McIntyre v. Kansas City, Missouri

171 S.W.2d 805, 237 Mo. App. 1178, 1943 Mo. App. LEXIS 258
CourtMissouri Court of Appeals
DecidedMay 3, 1943
StatusPublished
Cited by12 cases

This text of 171 S.W.2d 805 (McIntyre v. Kansas City, Missouri) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McIntyre v. Kansas City, Missouri, 171 S.W.2d 805, 237 Mo. App. 1178, 1943 Mo. App. LEXIS 258 (Mo. Ct. App. 1943).

Opinions

Defendant city appeals from a judgment in favor of McIntyre in the sum of $2110. The main question for determination on appeal is whether the five or ten-year Statute of Limitation applies to plaintiff's cause of action as shown by the petition and the evidence. A written contract between the parties is involved in the suit. Plaintiff alleged a breach of this contract and contends that his cause of action is founded upon a writing for the payment of money within the meaning of Section 1013, Revised Statutes Missouri 1939, and that the ten-year Statute of Limitation applies. Appellant contends to the contrary and claims that the cause of action is for damages on account of the alleged breach of the contract in question and is barred by Section 1014, Revised Statutes 1939, because suit was not filed within five years after the cause of action accrued. The parties differ as to the nature of the action and the character of the written contract mentioned in the petition, shown in evidence, and involved in the suit. It is therefore deemed advisable that the petition and the contract be fully set forth, together with the substance of the other pleadings and the evidence.

The petition was filed in the Circuit Court of Jackson County, August 25, 1939, and omitting caption and signatures, it reads as follows:

"Plaintiff for his cause of action against defendant states:

"The defendant is now and at all times herein mentioned was a municipal corporation duly organized and existing according to the laws of Missouri, and having a special charter pursuant to the provisions of the Constitution of Missouri. Plaintiff is now and at all times herein mentioned was an architectural engineer.

"On June 8, 1932, a contract was made and entered into and signed by defendant and plaintiff by the terms of which defendant employed the plaintiff, and plaintiff accepted employment, to plan, design, direct and supervise the construction of a viaduct to be constructed by the defendant in Swope Park connecting the Blue River Road with a road leading to the county highway on the south end of said Swope Park. Defendant agreed to pay plaintiff as compensation *Page 1181 for his services the sum of five per cent of the total amount of the actual cost of the construction of said viaduct.

"Ever since said contract was made and entered into as aforesaid, plaintiff has at all times been willing, ready and able to comply with, carry out and perform all the obligations and duties imposed upon and required of him under and by virtue of the terms of said contract, but the defendant in direct violation thereof, has breached said contract in the following particulars, to-wit:

"After said contract was entered into plaintiff prepared all maps, plans and specifications required in connection with the construction of said viaduct and submitted said maps, plans and specifications to the defendant, and said maps, plans and specifications were fully approved by defendant, by its Board of Park Commissioners and its engineers; thereafter the defendant delayed, neglected and refused to proceed to advertise for bids for the construction of said viaduct or to construct said viaduct, and refused to permit plaintiff to perform the remainder of the services required of him under said contract, and in direct violation of plaintiff's said contract defendant caused to be installed at the place described in the aforesaid contract as the location for said viaduct a dirt fill.

"Plaintiff states that had defendant not breached said contract as aforesaid and plaintiff had been permitted and allowed to complete the services provided for in said contract plaintiff would have derived and made a profit out of the services called for in said contract in the sum of $7250, the total actual reasonable cost of said viaduct would have been $165,000, and had defendant not breached said contract plaintiff would have received as compensation the sum of $8250, of which sum his profit would have been $7250. Defendant has paid plaintiff the sum of $2700 and on June 2, 1939, refused to pay plaintiff any further compensation.

"By reason of the acts and conduct on the part of defendant in breaching plaintiff's said contract as aforesaid, he has by the direct result thereof been damaged in the sum of Four Thousand Five Hundred Fifty Dollars ($4550).

