McLean Construction Co. v. Globe Indemnity Co.

168 F. Supp. 318, 1958 U.S. Dist. LEXIS 3089
CourtDistrict Court, W.D. Missouri
DecidedDecember 17, 1958
DocketNo. 1541
StatusPublished
Cited by3 cases

This text of 168 F. Supp. 318 (McLean Construction Co. v. Globe Indemnity Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McLean Construction Co. v. Globe Indemnity Co., 168 F. Supp. 318, 1958 U.S. Dist. LEXIS 3089 (W.D. Mo. 1958).

Opinion

R. JASPER SMITH, District Judge.

This is an action by plaintiff as a third party beneficiary to recover certain monies alleged to be due as a result of a written assignment.

The facts as shown by the evidence are these:

J. W. Bateson Company, Inc., of Dallas, Texas, was the general contractor for construction of family housing at Whiteman Air Force Base, Knob Noster, [320]*320Missouri. Plaintiff, McLean Construction Company, was a subcontractor under an agreement with Bateson for certain earth moving and grading required by the basic contract with the Department of the Army. In turn on January 26, 1957, plaintiff contracted with Neal B. Brown, third party defendant, to complete a portion of the work which it was responsible for performing, the finished grading and replacing of top soil on certain areas at the Air Force Base. The contract price for this work was $2,357.50. As a part of the agreement by Brown, he covenanted to provide a performance and payment bond acceptable to McLean. In due course defendant Globe Indemnity Company executed its bond number 524607 in the amount of $2,357.50 as surety for Brown.

In August, 1957, certain controversies having developed in connection with the performance of the contract by Brown, a conference was arranged on the 16th of that month at the Air Force Base with parties in attendance representing the General Contractor, Bateson, the plaintiff, McLean, the third party defendant, Brown, and defendant, Globe. At that time Brown had performed a portion of his contract with McLean, estimated at about one-third. Brown was represented at this conference by attorney Walter S. Pettit, Jr., of Springfield, Missouri. Globe was represented by its Claim Manager, George L. Long. Pettit and Long, representing their respective interests and attempting to save those they represented from harm, are the two central figures who drew up and negotiated the contract of assignment about which this litigation centers.

The conference was devoted primarily to a discussion of ways and means by which the work assigned to Brown under the subcontract could be completed with reasonable dispatch. At the conference, Bateson gave notice to Brown and McLean that if work was not commenced by August 20, 1957, to complete the remainder of Brown’s subcontract, McLean’s contract would be considered in default. At the same conference it developed that Brown was making claim either against McLean or the General Contractor, Bateson, for extra work done on the Air Force Base in a claimed amount in excess of $12,000.

Brown was interested in an arrangement by which he could be relieved of responsibility under his contract. That was the primary objective of his attorney in discussions at the general conference and in private discussions with Long, as the representative of Globe. Long, on his part, recognizing that there was a strong possibility of loss by his company because of non-performance of the contract by Brown, and knowing of Brown’s claim for the extra work, desired an assignment of Brown’s interest in the contract as well as an assignment of any additional monies that might be due Brown. He was uncertain whether or not a formal application for bond with the standard assignment and subrogation agreement had been executed in the first instance by Brown.

At the time of the conference none of the parties had any clear notion of the cost of completing Brown’s subcontract, and in the preliminary stages Pettit and Long discussed the possibility of Globe assuming Brown’s contract and completing it, along with the alternate possibility that Globe might want McLean to do the work and permit Globe to pay the penal sum of the bond.

A first draft of the assignment was prepared. Pettit and Long examined it and discussed it at length, it was revised, retyped, and in its final form was executed on August 16, 1957, by Brown and by Long. The assignment, between Brown, the party of the first part, and Globe, as party of the second part, omitting formal portions and preliminary recitals, is as follows:

“Now, therefore, in consideration of the execution of the aforementioned bond, second parties’ assumption of the sub-contract in case of default, and for the purpose of affording Second Party additional security, it is hereby agreed by and between the parties hereto that in [321]*321the event party of the first part should default or for any reason fail to perform under the said subcontract between party of the first part and McLean Construction Company, party of the second part shall be subrogated to all the rights and interests of party of the first part in said sub-contract, including deferred or reserved payments, current and earned estimates and final payments and any and all monies and securities that may be due and payable at the time of such default on said sub-contract or on account of extra work or material supplied in connection therewith, or that may hereafter become due and payable on said sub-contract. And the party of the first part hereby authorizes the party of the second part to endorse in the name of the party of the first part, and to collect any check, draft, warrant or other instrument made or issued in payment of any monies due on such sub-contracts and to disburse the proceeds thereof, to such person, persons, or corporations as their interests may appear.”

This is the portion of the assignment which furnishes the basis of the action pending now.

McLean, faced with the dilemma of default as the deadline approached which Bateman had established, gave notice to Globe and made demand for it to perform under the assignment. When Globe gave no indication of its willingness to do so, McLean on August 20, 1957, entered a written agreement with Johnmeyer Construction Company of Fayette, Missouri, to complete the work which Brown originally had undertaken. In due course Johnmeyer completed the work. McLean demanded payment by Globe. Globe admitted liability to the limits of the original bond, $2,357.50, but denied it was liable for the additional costs. McLean then brought this suit. Its theory is that under the original contract with Brown it had the right to provide for the performance of the work if Brown defaulted; that by the agreement of August 16, 1957, between Brown and Globe, the latter assumed the contractual liabilities of Brown; that plaintiff is a third party beneficiary of that assignment from Brown to Globe; and that Globe is now responsible for the amount it cost to bring in Johnmeyer. The critical issue is the definition of the contract rights which plaintiff derived from the assignment from Brown to Globe. The parties stipulated prior to trial that if plaintiff prevails as to Count I, which in substance alleges plaintiff's purported rights under the assignment, the verdict should be for plaintiff in the amount of $15,-750, and that if defendant prevails as to that Count the verdict should be for plaintiff in the amount of $2,357.50.

All agree that the significant portion of the assignment is contained in the language “second parties? (sic) assumption of the sub-contract in case of default, * * Plaintiff contends that this imposes a responsibility on Globe to complete the contract with McLean or in lieu thereof to pay the full cost of completion. Globe contends that the quoted portion, read in context, indicates an intention simply to succeed to all of Brown’s rights to receive money as a part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Aetna Insurance Company v. Saul Eisenberg
294 F.2d 301 (Eighth Circuit, 1961)
Aetna Insurance v. Eisenberg
294 F.2d 301 (Eighth Circuit, 1961)

Cite This Page — Counsel Stack

Bluebook (online)
168 F. Supp. 318, 1958 U.S. Dist. LEXIS 3089, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mclean-construction-co-v-globe-indemnity-co-mowd-1958.