This text of 2005 Ohio 4940 (McLeland v. First Energy, Unpublished Decision (9-21-2005)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLeland v. First Energy, Unpublished Decision (9-21-2005), 2005 Ohio 4940 (Ohio Ct. App. 2005).

Opinion

DECISION AND JOURNAL ENTRY
{¶ 1} Plaintiff-Appellant Joseph C. McLeland has appealed from the judgment of the Summit County Court of Common Pleas that granted Defendant-Appellee First Energy's motion for judgment on the pleadings and dismissed his case. This Court affirms.

I
{¶ 2} On August 25, 2004, Plaintiff-Appellant Joseph C. McLeland ("McLeland") filed a complaint in the Summit County Court of Common Pleas to enforce the Fair Credit Reporting Act against Defendants-Appellees First Energy dba Ohio Edison ("First Energy"), Allegheny Energy Company ("Allegheny"), CBF Business Solutions ("CBF"), and Trans Union Consumer Relations ("Trans Union"). The suit was the result of outstanding electric charges and McLeland's alleged missing credit on his First Energy bill. Part of McLeland's bill included electric power First Energy had purchased from Allegheny; when McLeland submitted payment of his bill, which included a check and a credit voucher, to First Energy, Allegheny was not paid for the power it provided. The outstanding charges on McLeland's First Energy bill lead to the involvement of CFB, a collection agency, and Trans Union, a credit reporting company. Subsequent to McLeland submitting payment to First Energy, Allegheny ceased supplying power to First Energy; the voucher McLeland sent with his bill was later applied to charges McLeland owed for power provided by a subsequent First Energy power supplier. Accordingly, Allegheny was never paid for the portion of power it supplied McLeland through First Energy.

{¶ 3} Pursuant to Civ. R. 12(C), First Energy filed a motion for judgment on the pleadings. First Energy argued that the trial court lacked subject matter jurisdiction under R.C. 4905.04 and R.C. 4903.12 because First Energy is a public utility. McLeland responded in opposition to the motion. On February 22, 2005, the trial court granted First Energy's motion and found that pursuant to R.C. 4905.04 and 4903.12 it lacked subject matter jurisdiction over McLeland's claim. The trial court dismissed McLeland's case.

{¶ 4} McLeland has timely appealed the trial court's decision, asserting two assignments of error.1 For ease of discussion, we have consolidated McLeland's assignments of error.

II
Assignment of Error Number One
"THE TRIAL COURT ERRED IN NOT APPLYING EXISTING APPLICABLE CASE LAW TO THE FACTS AS PLED BY APPELLANT, BRINGING THE CASE WITHIN THE JURISDICTION OF THE SUMMIT COUNTY COMMON PLEAS COURT."

Assignment of Error Number Two
"THE [TRIAL] COURT ERRED IN FINDING THAT APPELLANT'S CASE AS PLED, DOES FALL UNDER THE EXCLUSIVE JURISDICTION OF THE OHIO PUBLIC UTILITIES COMMISSION."

{¶ 5} In his first and second assignments of error, McLeland has argued that the trial court erred when it determined that it lacked jurisdiction to hear his case and that the Ohio Public Utilities Commission ("PUCO") had exclusive jurisdiction over his case. Specifically, McLeland has argued that because his claims were under tort and contract law, the trial court did have jurisdiction, and that R.C. 4905.04 does not apply in the instant matter. We disagree.

{¶ 6} This Court reviews a trial court's decision to grant a motion for judgment on the pleadings under the de novo standard of review.Fontbank, Inc. v. Compuserve, Inc. (2000), 138 App.3d 801, 807. Pursuant to Civ. R. 12(C), "after the pleadings are closed but within such times as not to delay the trial, any party may move for judgment on the pleadings." When construing a defendant's motion for judgment on the pleadings pursuant to Civ. R. 12(C), the trial court must construe as true all material allegations in the complaint, together with all reasonable inferences to be drawn therefrom. Peterson v. Teodosio (1973),34 Ohio St.2d 161, 165-66. The determination of a motion for judgment on the pleadings is restricted solely to the allegations of the pleadings. Id. at 166. To uphold a judgment on the pleadings pursuant to Civ. R. 12(C), a reviewing court must find, beyond a doubt, that the plaintiff could prove no set of facts in support of his claim that would entitle him to the relief requested. Lin v. Gatehouse Constr. Co. (1992),84 Ohio App.3d 96, 99.

