McGaughy v. City of Memphis

823 S.W.2d 209
CourtCourt of Appeals of Tennessee
DecidedJuly 24, 1991
StatusPublished
Cited by10 cases

This text of 823 S.W.2d 209 (McGaughy v. City of Memphis) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McGaughy v. City of Memphis, 823 S.W.2d 209 (Tenn. Ct. App. 1991).

Opinion

CRAWFORD, Judge.

Defendants, City of Memphis and Memphis Light, Gas & Water Division (hereinafter referred to as MLG & W or Defendants) appeal from the judgments of the trial court awarding money damages to plaintiffs in three cases (consolidated for trial) brought pursuant to the Governmental Tort Liability Act. Wrongful death actions were filed for the deaths of Brian K. Melton and Robert Elrod and a personal injury action was filed by plaintiff Elbert McGaughy.

The complaints as amended allege that plaintiffs’ decedents and plaintiff respectively (hereinafter referred to collectively as Plaintiffs), employees of the subcontractor, Madison Steel, were working with a crane in the course of their employment, building a structure on property owned by Weyerhaeuser, Inc., when a beam lifted by the crane came into contact with a high voltage wire over said property. Plaintiffs allege that defendant MLG & W failed to give safety recommendations and guidance to the contractor building the structure and the land owner, that it negligently failed to temporarily relocate, elevate or otherwise shield invitees from the energized lines, that said wires were improperly insulated or not insulated at all and that a dangerous situation was created without notice to the Plaintiffs and their employers. The complaint further avers that MLG & W violat[211]*211ed regulations applicable under the American National Standard Electrical Safety Code adopted under T.C.A. § 68-16-104. Plaintiffs also allege that Tom Lindsey, employee and agent of MLG & W failed to warn all interested parties of the dangers of the power lines, failed to have the lines de-energized or otherwise shielded from contact and failed to take all reasonable precautions to avoid harm from the lines.

MLG & W’s answer denies the material allegations of the complaint and joins issue thereon. It denies that it was guilty of any negligence or the breach of any duty and avers that it complied with all safety codes in the installation and maintenance of the electrical lines in question. It avers that the accident was caused by the independent intervening act of the crane operator and by the contributory negligence of Plaintiffs.

We will briefly review the evidence as pertinent to the issues before the Court. The accident occurred at Weyerhaeuser’s distribution center, where, among other things, the company maintained lumber storage facilities. It was stipulated that on December 11, 1984, the crane, operated by Plaintiffs’ employer, lifted a 39 foot steel beam in the course of constructing a storage shed, and the steel beam came into contact with a power line carrying 13,280 volts of electricity which was maintained by MLG & W, and that this caused the death of Elrod and Melton and the injury to McGaughy. The Weyerhaeuser property is essentially rectangular in shape, with the longer portion of the rectangle extending north and south and a railroad track running along the western border. Also running along the western border, and along the railroad track, are electrical wires carrying high voltage currents which are not the wires involved in the instant case. The power line involved in the instant case, built in 1968, put in service about January, 1969, crosses the Weyerhaeuser property approximately in the middle of the rectangle and connects with the north/south power lines bordering the railroad track. This is a noneasement power line, built over the private property of Weyerhaeuser.

In early 1984, Weyerhaeuser’s branch manager, Kenneth Taylor, was considering expansion of a storage shed facility, and a proposed bidder on the project, Throgmor-ton, arranged for a representative of MLG & W to meet with him and Taylor concerning the location of the proposed addition. At that time, the discussion concerned the proposed storage shed to be built along the western property line and involved the power lines running along the railroad track. The location of this building, as proposed by Taylor, was underneath the north/south power lines, and some discussion was had as to moving the wires and who would be responsible for this expense. Based on the discussions, Mr. Taylor decided it would not be feasible to have the wires moved, but that he should instead move the shed. Apparently, there was no discussion concerning the east/west line which is involved in the instant case.

Subsequently, bid packages were submitted to proposed bidders which included a general site location drawing, showing the approximate location of the building in relation to the north/south power lines and the east/west power line involved in this case. The bid package, among other things, stated: “It is the responsibility of the contractor to contact the local power company to de-energize, to insulate or to move the lines. The contractor is to be fully responsible to alert his employees or subcontractors to the dangers of all surrounding power lines both above and below the ground.” The subcontract was subsequently let to C & I Contractors.

A building permit was obtained from the Shelby County Office of Construction Code Enforcement which indicated the proposed building was to be located between two existing power poles at the west side of the building parallel to the power lines. The building was to be 7,200 square feet, measuring 40' X 80' and have a height of 24 feet. The permit file indicated that a power line existed on the south end of the building, but the distance from the building is not shown. It should be noted that the power line was not located in an easement.

[212]*212Kenneth Taylor, the Weyerhaeuser branch manager, testified that he had been with the company for 31 years and that the operation at this location had tripled in volume during that time. He testified that the lumber in the storage facility is stacked to a maximum height of 24 feet and they do stack the lumber under the power lines crossing the property. He recalled the meeting with Tom Lindsey at Weyerhaeu-ser in May, 1984, and he testified that he received advice from Lindsey regarding the wires that run along the railroad track and stated that at no time was there any discussion concerning the wires that were actually involved in the accident. After talking with Lindsey, Taylor knew that he could not place the building under the north/ south power lines and decided to move the building rather than incur the expense of moving the power lines. He explained the invitation for construction bids and the stipulation that it was the contractor’s responsibility to take care of the power lines. He testified that the exact location of the building was to be worked out by the contractor in the field and that he did not participate in that. He did tell the contractor that he should not push the limits and if a minimum distance was required they could leave a slightly larger cushion. When Mr. Lindsey left the meeting with Taylor and Throgmorton in May of 1984, Taylor’s understanding was that he had learned everything he needed to know about dealing with the power lines in the proposed construction. It was established in his testimony that in day to day operations, lumber is stacked under the wires, but the stacks are at least ten feet below the wires.

Plaintiffs also introduced into evidence the discovery deposition of Clarence Woo-dell, a supervisor of distribution in the electrical distribution office of MLG & W. He testified that at the time of the accident it was his understanding that Lindsey was a designer.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ward v. City of Lebanon
273 S.W.3d 628 (Court of Appeals of Tennessee, 2008)
Norman Hamby v. State of Tennessee
Court of Appeals of Tennessee, 2004
Norman Hamby v. State
Court of Appeals of Tennessee, 2002
Burton v. Carroll County
60 S.W.3d 829 (Court of Appeals of Tennessee, 2001)
Sabrina Burton v. Carroll Co.
Court of Appeals of Tennessee, 2000
Richard Deberry v. Lexington Electric System
Court of Appeals of Tennessee, 1997
Collins v. Metro Gov't
Court of Appeals of Tennessee, 1997
Roe v. Catholic Diocese of Memphis, Inc.
950 S.W.2d 27 (Court of Appeals of Tennessee, 1996)
Alfred Carroll Jones and Betty Jones v. City of Johnson City, Tennessee
917 S.W.2d 687 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
823 S.W.2d 209, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcgaughy-v-city-of-memphis-tennctapp-1991.