C. S. Foreman Company, a Corporation v. Great Lakes Pipe Line Company, a Corporation

274 F.2d 61, 1960 U.S. App. LEXIS 5465
CourtCourt of Appeals for the Eighth Circuit
DecidedFebruary 3, 1960
Docket16280
StatusPublished
Cited by4 cases

This text of 274 F.2d 61 (C. S. Foreman Company, a Corporation v. Great Lakes Pipe Line Company, a Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
C. S. Foreman Company, a Corporation v. Great Lakes Pipe Line Company, a Corporation, 274 F.2d 61, 1960 U.S. App. LEXIS 5465 (8th Cir. 1960).

Opinion

VAN OOSTERHOUT, Circuit Judge.

Plaintiff, C. S. Foreman Company, appeals from final judgment dismissing Count I of its complaint against defendant, Great Lakes Pipe Line Company. Count I of the complaint seeks reformation of a written contract covering construction work to be performed by plaintiff for defendant. The complaint contains seven additional counts not directly involved in this appeal. 1 Final judgment was entered dismissing Count I. 2

Jurisdiction based upon diversity of citizenship and the requisite amount is established.

In the summer of 1952 defendant found it necessary to have some emergency work done on its pipe line in the Missouri River near Onawa, Iowa. Defendant, through its Chief Engineer, Charles C. Keane, entered into negotiations with Charles S. Foreman, president of plaintiff corporation, looking towards contracting for the performance of the needed work. At Keane’s request, Foreman submitted two bids for the work, a cost-plus bid and a lump sum bid. Plaintiff was advised that defendant preferred *63 to proceed on the cost-plus basis. Plaintiff’s original cost-plus bid was not accepted. Further negotiations were carried on by Keane and Mr. Foreman. It was the understanding of all parties that the mutual rights and obligations of each of the parties would be evidenced by a written contract which would be drawn up and executed on behalf of both parties.

Thereafter a written contract was prepared by defendant and was signed on behalf of plaintiff, a Texas corporation, by its duly authorized officers, Charles S. Foreman, President, and his wife Helen McShane Foreman, Secretary, on August 29, 1952, and was sent to defendant. James B. Lawson, vice president in charge of construction, acting within the scope of his authority, signed the contract on behalf of the defendant.

A completed and signed copy of the contract was mailed to and received by plaintiff on or about September 9, 1952.

The written contract provides with reference to plaintiff’s compensation basically as follows:

“$18,500 per month rental of heavy equipment; $4,500 for furnishing small tools listed; $8,500 for moving on the job; $4,000 for moving off the job; cost-plus 15% of labor; of furnishing any of the material listed; of furnishing any of the supplies listed; of the purchase of small tools in excess of those listed; and of insurance. * * * >>

The contracted work was completed in January, 1953. Payments required by the written contract have been made. This action was commenced on February 1, 1957.

Plaintiff’s contention is that under the real agreement existing between the parties, plaintiff in addition to the compensation provided in the written contract is entitled to be reimbursed for all other costs incurred by it in the performance of the contract plus 15% for overhead, and that by reason of mutual mistake such provision was omitted from the written contract and that plaintiff is entitled to have the contract reformed to express the true agreement between the contracting parties. The complaint shows that the other costs which plaintiff seeks to recover are principally wear and tear damage to plaintiff’s machinery, damage to and loss of equipment and small tools, and damage caused to plaintiff’s dredge by its sinking in the river.

In dismissing Count I the court states:

" * * * it is my conclusion in this case that the plaintiff has not sustained the extremely heavy burden that is cast upon it in a case of this kind, seeking to reform a solemn written agreement, and under those circumstances, since the plaintiff has not sustained the burden imposed on it under the law, there can only be one decision on this first count of this proceeding, and that is that judgment will have to be entered for the defendant on Count One.”

Such dismissal was based upon findings of fact and conclusions of law, reading:

“Findings of Fact.
“1. That Plaintiff’s Exhibit 3 was read and signed by the president of plaintiff corporation and its secretary and treasurer, and the plaintiff’s corporate seal affixed thereto on August 29, 1952, and was thereafter signed by a vice-president and the secretary of the defendant corporation, and its corporate seal affixed thereto, and returned to the plaintiff on or about September 9, 1952.
“2. There was no evidence that the defendant intended to agree to pay ‘the cost plus 15% of all repairs and replacements required to restore plaintiff’s equipment and machinery to as good condition as when received upon the job site, plus rental at the agreed rate during the period of time required for such restoration; the value plus 15% of any of plaintiff’s equipment or tools lost or damaged beyond repair in the performance of the work; and all *64 other costs to plaintiff incurred in or arising from the performance of the work, plus 15%’, as claimed in the amended complaint, Paragraph 5(f), (g) and (h).
“3. There was evidence that plaintiff billed the defendant for repairs and parts and certain other costs, for which payment was not specified in Exhibit 3, and defendant paid a portion of such costs so billed.
“4. Plaintiff did not dispute the content of Exhibit 3 as not being the true agreement until after the work thereunder had terminated, although the secretary-treasurer of the plaintiff company testified she noticed a discrepancy concerning cost of repairs when she was reading it before she executed it.
“Conclusions of Law.
“1. Evidence of payments made for costs not provided for in the contract does not supply the clear, convincing and satisfactory proof required to justify reformation of the written contract.
“2. Plaintiff is estopped from asserting the contract was other than as written, by its officers’ actions in reading, executing and retaining the same, and in invoicing the defendant thereunder and receiving payments thereon.
“3. The ‘General Conditions’ are a part of the contract and paragraph .231 thereof, by which plaintiff assumes loss of or damage to property, including its own, arising out of the work, is a valid provision and also constitutes a bar to reforming the contract as prayed to provide that defendant should pay such loss plus 15%.
“4. The provision of paragraph .390 that ‘there are no agreements, understandings, conditions, warranties or representations, oral or written, express or implied, with reference to the subject matter * * * that are not merged (t) herein or superseded (t) hereby’ is also a valid provision and a bar to reformation.”

Plaintiff urges that it is entitled to a reversal for the following reasons:

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
274 F.2d 61, 1960 U.S. App. LEXIS 5465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/c-s-foreman-company-a-corporation-v-great-lakes-pipe-line-company-a-ca8-1960.