McPherson v. Longview United Pentecostal Church, Inc.

540 S.W.2d 424, 90 A.L.R. 3d 329, 19 U.C.C. Rep. Serv. (West) 1366, 1976 Tex. App. LEXIS 3004
CourtCourt of Appeals of Texas
DecidedJuly 15, 1976
Docket898
StatusPublished
Cited by10 cases

This text of 540 S.W.2d 424 (McPherson v. Longview United Pentecostal Church, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McPherson v. Longview United Pentecostal Church, Inc., 540 S.W.2d 424, 90 A.L.R. 3d 329, 19 U.C.C. Rep. Serv. (West) 1366, 1976 Tex. App. LEXIS 3004 (Tex. Ct. App. 1976).

Opinion

McKAY, Justice.

This suit was brought by appellee, The Longview United Pentecostal Church, against the building contractor, A. B. McPherson, now deceased, on a contract for the construction of a church building and parking lot for appellee. Annie Lou McPherson, Independant Executrix of the Estate of A. B. McPherson, was substituted as a party. Appellant answered that appel-lee had abandoned the plans and specifications and made many changes, and that appellee took possession and occupied the building to the exclusion of appellant and in so doing waived any claim that the building was not constructed according to the plans and specifications. Appellant also filed a cross-action seeking $21,809.85 for the extras for changes and additions in materials and equipment requested by appellee, for judgment on a deed of trust note executed by appellee in the sum of $138,000 together with interest and attorney’s fee and for damages for failure to pay for the extras.

Trial was before a jury, and the trial court, after disregarding issue 15, rendered judgment that appellant recover $12,715.86 with interest from February 18, 1972 to May 2, 1975, at 6% per annum, and $2,451.87 for extra work and materials, making total recovery of $15,167.73. The principal amount of the note had been paid during the pendency of the suit on April 19, 1973.

Appellee (church) alleged that in July, 1971, it entered into a contract with McPherson by which he agreed to construct a certain church building and appurtenances thereto in Longview in accordance with plans and specifications prepared by an architect, and that the church agreed to pay McPherson the sum of $138,000.00 upon completion and acceptance of the improvements by the church. The church further alleged (1) that McPherson agreed to obtain and pay for the interim financing; (2) that the church had obtained a commitment for permanent financing; and (3) that as an accommodation to McPherson and in order to aid him to obtain interim financing, the church executed and delivered to McPherson its promissory note payable on or before 180 days, in the amount of $138,000.00 together with a deed of trust on the property on which such church was to be built. The pleadings of the church further alleged that McPherson failed and refused to construct a parking lot as required by the contract until after the church employed an attorney. McPherson finally completed the parking lot in July, 1972, but he failed and refused to pay the cost of materials used therein. The church also plead that McPherson failed and refused to pay the cost of pews *426 which had been installed and for which demand had been made by the supplier of the pews. Allegations were also made that there were various items of poor workmanship by McPherson and that he failed to complete work on the building. It was also alleged there were extra items of work and materials furnished by McPherson which needed adjusting.

Appellee church also alleged that unreasonable demands had been made by McPherson and the First State Bank of Gladewater for payment of the $138,000.00 note as well as interest and attorney’s fee. The church prayed that the date of substantial completion of the contract be determined, that it be relieved of any obligation to pay interest before substantial completion and that it be relieved of any obligation to pay attorney’s fees.

Appellant’s answer and cross-action alleged that the church, in consideration of McPherson’s oral agreement to construct improvements according to plans and specifications, on August 23, 1973, executed and delivered to appellant its promissory note for $138,000.00, payable on or before 180 days from date. Appellant asserted the note was unpaid except for the principal sum of $138,000.00 paid April 19,1973, leaving unpaid principal, interest and attorney’s fees of $31,510.00. Appellant also alleged that the church took possession of the building without the consent of McPherson. Appellant described in some detail the changes and extras in the building which were not a part of the original contract, prayed for recovery of $21,809.85 as the reasonable net value of extras furnished, and asked for $3,000.00 as damages for failure to pay for extras. Appellant also sought the $31,-510.00 allegedly due on the note as of April 19, 1973, and for interest and attorney’s fees after that date. Appellant did not claim any interest on the note from date to maturity.

The trial was before a jury and the verdict was substantially as follows:

1.Several items of materials and labor were found to be extras not contemplated by the contract.

2. Found the reasonable value of the itemized extras.

3. Reasonable value of supervision, overhead and profit for contractor on work done by McPherson in making changes and alterations in the church building was 10%.

4. The date that appellee church accepted the building as complete was February 18, 1972.

5. The jury failed to find that the church took over possession of the building after the contractor told them not to do so.

6. McPherson substantially completed his construction contract with the church in July, 1972.

7. The jury failed to find that McPherson was prevented from completing the contract by February 19, 1972, by the conduct of the church.

8. McPherson had not completed the contract on March 17, 1972.

9. The note bearing date of August 23, 1971, was executed by the church to McPherson to enable him to secure interim financing from the First State Bank of Gladewater.

10. First State Bank of Gladewater, on or about March 17, 1972, was the owner of the note dated August 23, 1971, and the deed of trust lien given to secure payment of such note.

11. The provision in the note dated August 23, 1971, executed by the church payable to McPherson providing for interest from date of execution to maturity at the rate of 7½% per annum was contrary to the terms of the contract whereby McPherson agreed to furnish his own interim financing.

12. On March 17, 1972, the permanent financing the church had arranged for through First Federal Savings and Loan Association could not be secured because the contract of July 22, 1971, had not been completed.

13. The payment of the sum of $138,-000.00 was made as soon as practical after an agreement was entered into that the *427 matter of extras under the contract, interest and attorney’s fees would be determined by the lawsuit.

14. The jury failed to find that appellant is entitled to recover any attorney’s fees.

15. Appellant is entitled to recover reasonable interest of $3,700.00.

Appellant filed a motion to disregard the findings of the jury and the answers to issues 5 through 15. The trial court disregarded issue 15 only and otherwise overruled appellant’s motion and rendered judgment for appellant as above mentioned.

Appellant’s first point maintains that the judgment of the trial court should be reversed because the court denied appellant’s motion for judgment on the promissory note executed by appellee church. We sustain this point.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenkins v. Karlton
620 A.2d 894 (Court of Appeals of Maryland, 1993)
First National Bank of Amarillo v. Jarnigan
794 S.W.2d 54 (Court of Appeals of Texas, 1990)
Cooper v. Supercinski
700 S.W.2d 239 (Court of Appeals of Texas, 1985)
Federal Deposit Ins. Corp. v. Borne
599 F. Supp. 891 (E.D. New York, 1984)
Ketchian v. Concannon
435 So. 2d 394 (District Court of Appeal of Florida, 1983)
Labar v. Cox
635 S.W.2d 801 (Court of Appeals of Texas, 1982)
Brames v. Crates
399 N.E.2d 437 (Indiana Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
540 S.W.2d 424, 90 A.L.R. 3d 329, 19 U.C.C. Rep. Serv. (West) 1366, 1976 Tex. App. LEXIS 3004, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcpherson-v-longview-united-pentecostal-church-inc-texapp-1976.