McKnight Construction Co. v. Department of Defense

85 F.3d 565
CourtCourt of Appeals for the Eleventh Circuit
DecidedJune 17, 1996
Docket95-8811
StatusPublished
Cited by2 cases

This text of 85 F.3d 565 (McKnight Construction Co. v. Department of Defense) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKnight Construction Co. v. Department of Defense, 85 F.3d 565 (11th Cir. 1996).

Opinion

KRAVITCH, Circuit Judge:

The Army Corps of Engineers (“Army”) and Conner Brothers Construction Co., Inc., appeal the district court’s grant of summary judgment in favor of McKnight Construction Co. Although McKnight was the low bidder on an Army construction project, McKnight’s bid was rejected because it did not conform to the Army’s guidelines. After the Army and the Comptroller General refused to accept McKnight’s bid corrections, McKnight appealed to the district court, which reversed the Army’s decision. We now reverse the decision of the district court.

I.

The Army, acting through its Corps of Engineers, solicited bids for construction of barracks at Fort Benning, Georgia. At bid opening, the Army had received bids from four companies. The low bidder was McKnight; Conner Brothers was the next lowest bidder. The following day, Conner Brothers notified the Army of apparent errors in McKnight’s bid and asked the Army to reject it as “nonresponsive.” The day after Conner Brothers’ protest, the Army began a review to determine whether McKnight’s bid was responsive.

A bid is nonresponsive when it is mathematically and materially unbalanced; such a bid must be rejected. See G.C. Ferguson 4-T Constr., 92-1 CPD ¶ 381, 1992 WL 143301 (CG1992); Sanford Cooling, 91-1 CPD ¶ 376, 1991 WL 86957 (CG1991). A bid is mathematically unbalanced when each line item in the bid does not reflect the actual costs to the bidder. See 48 C.F.R. §§ 14.404-2(g), 15.814. The Army determined that Lines 1 and 2 of McKnight’s bid were mathematically unbalanced because the amount listed in each line was significantly higher than that listed by other companies and the government’s own estimate. For both line items 1 and 2, McKnight bid $4,203,500; the next highest bid estimate for the work corresponding to those lines was the government’s estimate of $395,557 for line item 1 and $55,780 for line item 2. A chart with all the bids is reproduced as Table I.

TABLE I

[[Image here]]

*568 [[Image here]]

Where a mathematically unbalanced bid is so grossly unbalanced that it will result in an advance payment, the bid is materially unbalanced and must be rejected. 48 C.F.R. § 15.814(b)(2); see Boston Graving Dock Corp., 91-2 CPD ¶ 178, 1991 WL 162533 (CG1991). Because the estimates in lines 1 and 2 front-loaded the bid with disproportionately high payments, the Army found that the bid was materially unbalanced. Approximately 50% of the bid’s total value of $16,850,000 was captured in the first two lines of McKnight’s bid; the next highest figure for the combined cost of each of the first two line items was the government’s estimate of approximately $450,000, which constituted less than 2.7% of. the overall bid price.

Although there is no suggestion that McKnight’s error was deliberate, a bidder could potentially manipulate the bidding process by intentionally front-loading a bid, and in the event that the “error” went unnoticed, collect extremely large advance payments. Advance payments are disfavored because a bidder that receives early payments gains an unfair advantage over other bidders through the potential use of interest-free money. In addition, because later work is undervalued, there is a reduced incentive to complete the work.

On the same day that the Army began its review of McKnight’s bid, McKnight notified the Army that its bid contained mistakes and sought permission to file a corrected bid. Two days later, McKnight formally requested permission to file a corrected bid and submitted an affidavit from its president, William McKnight. Later, McKnight sent the Army “post-bid opening” worksheets, which were created to “reconstruct ... [the] thought process in allocating the total bid price to the individual line items in the bid schedule.” The only pre-bid documentation provided was the bid papers, and “there is no dispute that these did not identify bid items, buildings, subcontractor pricing, or other aspects of the project by which McKnight’s intended allocation of bid line items could be ascertained.” McKnight Construction Co. v. Perry, 888 F.Supp. 1186, 1187 (S.D.Ga.1995).

In his affidavit, William McKnight stated that although the company’s overall bid was correct, in filling out the bid sheet he had made a transpositional error, mistakenly switching the bid prices for line items 1 and 2 with those intended for line items 4 and 5. The total bid would have been unchanged.

After reviewing McKnight’s request for bid correction, the Army found that although McKnight had made mistakes in computing its bid, it had not provided clear and convincing evidence of its intended bid with respect to each line item, as required by Federal Acquisition Regulations. See 48 C.F.R. § 14.406-3(a). Thus, the Army refused to permit McKnight to file a corrected bid. In reaching its conclusion, the Army noted McKnight’s inability to furnish independent corroboration for its intended bid. Because the original bid was rejected as nonresponsive, the next lowest bidder, Conner Brothers, was awarded the contract.

*569 McKnight filed a bid protest with the General Accounting Office that was rejected by decision of the Comptroller General. The Comptroller General determined that although the evidence supported McKnight’s contention that it had made a mistake in its bid, there was not clear and convincing evidence of McKnight’s intended bid price. The Comptroller General found that the similarity of McKnight’s bid on lines 1 and 2 to the government’s estimates and the other bids for line items 4 and 5 supported McKnight’s contention that line items 1 and 2 should have been placed on lines 4 and 5. 1 More importantly, however, the Comptroller General rejected as “implausible on its face” McKnight’s contention that the $250,000 listed on both lines 4 and 5 was the amount intended to be placed on lines 1 and 2. This conclusion was based on the gross disparity that would have resulted on line 2, where the next highest bid estimate would have been the government’s estimate of $55,780. Holding that there was a reasonable basis for the Army’s refusal to accept the corrected bid, the Comptroller General rejected the uncorreeted bid on reasoning similar to that of the Army.

Following the Comptroller General’s ruling, McKnight brought this action, challenging the Army’s refusal to permit it to correct its bid and the consequent award of the contract to Conner Brothers. Conner Brothers intervened as a defendant. McKnight argues that the Army’s actions violated the Administrative Procedures Act.

The district court initially granted a preliminary injunction barring the Army from implementing the contract award and later granted McKnight’s motion for summary judgment. The Army and Conner Brothers appeal that decision.

II.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
85 F.3d 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcknight-construction-co-v-department-of-defense-ca11-1996.