MCM Home Builders, L.L.C. v. Sheehan

2019 Ohio 3899
CourtOhio Court of Appeals
DecidedSeptember 25, 2019
Docket18 CAE 09 0074
StatusPublished
Cited by6 cases

This text of 2019 Ohio 3899 (MCM Home Builders, L.L.C. v. Sheehan) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCM Home Builders, L.L.C. v. Sheehan, 2019 Ohio 3899 (Ohio Ct. App. 2019).

Opinion

[Cite as MCM Home Builders, L.L.C. v. Sheehan, 2019-Ohio-3899.]

COURT OF APPEALS DELAWARE COUNTY, OHIO FIFTH APPELLATE DISTRICT

MCM HOME BUILDERS, LLC : JUDGES: : : Hon. W. Scott Gwin, P.J. Plaintiff-Appellee : Hon. John W. Wise, J. : Hon. Patricia A. Delaney, J. -vs- : : Case No. 18 CAE 09 0074 : MARK R. SHEEHAN, ET AL. : : : Defendants-Appellants : OPINION

CHARACTER OF PROCEEDING: Appeal from the Delaware County Court of Common Pleas, Case No. 16CVH-01- 67

JUDGMENT: AFFIRMED

DATE OF JUDGMENT ENTRY: September 25, 2019

APPEARANCES:

For Plaintiff-Appellee: For Defendants-Appellants:

RICHARD T. RICKETTS DAVID A. GOLDSTEIN ANDREW C. CLARK 511 South High St., Suite 200 50 Hill Road South Columbus, OH 43215 Pickerington, OH 43147 Delaware County, Case No. 18CAE-09-07 2

Delaney, J.

{¶1} Defendants-Appellants Mark R. Sheehan, Co-Trustee of the 9238 Deer

Path Court Trust dated August 31, 2013 and Tammy M. Johnson, Co-Trustee of the 9238

Deer Path Court Trust dated August 31, 2013 appeal the February 1, 2018 jury verdict

and September 6, 2018 judgment entry of the Delaware County Court of Common Pleas.

FACTS AND PROCEDURAL HISTORY

The Cost-Plus Contract

{¶2} On August 31, 2013, Defendants-Appellants Mark R. Sheehan, Co-Trustee

of the 9238 Deer Path Court Trust dated August 31, 2013 and Tammy M. Johnson (aka

Tammy Sheehan), Co-Trustee of the 9238 Deer Path Court Trust dated August 31, 2013

entered into a contract with Plaintiff-Appellee MCM Home Builders, LLC for the

construction of a 4988 square foot home located in Powell, Ohio. MCM, wholly owned

and operated by Marc Moldovan, was the general contractor, and construction on the

home was to be completed by subcontractors. An attorney reviewed the construction

contract on behalf of the Sheehans prior to entering the contract. At the time of the

contract, the Sheehans were executives at Huntington National Bank.

{¶3} The parties set the budget for the home construction at $499,235.00. The

construction contract was known as a “cost-plus contract” wherein the payment terms of

the contract stated as follows:

In consideration of the performance of the Contract, the Buyer agrees to

pay the Builder a Ten Percent (10%) Builder fee based upon the Budget for

the Project of $499,235.00. Draws will be paid to Builder as determined by

the Buyer’s Lender. Buyer and Builder shall cooperate in delivering any Delaware County, Case No. 18CAE-09-07 3

document reasonably required by the Buyer’s Lender in order to receive

draws. If permitted by Buyer’s Lender, each draw shall include a 10% fee

for the Builder.

{¶4} In a fixed fee contract, the builder provides the house plans to the customer.

The customer usually has limited choices between the levels of finishes, but the total price

of the construction is fixed. Within the fixed price of the home construction, the builder

has included his or her profit margin. If the customer desires to make a change during

construction, the customer would complete a change order for which the customer would

immediately pay for any overage outside of the fixed price. In a cost-plus contract,

typically used in custom-built homes, the builder takes the house plans, bids out each

phase of the construction, and establishes a construction budget dependent on the totality

of the bids. Allowances are put in place for the selection features in each phase. The

vendor invoices come directly to the builder. A cost-plus contract allows the customer

flexibility to change plans during construction. If the customer makes a change that comes

under the budget for that phase, the customer receives a credit. If the customer makes a

change that goes over budget for that phase, the customer is responsible for the overage.