"WHEREFORE, plaintiff prays judgment against defendant in the sum of Four Thousand Five Hundred Fifty Dollars ($4550) with interest thereon from June 2, 1939, together with his costs in this behalf expended."

Defendant's second amended answer admits that defendant is a municipal corporation with a special charter, but denies generally the other allegations of the petition. And for further answer states that plaintiff's cause of action, if any, is barred by the Statute of Limitations in that the same is of that class of actions upon which suit must be brought within five years after the accrual thereof as provided by Section 1014, Revised Statutes Missouri 1939, and that the present action was not brought until more than five years thereafter. *Page 1182 The answer further pleads that if plaintiff was hired as alleged in his petition the employment was for the purpose of preparing plans and supervising construction of a viaduct at an estimated cost of $60,000; that plaintiff abandoned said contract in that he prepared plans and specifications for a viaduct costing in excess of $125,000, and that when defendant learned of the estimated cost of the viaduct based upon said plans and specifications, it refused to continue the employment of plaintiff on such basis; that defendant has paid plaintiff $2700, in full discharge of any and all obligations which might have been owing to plaintiff. The answer also contained a plea of a long established custom that in the employment of architects, such as in plaintiff's case, it was understood that the proponent of any project requiring the preparation of plans and specifications was free to abandon the same at any time and that the architect was entitled to compensation for only such part of the work as was completed at the time of such abandonment.

Plaintiff filed reply in the nature of a general denial, and on the day of trial filed his motion for an order to strike from the answer the plea of limitation for the reason that plaintiff's suit is on a written contract between the parties and is not controlled by Section 1014, Revised Statutes Missouri 1939; and also moved the court to strike from the answer the plea of an established custom. Final ruling on the motion was reserved until the close of plaintiff's evidence, at which time the motion was sustained in part and the plea of limitation contained in the answer was stricken, and the court said: "I have concluded that this is a suit upon a contract and not a suit in tort for a tortuous breach of the contract."

The trial proceeded and at the close of all the evidence the court refused defendant's peremptory instruction in the nature of a demurrer to all the evidence, and refused all of defendant's tendered instructions except one submitting the question as to whether or not there was a custom such as that pleaded in the answer. The case was submitted upon plaintiff's instruction and ten jurors signed a verdict reading as follows: "We, the undersigned jurors, find the issues for the plaintiff and do assess his damages at $2110."

The assignments of error and points briefed by both parties include the question of limitation arising upon the demurrer to the evidence and the action of the court in striking the plea of limitation from the answer, and the ruling of the court in giving and refusing instructions.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lowery v. Air Support International, Inc.
982 S.W.2d 326 (Missouri Court of Appeals, 1998)
Community Title Co. v. Stewart Title Guaranty Co.
977 S.W.2d 501 (Supreme Court of Missouri, 1998)
E.J. Vitello Plumbing, Inc. v. Wayne M. Roberts, Inc.
955 S.W.2d 222 (Missouri Court of Appeals, 1997)
Aerotronics, Inc. v. Pneumo Abex Corporation
62 F.3d 1053 (Eighth Circuit, 1995)
Van Stratten v. Friesen
841 S.W.2d 750 (Missouri Court of Appeals, 1992)
Highland Inns Corp. v. American Landmark Corp.
650 S.W.2d 667 (Missouri Court of Appeals, 1983)
Boten v. Brecklein
452 S.W.2d 86 (Supreme Court of Missouri, 1970)
Kansas City v. City of Raytown
421 S.W.2d 504 (Supreme Court of Missouri, 1967)
Sam Kraus Co. v. State Highway Commission of Missouri
416 S.W.2d 639 (Supreme Court of Missouri, 1967)
Martin v. Potashnick
217 S.W.2d 379 (Supreme Court of Missouri, 1949)

Cite This Page — Counsel Stack

Bluebook (online)
171 S.W.2d 805, 237 Mo. App. 1178, 1943 Mo. App. LEXIS 258, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcintyre-v-kansas-city-missouri-moctapp-1943.