McLemore v. Hyundai Motor Manufacturing Alabama, LLC

7 So. 3d 318, 2008 Ala. LEXIS 211, 2008 WL 4531796
CourtSupreme Court of Alabama
DecidedOctober 10, 2008
Docket1070516 and 1070517
StatusPublished
Cited by18 cases

This text of 7 So. 3d 318 (McLemore v. Hyundai Motor Manufacturing Alabama, LLC) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLemore v. Hyundai Motor Manufacturing Alabama, LLC, 7 So. 3d 318, 2008 Ala. LEXIS 211, 2008 WL 4531796 (Ala. 2008).

Opinions

STUART, Justice.

George E. Russell and Thomas E. Russell, as coexecutors and cotrustees of the will and testamentary trust of Earnest W. Russell, and Myrtis Russell (“the Rus-sells”), and Price McLemore, Mary H. McLemore, John Mclnnis, Jr., Timothy N. Mclnnis, Charles R. Mclnnis, Williams S. Newell, and the Peoples Bank and Trust Company, as trustee for the Adaline Hooper Trust A and B (“the McLemore group”), sued the Industrial Development Board of the City of Montgomery (“the IDB”) and Hyundai Motor Manufacturing Alabama, LLC (“Hyundai”), alleging breach of contract. Specifically, they alleged that the IDB, on behalf of Hyundai, exercised options to purchase their real property but failed to pay them in accordance with the most-favored-nation clause in the option agreements the same price per acre that was paid to another landowner. The trial court entered summary judgments for the IDB and Hyundai. We affirm in part, reverse in part, and remand.

[322]*322 Facts

In September 2001, various officials of the State of Alabama, the City of Montgomery (“the City”), the Montgomery County Commission (“the County”), the Montgomery Area Chamber of Commerce, and the Montgomery Water Works Board began making preparations to secure options to purchase property in the Montgomery area to create an incentive package in the hope that they could persuade Hyundai to build an industrial plant in the Montgomery area for the purpose of manufacturing and assembling motor vehicles. This intent is evidenced by a signed letter to Hyundai from the City, the County, and the IDB stating that they, “in partnership with the State,” would commit to providing an industrial site to Hyundai at no cost. Although the funds to purchase the property were to be provided by the City and the County only, the option agreements on the property were acquired by the IDB, whose primary role in industrial projects is to “serve as the entity through which monies flow for the purchase of land for the ultimate use in industry.” 1 B.M. Ahn, the Hyundai representative in charge of Hyundai’s project to open a plant in the United States, testified during his deposition that one of the basic elements of an incentive package is “free land” offered to an automobile company as part of the incentive for the company to locate in a certain area. Ahn stated that Hyundai had no role in acquiring the options on the land.

The Russells owned approximately 328 acres of land in Montgomery County. In the fall of 2001, Reuben Thornton, the chairman of the IDB, entered into an option agreement on behalf of the IDB to purchase the Russells’ property for an industrial project.2 The agreement provided an option period of 120 days and stated:

“3. If Purchaser elects to exercise this Option the purchase price for the Property shall be determined as follows:
“Seller and Purchaser shall each, at its own cost and expense, secure a current appraisal of the Property. The purchase price shall be the average of the two appraisals provided, however, in no event shall the purchase price be less than $4,500 per acre and further provided that the purchase price shall in no event be less than the price per acre paid to any other landowner included in the project planned for the Property. The acreage shall be determined by a good and accurate survey provided by Purchaser.[3]
[[Image here]]
“16. This Option constitutes the entire and complete agreement between the parties hereto and supersedes any prior oral or written agreements between the parties with respect to the Property. It is expressly agreed that there are no verbal understandings or agreements which in any way change the terms, covenants, and conditions herein set forth, and that no modification of this Option and no waiver of any of its terms and conditions shall be effective unless made in writing and duly executed by the parties hereto.”

[323]*323The Russells and the IDB amended the option agreement in February 2002 to provide:

“1. It is hereby agreed that the purchase price for the Property is Four Thousand Five Hundred and No/100 Dollars ($4,500.00) per acre. The exact number of acres to be determined by the survey provided by Purchaser.
“2. The option period is hereby extended for a period of 120 days from the Effective Date of the Option, which Effective Date is October 3, 2001. The expiration date of the Option, as extended, is now May 31, 2002.
“3. Except as amended hereby, the Option is in all other respects ratified and confirmed.”

