McCarthy v. McArthur

63 S.W. 56, 69 Ark. 313
CourtSupreme Court of Arkansas
DecidedMay 11, 1901
StatusPublished
Cited by13 cases

This text of 63 S.W. 56 (McCarthy v. McArthur) is published on Counsel Stack Legal Research, covering Supreme Court of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McCarthy v. McArthur, 63 S.W. 56, 69 Ark. 313 (Ark. 1901).

Opinion

Battle, J.

J. S. McArthur and Wood Eainwater brought an action against J. H. McCarthy and George Eeiehardt, partners doing business under the firm name and style of McCarthy & Eeich-ardt, upon a contract in the words and figures following:

“Little Eock, Ark., November 29, 1898.

“Memorandum: It is agreed that James S. McArthur is to have the clearing of the right of way, subject to all conditions named in the Choctaw & Memphis specifications. He is to do 20 miles or more as hereafter agreed upon, and to work at such points as is necessary from time to time, for which we agree to pay $12 per acre. * * * No work will be estimated or paid for that is not in strict conformity to the requirements of the Choctaw & Memphis railroad specifications.

[Signed] “J. S. Mo Arthur,

“MoCaRti-iy & EeiohardtY

They alleged in their complaint that McCarthy & Eeiehardt and McArthur selected the 20 miles of the right of way of the Choctaw & Memphis Eailroad Company which was to be cleared by McArthur under the contract, and that McArthur at once entered upon the work of clearing the said 20 miles of right of way, and cleared the same to the extent of 13 miles,, in accordance with his contract, amounting to 144 acres, of the value of $1,738, of which $300 have been paid, and that there still remain due and unpaid $1,438.

McCarthy & Reichardt, answering, denied that he (McArthur) cleared 144 acres, and alleged that he cleared only 59.39 acres, for which they agreed to pay him at the rate of $13 per acre, making the sum of $664.68, and that they had paid him the sum of $300.

The jury that tried the issues in the action returned a verdict in favor of the plaintiffs for $1,031; and the defendants appealed.

The amount due the appellees for the work done depends upon the meaning of the words and figures, “$13 per acre” in the contract sued on. It appears from the evidence adduced in the.trial in this action that a large portion of the right of way which Mc-Arthur claims to have cleared passed through farms or open fields, where there was no or very little clearing to do, and that in many places in such farms or open fields he cut only an occasional tree or stump, and in some places did nothing. Appellees contend that they are entitled, for the work done by McArthur, to $13 per acre for the entire area covered by the right of way, without regard to the amount of work done in such farms or open fields; and appellants contend that appellees were entitled to $13 for each acre cleared where the forest had been undisturbed, and for the work done in farms and open fields in clearing the right of way they were entitled to the proportion of $13 that such work bore to that required to be performed in clearing the right of way where the forest was undisturbed.

Appellants offered evidence in the trial, in support of their contention, to prove that it was the general custom in this state to pay for work done in clearing the right' of way for railroads through farms and open fields the proportion of the contract price that such work bears to the' work to be done in clearing the right of way through the forest. To illustrate: Suppose the contract price was $40 an acre, and that the work of clearing the right of way through farms and open fields was one-tenth of- that done in clearing the same through the forest, $4 would be the price paid for the work done in the farms and fields, according to the custom. They offered to prove that this custom was in existence at the time the contract sued on was entered into, and had been for many years prior thereto, in this state and elsewhere. To the admission of this evidence the appellees interposed a general objection. The ground upon which the objection was based is not stated in the record, and we can consider it only as to the competency of the evidence. Railway Co. v. Murphy, 60 Ark. 333. The court sustained the objection, and refused to allow the evidence to be adduced, saying: “This is a suit upon a written contract. The price of the labor is fixed in the contract, and also the character of the labor to be done or performed is set out in the contract. Any extra or additional labor is not mentioned, and the court holds that custom and usage have no place in this suit upon this contract.”

The contract in question is not entirely free from ambiguity. Appellants agreed to pay McArthur $12 per acre for clearing the right of way for 20 miles. Does it mean that $12 an acre shall be paid for the acres actually cleared, or that the 20 miles, when entirely cleared, shall be paid for according to the number of acres contained in the same ? The 20 miles is not specified 'in the contract, but was to be thereafter “agreed upon.” Either construction can reasonably be placed upon the contract. Was the excluded evidence admissible ?

