McGinley v. WHEAT BELT PUBLIC POWER DIST.

332 N.W.2d 915, 214 Neb. 178
CourtNebraska Supreme Court
DecidedApril 29, 1983
Docket82-273
StatusPublished

This text of 332 N.W.2d 915 (McGinley v. WHEAT BELT PUBLIC POWER DIST.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGinley v. WHEAT BELT PUBLIC POWER DIST., 332 N.W.2d 915, 214 Neb. 178 (Neb. 1983).

Opinion

332 N.W.2d 915 (1983)
214 Neb. 178

Mike McGINLEY et al., Appellants,
v.
WHEAT BELT PUBLIC POWER DISTRICT, a public corporation and political subdivision of the State of Nebraska, et al., Appellees,
Richard W. Dunn et al., Intervenors-Appellees.

No. 82-273.

Supreme Court of Nebraska.

April 29, 1983.

*916 Wright, Simmons & Selzer, Scottsbluff, for appellants.

John Peetz, P.C., Sidney, for appellees Wheat Belt P.P. Dist. et al.

Steven C. Smith of Van Steenberg, Brower, Chaloupka, Mullin & Holyoke, Gering, for intervenors-appellees.

KRIVOSHA, C.J., BOSLAUGH, McCOWN, HASTINGS, and CAPORALE, JJ., and BRODKEY, J., Retired.

KRIVOSHA, Chief Justice.

The plaintiffs in this action, electric customers of Wheat Belt Public Power District, appeal from an order entered by the District Court for Cheyenne County, Nebraska, which dismissed their petition. Following the institution of the suit by the plaintiffs, certain other customers of Wheat Belt Public Power District intervened in the action and joined with Wheat Belt in defending the action. For reasons set out in this opinion, we reverse and remand.

The record reveals that Wheat Belt Public Power District is a public corporation and political subdivision created pursuant to Chapter 70, article 6, of the statutes of the State of Nebraska. As a public electric utility, it is one of 25 members of Tri-State Generation & Transmission Association, a multistate wholesale distributor of electric energy. Originally, Tri-State was a transmitting facility only, which acquired all of its power from the U.S. Bureau of Reclamation and, later, from Basin Electric Power Cooperative. Due to increasing load growth among its members, Tri-State exceeded its power allocations in the early 1970s and was faced with the decision whether to buy power from a third source or to become a generating facility. This load growth was primarily caused by an increased use of seasonal irrigation in the Tri-State area. The increased peak loads of *917 seasonal users resulted in voltage drops due to high loads and insufficient generating capacity.

In order to meet the rising power demands of its members and to stabilize voltage problems, Tri-State chose to become a generating facility and began construction of a peaking unit which would provide energy during periods of high seasonal demand. The unit was constructed at Wray, Colorado, and came on line in 1975. In 1977 Tri-State constructed a second peaking unit at Burlington, Colorado.

On February 3, 1975, Tri-State informed Wheat Belt that a surcharge or "ratchet" would be charged all customers of Tri-State, including Wheat Belt. Tri-State advised Wheat Belt that the ratchet would be assessed on the basis of Wheat Belt's summer peak demand. Wheat Belt considered three alternatives to deal with the imposed ratchet: (1) Refuse to add new irrigation customers and thereby stop irrigation growth; (2) Allocate the ratchet equally among all irrigation customers; (3) Create two classes of irrigation customers based on the date the customer requested service. The last alternative was apparently based upon Wheat Belt's notion that it was the new customers who were causing the increased summer peak demand, thereby causing the imposition of the ratchet.