In February 2002, Thornton, on behalf of the IDB, entered into an option agreement with the McLemore group, who owned approximately 54 acres of land near the Russell property. The terms in the option agreement with the McLemore group are identical to the terms in the original option agreement between the Russells and the IDB.

The IDB also acquired four additional option agreements with landowners near the property belonging to the Russells and the McLemore group. During the acquisition process, the IDB approached Joy Shelton about an option to purchase her property; however, she refused to enter into an option agreement. The IDB decided that the Shelton property4 was not necessary for the incentive package. By mid-March 2002, the IDB determined that it was not going to designate any additional funds, other than the funds already committed, to this particular project. The State and the IDB sent the incentive package, including the proposed project site, to Hyundai for consideration.

On March 28, 2002, Ahn contacted Todd Strange, then the director of the Alabama Development Office. He stated that Hyundai had not decided whether to locate the plant in Montgomery or in Kentucky but that additional property would need to be acquired for the rail access Hyundai required if Montgomery was to be selected as the site for the Hyundai plant. Ahn informed Strange that he would need an answer by noon of the next day as to whether the property could be acquired. Strange met with various State, City, and County officials to discuss Hyundai’s request. Recognizing that the City and the County would not provide additional funds to acquire more property and that the other option agreements contained most-favored-nation clauses, they decided to ask CSX Transportation, Inc., the rail company, to acquire the option to purchase the Shelton property. On March 29, 2002, Strange sent David Hemphill, an assistant vice president for CSX, the following letter via facsimile:

“Last evening, Thursday, March 28, 2002, at 6:05 p.m. Central Standard Time, I received a call from Mr. B.M. Ahn, President Hyundai Motor Company, U.S. from Seoul, Korea. He told me they were in the final stages of the decision and needed to make modifications to their Montgomery site layout because the CSX Railroad yard estimate had come in extremely high. In their (Hyundai’s) redesign, he wanted to do parallel tracks running north and south on the eastern side of the property boundary. His engineers told him he would not have enough room unless [additional property was] obtained in the [324]*324southeast corner of the quadrant. This property had been discussed a couple of months ago but we had been told as recently as two weeks ago that it would not be necessary.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Merida v. Olin Corporation
S.D. Alabama, 2023
O'Shea v. OMi Holdings Inc
N.D. Alabama, 2021
Sloan v. Cunningham
S.D. Alabama, 2017
Doug's Coin & Jewelry, Inc. v. America's Value Channel, Inc.
623 F. App'x 520 (Eleventh Circuit, 2015)
SE Property Holdings, LLC v. Sandy Creek II, LLC
954 F. Supp. 2d 1322 (S.D. Alabama, 2013)
Industrial Development Board v. Russell
124 So. 3d 127 (Supreme Court of Alabama, 2013)
Perdue ex rel. Perdue v. Green
127 So. 3d 343 (Supreme Court of Alabama, 2012)
Von Sury v. Kuehn
51 So. 3d 311 (Supreme Court of Alabama, 2010)
North River Insurance Co. v. Overton
59 So. 3d 1 (Supreme Court of Alabama, 2010)
Ex Parte Indus. Dev. Bd. of Montgomery
42 So. 3d 699 (Supreme Court of Alabama, 2010)
Russell v. Industrial Development Board of Montgomery
42 So. 3d 699 (Supreme Court of Alabama, 2010)
Odom v. Southeast Supply Header, LLC
675 F. Supp. 2d 1105 (S.D. Alabama, 2010)
Wheeler v. George
39 So. 3d 1061 (Supreme Court of Alabama, 2009)
McLemore v. Hyundai Motor Manufacturing Alabama, LLC
7 So. 3d 318 (Supreme Court of Alabama, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
7 So. 3d 318, 2008 Ala. LEXIS 211, 2008 WL 4531796, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclemore-v-hyundai-motor-manufacturing-alabama-llc-ala-2008.