{¶ 7} The trial court below found that McLeland's complaint was under the exclusive jurisdiction of PUCO and therefore it granted First Energy's Civ. R. 12(C) motion. McLeland has argued that R.C. 4905.04, which grants exclusive jurisdiction to PUCO, is inapplicable to the instant matter. First Energy has responded that the statute clearly applies and that the common pleas court does not have jurisdiction over McLeland's case.

{¶ 8} It is well settled law that PUCO has jurisdiction to adjudicate utility customer complaints related to rates or services of the utility.Kazmaier Supermarket, Inc. v. Toledo Edison Co. (1991), 61 Ohio St.3d 147,151-52. The Ohio Supreme Court has recognized that "the commission with its expert staff technicians familiar with the utility commission provisions" is best suited to resolve such disputes. Id. at 153.

{¶ 9} McLeland correctly asserts that contract and pure common-law tort claims against a public utility may be brought in a common pleas court. See State ex rel. Ohio Power Co. v. Harnishfeger (1980),64 Ohio St.2d 9, 10. However, where a claim is related to service, R.C. 4905.26 gives PUCO exclusive jurisdiction. State ex rel. Northern OhioTel. Co. v. Winter (1970), 23 Ohio St.2d 6, 9-10. Pursuant to R.C. 4905.26:

"Upon complaint in writing against any public utility by any person, firm, or corporation, or upon the initiative or complaint of the public utilities commission, that any rate, fare, charge, toll, rental, schedule, classification, or service, or any joint rate, fare, charge, toll, rental, schedule, classification, or service rendered, charged, demanded, exacted, or proposed to be rendered, charged, demanded, or exacted, is in any respect unjust, unreasonable, unjustly discriminatory, unjustly preferential, or in violation of law, or that any regulation, measurement, or practice affecting or relating to any service furnished by the public utility, or in connection with such service, is, or will be, in any respect unreasonable, unjust, insufficient, unjustly discriminatory, or unjustly preferential, or that any service is, or will be, inadequate or cannot be obtained, and, upon complaint of a public utility as to any matter affecting its own product or service, if it appears that reasonable grounds for complaint are stated, the commission shall fix a time for hearing and shall notify complainants and the public utility thereof. Such notice shall be served not less than fifteen days before hearing and shall state the matters complained of.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hall v. Waseleski
2025 Ohio 2552 (Ohio Court of Appeals, 2025)
N.H. v. Soisson
2025 Ohio 2285 (Ohio Court of Appeals, 2025)
A.W. v. Twinsburg Bd. of Edn.
2024 Ohio 2486 (Ohio Court of Appeals, 2024)
Needham v. Columbus
2014 Ohio 1457 (Ohio Court of Appeals, 2014)
Chenault v. Ohio Department of Job & Family Services
957 N.E.2d 858 (Ohio Court of Appeals, 2011)
Greene v. Ohio Adult Parole Auth., 08ap-555 (11-18-2008)
2008 Ohio 5972 (Ohio Court of Appeals, 2008)
Capshaw v. Hickman
880 N.E.2d 118 (Ohio Court of Appeals, 2007)
Smith v. Nagel, 23551 (6-13-2007)
2007 Ohio 2894 (Ohio Court of Appeals, 2007)
M.B. v. Elyria City Bd. of Edn., Unpublished Decision (9-5-2006)
2006 Ohio 4533 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2005 Ohio 4940, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcleland-v-first-energy-unpublished-decision-9-21-2005-ohioctapp-2005.