On May 19, 1975, the Wheat Belt board of directors announced that there would be two classes of irrigation customers in the future. One class, called "Rate Class 75" would be all customers who were receiving service from Wheat Belt before February 3, 1975, or who had notified Wheat Belt before February 3, 1975, that they desired service and who were put in service before August 15, 1975. A second class, to be called "Rate Class 76," would consist of those customers put in service after August 15, 1975, that had not been committed to by February 3, 1975. The rationale for the subclassification was to protect the old customers from having to pay any increased cost associated with Tri-State's construction of the peaking units, on the theory that they "were not creating a major problem." Because the members of Rate Class 76 were assessed the greatest portion of the ratchet, the rates for similar service for the two classes of customers were significantly different. The evidence discloses, as an example, that in 1976 the charge per horsepower for members of Rate Class 75 was $.39, while the members of Rate Class 76 obtaining identical service paid $5.02 per horsepower. This difference continued throughout the years, and in 1981, while the members of Rate Class 75 consumed 31,830.5 horsepower, their charge per horsepower was only $5.75, while members of Rate Class 76, who used 11,198 horsepower, were charged a rate of $17.15 per horsepower. The evidence conclusively established that the only difference between consumers in Rate Class 76 and those in Rate Class 75 was the date upon which they requested service. The consumptive characteristics of both classes were shown to be similar in all respects. Both classes of customers raised similar crops in the same geographical area, used the energy in the same way, and had identical energy and horsepower demand charges assessed. While Wheat Belt maintained that there were higher horsepower motors used by consumers in Rate Class 75, it was demonstrated that there are almost as many high horsepower motors in Rate Class 76 as there are in Rate Class 75. The load factor was also shown to be the same for the two classes and, despite the fact that members of Rate Class 75 were placed on a voluntary, unmonitored rotation schedule in which each well was to be operated only 2 out of 3 days, there was evidence that both classes were irrigating in the same way and that many Rate Class 75 customers simply did not comply with the rotation policy. The evidence further disclosed that in addition to allocating the principal portion of the ratchet to consumers in Rate Class 76, Wheat Belt also allocated a ratchet-free block of U.S. Bureau of Reclamation power only to consumers in Rate Class 75.

The plaintiffs presented expert testimony at trial regarding the propriety of the ratchet allocation formula used by Wheat Belt. Donald Salow, a consulting engineer *918 specializing in utility operations and rate setting, testified that customers in both Rate Class 75 and Rate Class 76 receive equal benefits from construction of the peaking unit. After analyzing the two rate classes Salow concluded that there were no differences in cost of service which would warrant this disproportionate ratchet allocation. In addition, Wheat Belt's practice of allocating the benefit of ratchet-free Bureau of Reclamation power entirely to Rate Class 75 was characterized by Salow as a "deviation" from the norm that was, in his opinion, unfair and unreasonable. He also testified that if none of the Tri-State members had added new customers or had little or no load growth after the peaking units were constructed, the existing customers would have simply paid for the debt retirement through higher energy and demand charges.

Henry Rice, a consulting engineer and former employee of Nebraska Public Power District, testified that exit and entry into a system should make no difference between customers who take similar service under similar conditions. In his opinion, the present ratchet allocation between Rate Class 75 and Rate Class 76 was neither proper, reasonable, fair, nor nondiscriminatory.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Ex Rel. Utilities Commission v. Mead Corp.
78 S.E.2d 290 (Supreme Court of North Carolina, 1953)
Contractors & Builders Ass'n v. City of Dunedin
329 So. 2d 314 (Supreme Court of Florida, 1976)
Noble v. City of Lincoln
63 N.W.2d 475 (Nebraska Supreme Court, 1954)
City of Scottsbluff v. United Tel. Co. of the West
106 N.W.2d 12 (Nebraska Supreme Court, 1960)
Erickson v. Metropolitan Utilities District
107 N.W.2d 324 (Nebraska Supreme Court, 1961)
York County Rural Public Power District v. O'CONNOR
111 N.W.2d 376 (Nebraska Supreme Court, 1961)
United States Steel Corp. v. Commonwealth
390 A.2d 849 (Commonwealth Court of Pennsylvania, 1978)
United Gas Corp. v. Shepherd Laundries Inc.
189 S.W.2d 485 (Texas Supreme Court, 1945)
State ex rel. Randall v. Hall
249 N.W. 756 (Nebraska Supreme Court, 1933)
City of Omaha v. Douglas County
251 N.W. 262 (Nebraska Supreme Court, 1933)
Cornhusker Electric Co. v. City of Fairbury
270 N.W. 482 (Nebraska Supreme Court, 1936)
Best & Co. v. City of Omaha
33 N.W.2d 150 (Nebraska Supreme Court, 1948)
McGinley v. Wheat Belt Public Power District
332 N.W.2d 915 (Nebraska Supreme Court, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
332 N.W.2d 915, 214 Neb. 178, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcginley-v-wheat-belt-public-power-dist-neb-1983.