McCormick v. Luke Collison Drywall & Constr., L.L.C.

2022 Ohio 4260
CourtOhio Court of Appeals
DecidedNovember 28, 2022
Docket2021 CA 00036
StatusPublished
Cited by1 cases

This text of 2022 Ohio 4260 (McCormick v. Luke Collison Drywall & Constr., L.L.C.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCormick v. Luke Collison Drywall & Constr., L.L.C., 2022 Ohio 4260 (Ohio Ct. App. 2022).

Opinion

[Cite as McCormick v. Luke Collison Drywall & Constr., L.L.C., 2022-Ohio-4260.]

COURT OF APPEALS FAIRFIELD COUNTY, OHIO FIFTH APPELLATE DISTRICT

KENDRA McCORMICK, et al. JUDGES: Hon. William B. Hoffman, P.J. Plaintiffs-Appellants/Cross-Appellees Hon. John W. Wise, J. Hon. Patricia A. Delaney, J. -vs-

LUKE COLLISON DRYWALL & Case No. 2021 CA 00036 CONSTRUCTION LLC

Defendant-Appellee/Cross-Appellant OPINION

CHARACTER OF PROCEEDING: Civil Appeal from the Court of Common Pleas, Case No. 2020 CV 00001

JUDGMENT: Dismissed

DATE OF JUDGMENT ENTRY: November 28, 2022

APPEARANCES:

For Plaintiffs-Appellants/Cross-Appellees For Defendant-Appellee

BRUCE M. BROYLES DAVID W. ORLANDINI 1379 Standing Stone Way SUNNY L. HORACEK Lancaster, Ohi 43130 DAVID G. JENNINGS 655 Metro Place South, Suite 200 Dublin, Ohio 43017

For Defendant-Appellee/Cross Appellant

JEFFREY B. SAMS 10400 Blacklick Eastern Rd. NW, Suite 140 Pickerington, Ohio 43147 Fairfield County, Case No. 2021 CA 00036 2

Wise, J.

{¶1} Appellants Kendra McCormick and McCormick Farms, LLC appeal the

September 21, 2021, decision of the Fairfield County Court of Common Pleas granting

partial summary judgment in favor of Appellee Luke Collison Drywall & Construction, LLC

and the November 5, 2021, decision granting judgment in favor of Appellee on its

counterclaim after a bench trial.

STATEMENT OF THE FACTS AND CASE

{¶2} This action arises from an agreement between Appellant Kendra

McCormick (McCormick) and Appellee Luke Collison Drywall & Construction LLC

(Collison) for the demolition of an existing structure, construction of a new home, and the

remodeling of an existing garage. The house was constructed on land owned by Appellant

McCormick Farms, LLC.

{¶3} The relevant facts and procedural history are as follows:

{¶4} On May 31, 2019, Collison submitted an estimate to McCormick detailing

the work to be completed for the demolition, new construction and remodeling.

McCormick signed this estimate on July 17, 2019. At McCormick's request, on August 18,

2021, Collison submitted to McCormick Change Order #1.

{¶5} Change Order #1 detailed additional work McCormick requested to be

completed on the project, included an updated draw schedule, and contained a new grand

total for the agreed upon work of $246,000. On August 25, 2019, McCormick signed

Change Order #1, including the updated draw schedule and grand total.

{¶6} On August 12, 2019, McCormick paid Collison a $20,000 draw for the

demolition of the existing home and new foundation work. McCormick raised issues Fairfield County, Case No. 2021 CA 00036 3

regarding the design of the new home when Collison began work performing framing and

installing windows on the new structure.

{¶7} On September 10, 2019, McCormick expressed concerns that she still had

a lot of questions about the design of the home. At that point, Collison suggested that

they leave the project and that McCormick could pay for the work already completed.

{¶8} On September 13, 2019, McCormick paid Collison $65,000 for framing and

window installation. The total amount paid by McCormick to Collison for work completed

on the project was $85,000.

