MCI Constructors, Inc. v. District Court of Pueblo County

799 P.2d 40, 14 Brief Times Rptr. 1385, 1990 Colo. LEXIS 666, 1990 WL 153209
CourtSupreme Court of Colorado
DecidedOctober 15, 1990
Docket90SA247
StatusPublished
Cited by6 cases

This text of 799 P.2d 40 (MCI Constructors, Inc. v. District Court of Pueblo County) is published on Counsel Stack Legal Research, covering Supreme Court of Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MCI Constructors, Inc. v. District Court of Pueblo County, 799 P.2d 40, 14 Brief Times Rptr. 1385, 1990 Colo. LEXIS 666, 1990 WL 153209 (Colo. 1990).

Opinions

Justice ERICKSON

delivered the Opinion of the Court.

This case is an original proceeding under C.A.R. 21 to prohibit the trial court from enforcing a contempt citation against the petitioner, MCI Constructors (MCI). On June 7, 1990, this court issued a Rule to Show Cause and stayed enforcement of the contempt citation. We now make the rule absolute and direct the trial court to conduct further proceedings consistent with this opinion.

MCI Constructors is a general contractor that contracted to work on a project known as the Pueblo Wastewater Treatment Plant. In November 1986, MCI hired Chapman Construction (Chapman) as a subcontractor on the project. A year later, Chapman hired Judith Ward Mattox as counsel and filed an action against MCI alleging breach of contract.

MCI filed counterclaims for breach of contract and failure to timely perform the contract. On February 15, 1989, the president of MCI and the president of Chapman entered into a “release and settlement agreement.” Neither party’s attorneys were present. The agreement, which was subscribed, sworn to, and duly acknowledged by Chapman and MCI on February 15, 1989, provided that MCI would pay Chapman $150,000 in exchange for Chapman’s release of all claims and liens against MCI, indemnification of MCI, and dismissal of the underlying law suits. MCI placed the $150,000 in escrow and, on March 17, 1989, informed Chapman it was ready and willing to perform the settlement agreement.

On April 6, 1989, Mattox filed a Notice of Intent to Enforce Attorney’s Lien as provided by section 12-5-119, 5 C.R.S. (1985). That notice was served on all parties and did not specify the property on which she was asserting her attorney’s lien. Four days later, Mattox filed a motion to withdraw as counsel, presumably because her client had entered into the settlement agreement without her knowledge or participation. That motion was granted on September 8, 1989.

On September 26, 1989, the district court granted MCI’s motion for summary judgment, based on the settlement agreement, and dismissed the underlying action with prejudice. Chapman Constr. Co., Inc. v. MCI Constructors, Inc., 87CV1065. The settlement agreement, which was the basis for the summary judgment, provided in part:

THE UNDERSIGNED further deposes and says that all labor, materials, services, supplies, equipment, etc. furnished by the undersigned will be fully paid for [42]*42prior to the final release of funds from the referenced escrow.
*IT IS UNDERSTOOD AND AGREED, that the settlement amount will be held in escrow at the law firm of Watt, Tied-er, Killian & Hoffar and that said funds will be released pursuant to the applicable laws and upon the receipt of final lien waivers from H.E. Chapman’s vendors and subcontractors. These lien waivers shall include those from the following companies:
SMELKER CONCRETE
WACO SCAFFOLD & EQUIPMENT
MPM CONSTRUCTION
SYMONS FORMS
GRANT RENTAL
CBS LUMBER
IT IS UNDERSTOOD that MCI Constructors will assume the liability for final settlement of Chapman’s subcontractor Nicholson Steel Erectors only.

At that time, Chapman had not performed any of its obligations under the settlement agreement. It is undisputed that Chapman has not provided the lien waivers from the listed vendors and subcontractors.1

Mattox filed a Petition for Enforcement of Attorney’s Lien on December 22, 1989. In that petition, Mattox stated that “By the terms of the Settlement Agreement, the Plaintiff [Chapman] is entitled to receive the sum of $150,000, which amount constitutes money to which a lien attaches [under sections 12-5-119 and 12-5-120]_” Mattox did not address whether her ex-client had performed the terms of the agreement. MCI filed a response claiming that Chapman was not entitled to the escrow amount since it had breached the settlement agreement. MCI also claimed that the failure of Chapman to pay its subcontractors or release MCI resulted in the subcontractors filing claims directly against MCI. Subsequently, United States Fidelity and Guaranty Co. intervened claiming that it had an interest in the escrow amount to satisfy an unrelated judgment against Chapman.

On February 20, 1990, the district court granted Mattox’s petition for the enforcement of attorney’s lien in the following order:

That the former Counsel for Plaintiff’s Petition for Enforcement of Attorney’s Lien is hereby granted, subject to proof that the requested amount is reasonable and owed by Plaintiff.
The Court finds that the Petitioner Attorney has filed, and certified service upon the Plaintiff, an itemized statement of account for services rendered and an affidavit of services rendered, which statement and affidavit appear to be proper in form.
It is further Ordered that Plaintiff, H.E. CHAPMAN CONSTRUCTION CO, INC, shall have twenty (20) days from its receipt of this Order to respond in writing to this Court contesting that the amount requested is owed and/or that the amount requested is not reasonable or necessary. In the event that no such response is filed by the Plaintiff, the Court may enter an Order directing that the requested amount be paid to Petitioner Attorney.

The court did not address whether Chapman was entitled to all or any part of the escrow account, or MCI’s arguments that the settlement agreement had been breached. On MCI’s motion for clarification, the court simply stated that Mattox had shown that the fees were reasonable, and that MCI was “ordered to pay to Judith Ward Mattox the amount of $44,277.75 from the funds held in escrow in settlement of the above captioned matter, such payment to be made within ten (10) days after the date [43]*43of this order.” That order was dated March 22, 1990.

Rather than pay Mattox, MCI advised the court on April 2, 1990, that because Chapman had breached the agreement and had not provided the requisite lien waivers, and because there were competing claims for the escrow amount, the escrow trustee was directed to “immediately interplead the $44,277.75 into the registry of this Court in order to protect the interests of all concerned parties.” The interpleader action was filed March 30, 1990.

Mattox thereafter filed a motion for a contempt citation, and that motion was granted on May 31, 1990. The court stated that the settlement agreement was fulfilled when the court granted summary judgment and dismissed the suits. The court did not address or allude to the other conditions of the agreement. The court then found MCI in contempt, and ordered it to pay a $1,000 per day penalty until it complied with the order to pay Mattox.

MCI subsequently brought this original proceeding to prevent the district court from enforcing its March, 22, 1990, order requiring MCI to pay Mattox, and its May 31, 1990, contempt order. We issued a Rule to Show Cause on June 7, 1990, and granted MCI’s motion to stay the contempt order.

I.

MCI argues that the district court abused its discretion in granting the lien and then subsequently issuing the contempt citation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Granite v. Scheid
Colorado Court of Appeals, 2025
Davis v. Kutak Rock
560 F. App'x 756 (Tenth Circuit, 2014)
Berger v. Dixon & Snow, P.C.
868 P.2d 1149 (Colorado Court of Appeals, 1993)
MCI Constructors, Inc. v. District Court of Pueblo County
799 P.2d 40 (Supreme Court of Colorado, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
799 P.2d 40, 14 Brief Times Rptr. 1385, 1990 Colo. LEXIS 666, 1990 WL 153209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mci-constructors-inc-v-district-court-of-pueblo-county-colo-1990.