In speaking of usages and trade, Greenleaf says: “Their true office is to interpret the otherwise indeterminate intentions of parties, and to ascertain the nature of their contracts, arising not from express stipulation, but from mere implications and presumptions, and acts of doubtful and equivocal character, and to fix and explain the meaning of words and expressions of doubtful and various senses.” 2 Greenleaf, Evidence, § 251. Again he says: “But though usage may be admissible to- explain what is doubtful, it is not admissible to contradict what is plain.” Id. § 292.

In Oelricks v. Ford, 23 How. 63, it is said: “This proof is admissible in the absence of express stipulations, or where the meaning of the parties is uncertain upon the language used, arid where the usage of the trade to which it was made may afford explanation, and supply deficiencies in the instrument. Technical, local, or doubtful words may be thus explained. So where stip-rdations in the contract refer to matters outside of the instrument, parol proof of extraneous facts may be necessary to interpret their meaning. As a general rule, there must be ambiguity or uncertainty upon the face of the written instrument, arising out of the terms used by the parties, in order to justify the extraneous evidence; and, when admissible, it must be limited in its effect to the clearing up of the obscurity. It is not admissible to add to or engraft upon tbe contract new stipulations, nor to contradict those which are plain.”

In National Bank v. Burkhardt, 100 U. S. 692, it-is said: “A general usage may be proved, in proper cases, to remove ambiguities and uncertainties in a contract, or to annex incidents, but it cannot destroy, contradict or modify what is otherwise manifest. Where the intent and meaning of the parties are clear, evidence of a usage to the contrary is irrelevant and unavailing. Usage cannot make a contract where there is none, nor prevent the effect of the settled rules of law.” See also, Insurance Companies v. Wright, 1 Wall. 456-470; Hearne v. Marine Ins. Co., 20 Wall. 492, 493; Walls v. Bailey, 49 N. Y. 464; Berkshire, etc., Co. v. Proctor, 7 Cush. 417; Clark v. Baker, 11 Met. 186; notes to Wigglesworth v. Dallison, 1 Smith's Leading Cases, Pt. 2 (8th Ed.), 934-965.

In Walls v. Bailey, 49 N. Y. 464, the plaintiffs contracted in writing to furnish the materials to do certain plastering for defendant upon his building in Buffalo, and to the work of laying it on. The defendant was to pay them for the work and material a price per square yard.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Venturi, Inc. v. Adkisson
552 S.W.2d 643 (Supreme Court of Arkansas, 1977)
Snow v. Martensen
522 S.W.2d 371 (Supreme Court of Arkansas, 1975)
C. & A. Construction Co. v. Benning Construction Co.
509 S.W.2d 302 (Supreme Court of Arkansas, 1974)
George W. Condon Co. v. Loup River Public Power District
281 N.W. 31 (Nebraska Supreme Court, 1938)
Murdock v. Reynolds
22 S.W.2d 1007 (Supreme Court of Arkansas, 1929)
Williams v. Ledbetter
285 P. 214 (Oregon Supreme Court, 1929)
Alexander v. Williams-Echols Dry Goods Co.
256 S.W. 55 (Supreme Court of Arkansas, 1923)
Morris v. Hellums Co.
199 S.W. 927 (Supreme Court of Arkansas, 1917)
A. M. Dillow & Co. v. City of Monticello
124 N.W. 186 (Supreme Court of Iowa, 1910)
Montgomery v. Arkansas Cold Storage & Ice Co.
124 S.W. 768 (Supreme Court of Arkansas, 1910)
Arkadelphia Lumber Co. v. Asman
107 S.W. 1171 (Supreme Court of Arkansas, 1907)
Arkadelphia Lumber Co. v. Henderson
105 S.W. 882 (Supreme Court of Arkansas, 1907)

Cite This Page — Counsel Stack

Bluebook (online)
63 S.W. 56, 69 Ark. 313, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mccarthy-v-mcarthur-ark-1901.