{¶9} Collison continued to perform work that included completing siding and

roofing of the new home and remodeling the existing garage.

{¶10} On October 4, 2019, McCormick requested a two-week delay on the project

to facilitate farming operations occurring on the property. Even though a delay was not

contained in the parties' agreement and any delay would have-implications for the cost

and the schedule of the project, Collison complied and stopped work on the project.

Collison indicated to McCormick that bills on the project would be coming due soon.

{¶11} Similar delays had occurred earlier in the project at McCormick's request,

including a delay of 12 days around the time the parties agreed to Change Order #1.

{¶12} On October 7, 2019, during the two-week delay, Collison requested a draw

of $52,400. The draw request consisted of a draw of $30,000 that was due when

siding/roofing was complete, and a draw of $24,000, less a $1,600 credit, that was due

upon completion of the garage remodeling. When requesting the draw from McCormick,

Collison indicated the draw was needed in order to make payments on labor and material

for the home that were due on October 10, 2019. Fairfield County, Case No. 2021 CA 00036 4

{¶13} Having not received payment for the requested draw, Collision inquired

again on October 10, 2019. McCormick stated that she was unable to pay the draw as

she was sick and her mother was in the hospital, but that she would contact Collison the

following day.

{¶14} On October 12, 2019, still having not paid the draw, McCormick requested

all work stop on the project until she was able to sell her existing home, which ultimately

did not occur until December 2019.

{¶15} On October 13, 2019, Collison removed their equipment, tools, and

materials from the project site.

{¶16} Subsequently, Plaintiff Kendra McCormick arranged for the project to be

completed by another contractor.

{¶17} On January 2, 2020, Appellants Kendra McCormick and McCormick Farms,

LLC filed a Complaint against Appellee Luke Collison Drywall & Construction LLC in the

Fairfield Court of Common Pleas, alleging five (5) claims for relief: (1) breach of contract,

(2) a violation of R.C. §4127.22, (3) slander of title, (4) abuse of process, and (5)

declaratory judgment.

{¶18} On March 2, 2020, Appellee filed its Answer and Counterclaim alleging that

Kendra McCormick breached the parties' contract and owes Appellee eighty-three

thousand dollars ($83,000.00), that it was entitled to be compensated based upon unjust

enrichment and quantum meruit, and that Appellant Kendra McCormick was liable for

fraud.

{¶19} On June 21, 2021, Appellee filed a motion for summary judgment. Fairfield County, Case No. 2021 CA 00036 5

{¶20} On July 14, 2021, Appellants filed their memorandum in opposition to

motion for summary judgment.

{¶21} By Judgment Entry filed September 21, 2021, the trial court granted partial

summary judgment in favor of Appellee. The trial court found that an implied contract for

the construction of the house existed between Appellee Luke Collison Drywall &

Construction, LLC and McCormick Farms, LLC, the owner of the real property. As a result,

Appellee's mechanic's lien on the real property of McCormick Farms, LLC was valid.

Therefore, the trial court granted summary judgment on the claims of slander of title,

abuse of process, and the request for declaratory judgment. The trial court also granted

summary judgment on Appellant Kendra McCormick's claim for breach of contract finding

that she could not demonstrate that the cost to complete the contract exceeded the

original contract amount. The trial court allowed Appellants' claim of a violation of R.C.

§4127.22 to remain for trial.

{¶22} Appellants proceeded on their claim for violation of R.C. Chapter 4722 and

Appellee proceeded on its Counterclaim. Prior to trial, Appellants and Appellee stipulated

to the violations of R.C. 4722, agreed that Appellants were not entitled to any actual

economic damages but was entitled to an award of nominal damages in the amount of

ten dollars ($10.00).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Guardianship of Dwyer
2024 Ohio 2544 (Ohio Court of Appeals, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
2022 Ohio 4260, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccormick-v-luke-collison-drywall-constr-llc-ohioctapp-2022.