McWilliams v. Drainage Dist. No. 19

224 S.W. 35, 204 Mo. App. 237
CourtMissouri Court of Appeals
DecidedJune 5, 1920
StatusPublished
Cited by4 cases

This text of 224 S.W. 35 (McWilliams v. Drainage Dist. No. 19) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McWilliams v. Drainage Dist. No. 19, 224 S.W. 35, 204 Mo. App. 237 (Mo. Ct. App. 1920).

Opinion

TRIMBLE, J.

Defendant is a Drainage District organized December 5, 1910, under the provisions of article 4, chapter 41, Revised Statutes 1909. By section 5583 thereof, it is a municipal corporation capable of suing and being sued; and under said article certain county officials are ex-officio officers of said District. Plaintiff is the contractor who, under a contract with said Drainage District, excavated the drainage ditch therein and built the bridges and farm crossings required thereby, and this suit is for the unpaid balance of the price named in the contract, said unpaid' balance being the sum of $3226.69, and for which a general judgment against the District is asked. There is no controversy over the fact that the work was performed by plaintiff in accordance with the contract, nor is it disputed that plaintiff has not been paid the above named amount nor that the aggregate of the sums paid the contractor lacks that amount in order to equal the price specified in the written contract. The failure of the District to pay the balance of the contract price grows out of the fact that after taking out of the' total amount of money raised by the District for all purposes' the sum awarded as damages to the landowners and the sum expended for costs' of location, attorneys fees, etc., the amount left to pay for construction of the improvement specified in plaintiff’s contract is insufficient to pay the contract price to the extent of said unpaid balance. It is the contention of defendant that the contract was *239 illegal for reasons which will be hereinafter stated; that all of the funds provided for to pay for everything in the way of expense connected with the origination and establishment of the District and the drainage contemplated thereby, have been exhausted; that no additional funds can be raised by the District to pay such unpaid balance; and that by an oral agreement made after the contract had been entered into, the plaintiff agreed; to do the work of construction for whatever sum was left on hand for that purpose. The reply! denied this and objection was made to the introduction of any evidence to that effect, on the ground thait such was an attempt to vary the terms of a written contract by parol proof and that too -without any consideration to support it.

The ease was tried before the court withput a jury, and judgment went in favor of the defendant. The plaintiff appealed.

Upon reaching this court it was found that defendant in its answer had apparently raised a constitutional question by invoking certain specified sections of the Constitutions of the United States and of the State of Missouri; and plaintiff asserted that if a constitutional question was involved, jurisdiction to hear the appeal was in the Supreme Court. The matter being left thus by the parties to the cause, and this court realizing that if there were) any doubt in regard to the -matter the question should be determined by the Supreme Court, the case was transferred there. That court decided against the proposition that jurisdiction was with it and returned the case to this court, where it was argued and submitted at the last April Call.

The first question which should be disposed of is whether the contract was illegal, that is to say whether, at the time it was made, it was void because the District had no power to malee it. If it was,' then plaintiff’s case is disposed of at once since in that event his cause of action is without contractual foundation. If we understand defendant’s contention,- it is not based upon any claim of invalidity in the steps taken to authorize *240 the contract, nor that the subject-matter or object to be accomplished is not perfectly legitimate and within the power of the parties to contract about. To obtain a clear perception of wherein its alleged invalidity is claimed to consist, it may be well to state some of the statutory provisions governing the making of such a contract and what was done in this case thereunder.

The ditch and drainage system involved herein is located in two counties, Caldwell and Livingston, and the project was instituted, organized and carried out under the provisions of sections 5608', 5609 and 5610 and other sections of the above mentioned chapter. Under the provisions of these various sections it will be observed that up to á certain point the proceedings are carried along simultaneously, in each county as if there were but one District. Under section 5Í608' the county court of each county, upon reception of its petition for the ditch, appoints a] preliminary viewer and they meet and appoint an engineer to assist them and view the line, of the entire proposed ditch and report to each county court whether the improvement is necessary or will be conducive to the public health, convenience or welfare, and' also the best route for the ditch’; they also examine and report what lands will be benefitted in each county and the relative degree of such benefit, and the estimated proportion of the work which shall be charged to each county. Under section 5600 if the several courts find in favor of making the improvements (as was done; in this case) each court appoints two additional viewers who, with the first viewer and an engineer, proceed to stake out, estimate and apportion that part of the ditch apportioned to each county as if the ditch were located wholly within that county. The engineer selected by these viewers has charge of the construction of the entire ditch and is paid' by each county in proportion to the work charged to each. And the proceedings necessary to the construction' of said work are had in the same manner as if such ditch was located wholly in said county. That is to say, as We *241 understand it, after the work of these last named viewers has been done and their reports have been approved, the proceedings necessary to' the construction of the work are conducted in each county separately, and separate contracts for the work in each county áre made fori that portion of the ditch therein, as if the whole ditch were in said county. ■ The contract involved in this suit has to do solely with the construction of the ditch in Caldwell county, and the fact that the drainage system lies in two counties has no material bearing on the case and need not be stated were it not necessary in order to make clear how it happens that" the estimates hereinafter referred to were made as they were, and also to settle an apparent disagreement between counsel as to what the record show;s as to certain claimed unapportioned benefits.

Under said section 5608 the viewers estimated the propórtion of the work to be charged, to the lands in each county and in their reports fixed the number of acres in Caldwell county to be included in that district at 1978, and the number of acres in Livingston county to be included in that district at 1340' making total number of acres in the two districts amount to 3318. The viewers apportioned 63 per cent, of the< entire cost to the lands in Caldwell county and 37 per. cent, of the cost to the lands in Livingston county. As both of the county courts found in favor of making the improvement, viewers were appointed under section 5609' and ■in their report they specified the same number of acres and apportioned to the lands in each county the. same proportion of the cost, namely, 63 and 37 per cent, respectively.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McFaw Land Co. v. Kansas City Title & Trust Co.
211 S.W.2d 44 (Supreme Court of Missouri, 1948)
Senseney v. Landay Real Estate Co.
131 S.W.2d 595 (Supreme Court of Missouri, 1939)
McCaw v. O'Malley
249 S.W. 41 (Supreme Court of Missouri, 1923)
Bates County v. Wills
269 F. 734 (Eighth Circuit, 1920)

Cite This Page — Counsel Stack

Bluebook (online)
224 S.W. 35, 204 Mo. App. 237, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcwilliams-v-drainage-dist-no-19-moctapp-1920.