At the end of construction, the builder determines the costs of construction guided by the

original budget and then charges a 10% builder’s fee.

{¶5} In the parties’ cost-plus contract, MCM’s responsibilities as Builder were

stated as follows:

Builder's Services

2.1 Services. The Builder will perform the following services under this

Agreement in each of the two phases described below: Delaware County, Case No. 18CAE-09-07 4

(a) Design Phase.

***

(iii) Project Construction Budget. Prepare a Project budget as soon as major

Project requirements have been identified, and update periodically for the

Buyer's approval. Prepare an estimate based on Construction Drawings for

approval by the Buyer as the Project Construction Budget. Update and

refine this estimate for the Buyer's approval as the development of the

Drawings and Specifications proceeds, and advise the Buyer and the

Architect/Engineer if it appears that the Project Construction Budget will not

be met and make recommendations for corrective action;

(b) Construction Phase.

(ii) Cost Control. Develop and monitor an effective system of Project cost

control and negotiate the best price possible for the Buyer. Revise and

refine the initially approved Project Construction Budget, incorporate

approved changes as they occur, and develop cash flow reports and

forecasts as needed. Identify variances between actual and budgeted or

estimated costs and advise Buyer and Architect/Engineer whenever

projected cost exceeds budgets or estimates. Maintain cost accounting

records on authorized Work performed under unit costs, actual costs for

labor and material, or other bases requiring accounting records. Delaware County, Case No. 18CAE-09-07 5

(iii) Workmanlike Manner. All work shall be performed in a Workmanlike

Manner, conforming to the standards set forth by the Ohio Home Builders

Association and published on their website.

{¶6} The cost-plus contract included terms as to the Builder’s Fee:

EXCESS COSTS

IF AT ANY TIME A HOME CONSTRUCTION SERVICE REQUIRES

EXTRA COSTS ABOVE THE COST SPECIFIED OR ESTIMATED IN THE

CONTRACT THAT WERE REASONABLY UNFORESEEN, BUT

NECESSARY, AND THE TOTAL OF ALL EXTRA COSTS TO DATE

EXCEED FIVE THOUSAND DOLLARS OVER THE COURSE OF THE

ENTIRE HOME CONSTRUCTION CONTRACT, YOU HAVE THE RIGHT

TO AN ESTIMATE OF THOSE EXCESS COSTS BEFORE THE HOME

CONSTRUCTION SERVICE SUPPLIER BEGINS WORK RELATED TO

THOSE COSTS.

The estimated additional costs shall be set forth in writing and shall require

the written agreement of all affected parties. In the event that they Buyer

does not consent to the excess costs, either Buyer or Builder shall have the

right to terminate the Contract upon 10 days written notice to the other. In

the event of such termination, the Buyer shall pay the Builder for all work

performed to that point, however, Buyer shall not owe for any Non-

Conforming Work as defined above, Builder’s profit and/or overhead for Delaware County, Case No. 18CAE-09-07 6

work not performed or related to Non-Conforming Work, or work yet to be

performed. This amount shall be liquidated damages. * * *

{¶7} In case of termination, the cost-plus contract provided as follows:

10.2 Buyer’s Right to Perform Builder’s Obligations and Termination by the

Buyer for Cause. If the Builder fails to perform any of his obligations under

this Agreement, the Buyer may, after seven (7) days’ written notice during

which periods the Builder fails to perform such obligation, make good such

deficiencies and terminate this contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Waldock v. Waldock Invest. Co.
2025 Ohio 872 (Ohio Court of Appeals, 2025)
Clark v. Clark
2025 Ohio 159 (Ohio Court of Appeals, 2025)
Eichenberger v. McCown
2024 Ohio 6033 (Ohio Court of Appeals, 2024)
Kerbler v. Biltwell Contrs., L.L.C.
2024 Ohio 5607 (Ohio Court of Appeals, 2024)
State v. Acker
2023 Ohio 2085 (Ohio Court of Appeals, 2023)
State v. Fliger
2020 Ohio 753 (Ohio Court of Appeals, 2020)

Cite This Page — Counsel Stack

Bluebook (online)
2019 Ohio 3899, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcm-home-builders-llc-v-sheehan-ohioctapp-2019.