McKinstry Co. v. Aeronautical Machinists, Inc.

814 P.2d 251, 62 Wash. App. 442, 1991 Wash. App. LEXIS 306
CourtCourt of Appeals of Washington
DecidedAugust 19, 1991
DocketNo. 26835-0-I
StatusPublished
Cited by1 cases

This text of 814 P.2d 251 (McKinstry Co. v. Aeronautical Machinists, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Washington primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McKinstry Co. v. Aeronautical Machinists, Inc., 814 P.2d 251, 62 Wash. App. 442, 1991 Wash. App. LEXIS 306 (Wash. Ct. App. 1991).

Opinion

Pekelis, J.

Evergreen State Construction, Inc. (ESC) appeals from the denial of its motion for partial summary judgment against McKinstry Co. McKinstry had sought to foreclose a materialmen's lien on a building project owned by Aeronautical Machinists, Inc. (AMI). ESC, the project's general contractor, moved for partial summary judgment contending that because McKinstry failed to give ESC prelien notice, part of its claim was void. The trial court denied ESC's motion, ruling that ESC's failure to comply with RCW 60.04.230 excused McKinstry's failure to give ESC notice.

I

In August 1987, ESC began construction on the Aerospace Machinists District Lodge 751 Headquarters and Meeting Hall (the AMI project). The roofing subcontractor on the project was Puget Sound Roofing, Inc. (PSR). McKinstry provided labor and roofing materials to PSR [444]*444for the project. At some point before completion, PSR became insolvent and was unable to pay McKinstry.

On March 17, 1988, McKinstry notified AMI that it was supplying labor and roofing materials to PSR on the AMI project. On May 25, 1988, McKinstry sent a letter to ESC by certified mail. This letter did not specifically state that McKinstry would file a lien against the AMI property in the event of nonpayment. However, in a subsequent letter sent to ESC on August 3, 1988, McKinstry indicated that it would do so if necessary. Thereafter, on September 6, 1988, McKinstry recorded its lien claim.

On May 3, 1989, McKinstry brought a foreclosure action against AMI, the lessee of the building, five other subcontractors with recorded mechanics' liens, and the project's lender. ESC was brought in as a third party defendant and, pursuant to a contractual indemnification and hold harmless agreement with AMI, defended the action on AMI's behalf.

Prior to trial, all lien claims except McKinstry's were satisfied or released. On September 11, 1989, ESC posted a bond as authorized by RCW 60.04.115, which had the effect of releasing the property from McKinstry's lien.

On July 3, 1990, ESC moved for partial summary judgment pursuant to RCW 60.04.020,1 asserting that it was entitled to prelien notice from McKinstry. Because the May 25, 1988, notice contained no expression of [445]*445McKinstry's intent to claim a lien, ESC asked the trial court to declare as a matter of law that McKinstry's lien claim for materials supplied before June 4, 1988, was invalid.2 This date was chosen because notice under RCW 60.04.020 only covers those materials furnished 60 days before the notice is given and thereafter, and June 4 preceded McKinstry's valid August 3, 1988, notice by 60 days.3

In response, McKinstry argued that ESC was not entitled to prelien notification because ESC had failed to satisfy the proviso in RCW 60.04.020 which conditions prelien notification on the prime contractor's compliance with RCW 60.04.230.4 Thus, the critical issue before the court was whether ESC had complied with RCW 60.04-.230(2).

The evidence before the court consisted of the declaration of Joel Bushman, ESC's superintendent for the AMI project, submitted by ESC, and excerpts from Bushman's deposition submitted by McKinstry.

In his declaration, Bushman stated that copies of the various building permits obtained by ESC were posted in the entry area of the job trailer. These included the [446]*446building permit for the headquarters and meeting hall, the site work permit, and the tenant improvement permit. According to Bushman, the building permit identified AMI as the property owner, listed the address of the site, and identified ESC as the prime contractor both by name and registration number. Also posted inside the trailer was a copy of the job schedule, which further identified ESC as the prime contractor. Finally, Bushman stated that a large sign, approximately 10 feet by 4 feet, was posted at the most prominent corner of the project and identified AMI as the owner and ESC as the prime contractor. There were also two other similar signs posted back to back along one side of the project, which were only slightly smaller.

In his deposition, Bushman testified that he did not post a special notice for the purpose of advising materi-almen. He contended that he believed the statutory requirement was satisfied by the signs on the site and by the "job schedule, which has the name and address of our projects, and then it has the company's name and my name." Bushman also testified that the job schedule was used to monitor the project's progress and was posted on a conference room wall inside the jobsite trailer.

In addition to Bushman's deposition, McKinstry also submitted the declaration of John Gundlach, the project manager for McKinstry on the AMI project. Gundlach stated that he:

attended an initial job start meeting on February 3, 1988 in the conference room in the job trailer, which is referred to in Mr. Bushman's Declaration. There was no special notice containing the above information posted. I think there was a hoard on the left hand side inside the trailer before you enter the conference room which had various permits and OSHA safety notices posted. Every job requires an OSHA hotice and the building permit is one of several forms posted so the inspectors can sign off. A material sub to a sub-contractor would not have any need to refer to the building permit. On this job material suppliers did not use the entrance near the job trailer and thus could not observe a building permit tacked up inside the trailer.

[447]*447On July 10, 1990, the trial court denied partial summary judgment, finding that RCW 60.04.230 required the posting of a special notice to materialmen. Because ESC had not done so, it was not entitled to prelien notice as a matter of law. This ruling effectively decided the entire case. The parties subsequently stipulated to the principal sum claimed by McKinstry, reserving only the question whether McKinstry was entitled to prejudgment interest and attorney's fees. After hearing argument on this question, the court entered judgment in favor of McKinstry on July 30, 1989. The judgment noted that the stipulation did not prejudice ESC's right to appeal from the denial of partial summary judgment. ESC appeals.

II

ESC contends that the building permit and job schedule posted inside the job trailer and the outdoor signs meet, or substantially meet, the requirements of RCW 60.04-.230.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Littlejohn Construction Co. v. Department of Labor & Industries
873 P.2d 583 (Court of Appeals of Washington, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
814 P.2d 251, 62 Wash. App. 442, 1991 Wash. App. LEXIS 306, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mckinstry-co-v-aeronautical-machinists-inc-washctapp-1991.