitration Act.

A hearing was held on the motion in federal district court on June 10, 1987. That same day, appellants served respondent with a summons and complaint in Ramsey County District Court, the action at the heart of the present appeal. The claims asserted by appellants in this action were essentially the same as those asserted by Development in the federal action.

The federal district court issued its decision on June 17, 1987, which denied appellants’ motion to remand the case to state court and stayed all further proceedings pending arbitration of the matter. Appellant Chemical Bank appealed this decision to the Eighth Circuit Court of Appeals, but withdrew the appeal when respondent later filed a motion for attorney fees in the state action.

Respondent then brought a motion to stay appellants’ state court action, commenced June 10, pending arbitration. That motion was heard August 5, 1987, in Ramsey County District Court. The trial court granted respondent’s motion, and confirmed its ruling from the bench with an Order and Consolidated Memorandum dated August 20, 1987. The Memorandum included the following findings:

All of the Contracts contained an arbitration clause providing in clear and unmistakable language that all claims and disputes and other matters arising out of the Contracts were to be decided by arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association. All of the Contracts also contained clear and unmistakable language binding each of the parties and their successors and assigns to all of the covenants of the Contracts, and no Contract was to be assigned without the written consent of the other party. These two provisions of the Contracts frame the issues raised by the moving defendants in their motions.

The trial court found the claims in the federal action and the state action “virtually identical,” and concluded “the lawsuit started in this Court was designed to circumvent any ruling of [the federal district judge] which might be adverse to the Mears Park interests.”

On September 23, 1987, respondent brought a motion for an order compelling the payment of attorney fees under Minn. Stat. § 549.21 (1986) and Minn.R.Civ.P. 11. The trial court awarded respondent $29,- *217 663.10 for fees it incurred in the state action. In its order and memorandum filed October 29, 1987, the court stated the decision to commence a second lawsuit against Morse/Diesel and to argue arbitration was not required was

frivolous and carried on for the sole purpose of avoiding the arbitration which the Federal court had already ordered. There was no merit to its position in Federal court and having lost there, there was even less reason to assert the same position in this court. Vigorous and zealous advocacy cannot disguise an unfounded position.

The court also determined appellants’ efforts were “unfounded in fact and in law” and were “asserted for the purpose of delaying the ordinary course of the proceedings.” Final judgment was entered January 6, 1988, and this appeal followed.

ISSUE

Did the trial court abuse its discretion in compelling appellants to pay $29,663.10 in attorney fees under Minn.Stat. § 549.21 (1986) and Minn.R.Civ.P. 11?

ANALYSIS

I. Standard of review

The trial court awarded respondent attorney fees and costs under Minn. Stat. § 549.21 (1986) providing reimbursement for certain costs in civil actions, and Minn.R.Civ.P. 11, authorizing sanctions in connection with the signing of pleadings, motions and other papers. Section 549.21 provides that upon the motion of a party,

the court in its discretion may award to that party costs, disbursements, reasonable attorney fees * * * if the [opposing] party * * * acted in bad faith; asserted a claim or defense that is frivolous and that is costly to the other party; asserted an unfounded position solely to delay the ordinary course of the proceedings or to harass; or committed a fraud upon the court.

Minn.Stat. § 549.21, subd. 2 (1986) (emphasis added). Case law has clearly delineated an abuse of discretion standard of review for cases falling under this provision of the statute. See Blattner v. Forster, 322 N.W.2d 319, 321 (Minn.1982); National Recruiters, Inc. v. Toro Co., 343 N.W.2d 704, 709 (Minn.Ct.App.1984). There is, however, no established standard of review for Rule 11 cases in Minnesota.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
426 N.W.2d 214, 1988 Minn. App. LEXIS 596, 1988 WL 61163, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mears-park-holding-corp-v-morsediesel-inc-minnctapp-1988.