McGrew Machine Co. v. One Spring Alarm Clock Co.

245 N.W. 263, 124 Neb. 93, 1932 Neb. LEXIS 315
CourtNebraska Supreme Court
DecidedNovember 17, 1932
DocketNo. 28292
StatusPublished
Cited by8 cases

This text of 245 N.W. 263 (McGrew Machine Co. v. One Spring Alarm Clock Co.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGrew Machine Co. v. One Spring Alarm Clock Co., 245 N.W. 263, 124 Neb. 93, 1932 Neb. LEXIS 315 (Neb. 1932).

Opinion

Paine, J.

Plaintiff, who was the appellant in this court, sued defendant and appellee for $7,484.14, due upon certain contracts to manufacture and deliver parts of its one spring alarm clock. Defendant claimed the parts furnished were not made according to specifications, and were of no value whatever, and in a cross-petition defendant asks judgment against plaintiff in the sum of $17,399.43. The jury returned a verdict for the plaintiff in the sum of $1,000, for which amount judgment was entered on October 8, 1931, with 7 per cent, interest. Plaintiff, being dissatisfied with the verdict returned in its favor, filed a motion for new trial, setting out 57 errors therefor. From an overruling of the motion for new trial, plaintiff gave a supersedeas bond of $400 and appealed to this court to reverse and set aside said verdict and judgment.

In this case we find the record is very extensive, with 153 pages of briefs, three volumes in the transcript and bill of exceptions, with a fourth heavy volume of blueprints and order sheets, and a large box of exhibits of parts of, and also complete, alarm clocks. It would take many pages in this opinion to give a complete synopsis of the pleadings and the evidence set out in this mass of material, and if this opinion is to be kept down to an acceptable length it must be limited to a brief summary.

A. F. Kendle, who had resided in Syracuse, Nebraska, for 30 years, and was a jeweler and watchmaker by pro[95]*95fession, invented a one spring alarm clock, after working ■on it for six or eight years, and made by hand an excellent working model. The Reliance Die Shop in Chicago under his direction completed certain parts thereof, and a number of his friends then organized at Syracuse the One Spring Alarm Clock Company, the defendant herein, for the manufacture and sale of this new clock. Negotiations were begun with the plaintiff company for the purpose of manufacturing dies, from which parts could be made, and also of perfecting and manufacturing the various parts of the same, so that this clock could be put out on a commercial basis. After several years, the relations between the companies became very unsatisfactory, and the plaintiff brought suit in Otoe county.

The petition sets out several causes of action, the first one being upon an oral agreement entered into prior to January 14, 1929, to perform certain services on a cost plus basis, which services were performed and goods furnished amounting to $2,111.51. It is admitted that payments were received of $769.45, leaving a balance due thereon of $1,342.06.

For a. second cause of action, the plaintiff sáid there was a balance of $2,373.58 due under a written contract dated April 2, 1929, for special dies, limit gauges, and wheels. For answer to this, the defendant stated that it had paid $8,000 to Chicago die makers for dies which were delivered to the plaintiff, and that the parts made.by plaintiff were not up to standard in material and workmanship, or according to the specifications, and said articles were refused, and denied there was anything due thereon.

In its third cause of action, plaintiff sued for 2,000 sets of parts of the one spring alarm clock, at a cost of $1.30 a set, a total of $2,600, upon which $200 was paid, leaving $2,400 due. The defendant, for answer to this, alleged that the plaintiff did not use material equal to the material in the model clock, and, of the sets furnished, only 200 were used, which, however, the defendant was compelled to work over by hand before they would meet the specifi[96]*96cations and requirements, or could be used, and that the other sets, 1,800 .sets, were returned to the plaintiff as unsatisfactory.

The plaintiff’s fourth cause of action was for certain pinion wire, which, it is alleged, the defendant had agreed to take off plaintiff’s hands if it was not entirely used, and ■that there was $944.40 due for the value of the wire left on plaintiff’s hands, which facts defendant denies. Plaintiff, therefore, sues for a total sum of $7,484.14.

The defendant, in its cross-petition, claims that all payments made by it were made under a written contract, being exhibit 2, dated April 2, 1929, under which the plaintiff company agreed to make all dies required for the 12 wheels for a sum not to exceed $2,500, to make special tools for the Brown & Sharp, automatic screw machine for not to exceed $500, to make limit gauges for not to exceed $800, which sums the defendant agreed to pay in part payments as the work progressed, and alleged that the plaintiff agreed that all work would be according to specifications, and would guarantee the same .as to material and workmanship, and that ofily when the tools and dies were completed and approved would the unpaid balance be due and payable. Defendant alleges that, as the plaintiff failed to turn out satisfactory work, there has been a complete failure of performance under the contract, exhibit 2, and that, except fdr $81.98,’ express charges paid, and $13.32 for telephone calls, all other payments made under the terms of exhibit 2 should be returned to the defendant for entire failure under the terms of the contract, and that therefore the defendant is entitled to recover the sum of $2,339.43.

The plaintiff, for answer to the first cause of action of defendant’s cross-petition, alleges that all dies and tools were made of first grade materials, and perfectly performed the operations for which they were intended, and that part of the money paid to the plaintiff was for extra work not provided in the contract, exhibit 2, and denied all other allegations.

[97]*97At the close of the evidence, the court withdrew from the jury the second, third, and fourth causes of action of the defendant’s cross-petition, on the ground of failure of evidence to support the same.

This brief statement is a mere outline of the voluminous pleadings, and will indicate the many issues contested and the wide scope of the evidence taken in support thereof.

The trial judge gave some 12 instructions, which covered all the issues involved in a fairly satisfactory manner, and in his refusal to give 17 additional instructions requested by the plaintiff is based a large, number of the errors set out.

1. Plaintiff claims that the jury entirely disregarded the evidence and the instructions, and returned a verdict not supported by either, and that a new trial must be granted.

As one ground for reversal, the plaintiff insists that, by returning a general verdict, the jury necessarily found in favor of the plaintiff on every material issue raised in the pleadings, including all four causes of action.

Defendant insists that the verdict of $1,000 conclusively establishes the contrary. Upon the return of the verdict, the plaintiff did not except to it, but the defendant claims it excepted to it for the reason that it did not find the amount allowed the defendant upon its set-off, and moved the court that the jury be required to correct the verdict in this respect, which motion was overruled.

In Everson v. Graves, 26 Neb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradley T. Ex Rel. D.T. v. Central Catholic High School
653 N.W.2d 813 (Nebraska Supreme Court, 2002)
Zanakis-Pico v. Cutter Dodge, Inc.
47 P.3d 1222 (Hawaii Supreme Court, 2002)
Hiway 20 Terminal, Inc. v. Tri-County Agri-Supply, Inc.
454 N.W.2d 671 (Nebraska Supreme Court, 1990)
Melcher v. Boesch Motor Company
198 N.W.2d 57 (Nebraska Supreme Court, 1972)
Perkins v. Reynolds Construction Co.
247 So. 2d 118 (Court of Civil Appeals of Alabama, 1971)
Thompson v. Anderson
153 P.2d 665 (Utah Supreme Court, 1944)
Bosheck v. Gappa
279 N.W. 185 (Nebraska Supreme Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
245 N.W. 263, 124 Neb. 93, 1932 Neb. LEXIS 315, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgrew-machine-co-v-one-spring-alarm-clock-co-neb-1932.