McEwen v. Burlington Northern Railroad

494 N.W.2d 313, 1992 Minn. App. LEXIS 1282, 1993 WL 508
CourtCourt of Appeals of Minnesota
DecidedJanuary 5, 1993
DocketC5-92-1148
StatusPublished
Cited by4 cases

This text of 494 N.W.2d 313 (McEwen v. Burlington Northern Railroad) is published on Counsel Stack Legal Research, covering Court of Appeals of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McEwen v. Burlington Northern Railroad, 494 N.W.2d 313, 1992 Minn. App. LEXIS 1282, 1993 WL 508 (Mich. Ct. App. 1993).

Opinions

OPINION

KALITOWSKI, Judge.

Appellant Maxine L. McEwen, as trustee for the heirs of Ruth Lysford, challenges the trial court’s decision that her claims against respondent State of Minnesota in this wrongful death action are barred by statutory and discretionary immunity pursuant to Minn.Stat. §§ 219.402 and 3.736, subd. 3(b) (Supp.1985).

FACTS

On the afternoon of July 5, 1986, an automobile driven by Hjalmer Lysford with [315]*315Ruth Lysford as a passenger collided with a train at a grade crossing on Trunk Highway 32 in Dugdale. Mr. and Mrs. Lysford died as a result of injuries caused by the collision.

The Dugdale crossing was a single track, mainline crossing, protected by active flashing light signals and stop signs that rotated to face traffic when the signals were activated by an approaching train. Advance warning signs were also in place 866 feet south of the crossing.

In addition to the flashing light signals, the Dugdale crossing usually exhibited a pavement marking. However, ten days before the collision, that marking was obliterated during a spot pavement overlay project. The marking was not repainted until July 9, 1986, four days after the accident.

In support of its motion for summary judgment on a claim challenging the adequacy of the warning devices, the state submitted an affidavit by an official at the Minnesota Department of Transportation (DOT). According to the affiant, the flashing light signals were installed at the Dug-dale crossing in 1957 pursuant to order of the Railroad and Warehouse Commission. Since then, the crossing has not been identified as warranting evaluation for upgrading, no complaints have been filed regarding the crossing and no highway construction projects have involved the crossing. Further, the affiant asserted that in the ten years prior to this accident, there has been only one other automobile-train collision at the crossing, which resulted from the driver’s admitted inattention to the flashing signals.

The state also submitted evidence that the crossing has not merited review under the state’s hazard index rating (HIR) priority system. That system assigns each railroad crossing a priority number based on a formula which considers the amount of vehicular and train traffic, the number of accidents which have occurred at the crossing, and the type of warning devices already in place at the crossing. Due to the limited funds available for improving warning devices at railroad crossings, only those crossings that receive a high number under the HIR priority system are evaluated for upgrading. At no time has the Dugdale crossing’s priority number been high enough to merit review under this system.

In 1984, the DOT established a corridor review system to examine the need for railroad crossing improvements. A study of corridor 6, which includes the Dugdale crossing, determined that the flashing lights were adequate for the crossing and that gates and/or cantilevers were not necessary. In making this determination, the DOT weighed the need for gates and/or cantilevers at the crossing against the need to upgrade other crossings in this and other corridors. A 1987 review reaffirmed that gates and cantilevers were not necessary at the Dugdale crossing.

In support of its motion for summary judgment on the claim for failure to provide pavement markings in advance of the crossing, the state submitted an affidavit by a district traffic engineer for the DOT. According to the affiant, the district generally delays repainting of pavement markings obliterated during spot overlay projects “for at least a week and preferably two weeks” in order to allow the new pavement to cure. If pavement is not cured before repainting, the paint will soak into the pavement and obliterate the message, necessitating a second repainting. The af-fiant further states that immediate repainting of pavement markings “would double the amount of time involved in painting the messages and delay other priority painting needs along with a negative impact on already limited resources.”

While the spot overlay project at the Dugdále crossing was completed on June 25, 1986, the markings were not repainted until July 9, because the painting crew was on vacation and holiday leave over the July 4 weekend. The affiant stated that the policy of scheduling vacation over the July 4 weekend allows the painting crew to work continually through the rest of the summer. He further explained that undertaking painting projects over the holiday weekend, when traffic along the highway is at its highest, would result in a greater number of accidents, increased danger to [316]*316the painting crew, and increased problems in traffic flow, and would require the hiring of extra personnel or the paying of overtime wages.

ISSUES

1. Did the district court err in concluding the claim of inadequate warning device is barred either by statute or by discretionary immunity?

2. Did the district court err in concluding the state’s decision to delay repainting the pavement marking is subject to discretionary immunity?

ANALYSIS

Summary judgment is properly granted

if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that either party is entitled to a judgment as a matter of law.

Minn.R.Civ.P. 56.03. A governmental entity may be entitled to summary judgment if its actions are entitled to immunity. See Ostendorf v. Kenyon, 347 N.W.2d 834, 836 (Minn.App.1984). However, where factual disputes exist as to whether a governmental decision is entitled to immunity, summary judgment may not be appropriate. See Schaeffer v. State, 444 N.W.2d 876, 880 (Minn.App.1989) (denial of summary judgment affirmed when governmental entity failed to produce evidence that its decisions regarding the design, installation, and maintenance of freeway guardrail were immune).

In deciding whether immunity applies, this court must identify the precise governmental conduct or decision being challenged. See Nusbaum v. County of Blue Earth, 422 N.W.2d 713, 722 (Minn.1988). Thus, each governmental decision or act will be examined separately to determine whether immunity applies.

I.

The acts appellant challenges in her warning device claim are: (1) the maintenance of inadequate devices at the Dugdale crossing; and (2) the failure to upgrade and install crossing gates or cantilever lights at the crossing.

The first challenged act is within the plain language of Minn.Stat. § 219.402 (Supp.1985):

Crossing safety devices or improvements installed or maintained under this chapter as approved by the board, whether by order or otherwise, are adequate and appropriate protection for the crossing.

The state established that the Dugdale crossing signals were installed in 1957 pursuant to order of the Railroad and Warehouse Commission, a predecessor to the DOT, and that subsequent reviews of the signals have determined that the signals remain adequate. Thus, under Minn.Stat.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Gary William Frieler v. BNSF Railway Company
Court of Appeals of Minnesota, 2014
Archon v. Union Pacific RR
657 So. 2d 987 (Supreme Court of Louisiana, 1995)
Gutbrod v. County of Hennepin
529 N.W.2d 720 (Court of Appeals of Minnesota, 1995)
McEwen v. Burlington Northern Railroad
494 N.W.2d 313 (Court of Appeals of Minnesota, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
494 N.W.2d 313, 1992 Minn. App. LEXIS 1282, 1993 WL 508, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcewen-v-burlington-northern-railroad-minnctapp-1993.