George W. Condon Co. v. Loup River Public Power District

281 N.W. 31, 135 Neb. 284, 1938 Neb. LEXIS 180
CourtNebraska Supreme Court
DecidedJuly 15, 1938
DocketNo. 30278
StatusPublished
Cited by1 cases

This text of 281 N.W. 31 (George W. Condon Co. v. Loup River Public Power District) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
George W. Condon Co. v. Loup River Public Power District, 281 N.W. 31, 135 Neb. 284, 1938 Neb. LEXIS 180 (Neb. 1938).

Opinion

Eberly, J.

This is an action at law. It was tried upon the second amended petition, which set forth three distinct causes of action alleged to have arisen out of a single construction contract. Issues were joined. A jury was waived and trial had to the court, resulting in a judgment in favor of plaintiffs on their first cause of action for $8,983.75; a judgment in favor of plaintiffs on the second cause of action for $3,000; a judgment in favor of defendant on the third cause of action and a dismissal of the same. Plaintiffs filed their motion for a new trial as to the judgments entered on the second and third causes of action, and from the order of the district court overruling the same have appealed. The defendant also filed its praecipe on cross-appeal, as required by the rules of this court.

[285]*285Preliminary to the consideration of the merits of these appeals, a question of procedure is presented. There is in the transcript a document entitled “Findings of the Court,” subscribed by the trial judge, and filed in the cause. Section 20-1127, Comp. St. 1929, provides (where a jury is waived) :

“Upon the trial of questions of fact by the court, it shall not be necessary for the court to state its finding, except, generally, for the plaintiff or defendant, unless one of the parties request it, with a view of excepting to the decision of the court upon the questions of law involved in the trial; in which case the court shall state in writing the conclusions of fact found separately from the conclusions of law.”

We have construed this statute as mandatory, and have held that, upon a trial of a law action to the court without a jury, the court on request shall separately state conclusions of fact and law. Carl v. Wentz, 116 Neb. 880, 219 N. W. 390.

But, in the instant case, the record does not disclose that either party requested the trial court to state, in writing, its conclusions of fact found separately from its conclusions of law.

“In the absence of statute it is not the common-law function of a judge in a common-law action, trying a case without a jury, to make special findings of fact.” 8 Standard Encyclopedia of Procedure, 994.

Construing the statute as creating and imposing a power that did not exist at common law, it is quite obvious that a “request” by one of the parties is made a prerequisite to its exercise. This situation has been in part recognized by this jurisdiction in the case of Sheibley v. Dixon County, 61 Neb. 409, 85 N. W. 399, wherein the rule is announced, viz.: “Error cannot be predicated on the failure of the court to make special findings of fact where none were asked.” See, also, State v. Mitchel Irrigation District, 129 Neb. 586, 262 N. W. 543.

But, it appears that this court has not passed upon the effect of a “special finding of fact” made by a court with[286]*286out previous request by either party. However, under statutory provisions quite similar, if not identical, with the one we have quoted above, courts of last resort have held that a finding so made is not to be regarded as a valid statutory finding, and may not be considered except as a general finding. Lesan Advertising Co. v. Castleman, 265 Mo. 345, 177 S. W. 597; Anger v. McCorkle, 253 S. W. (Mo. App.) 72; Kansas City v. Boyer, 202 S. W. (Mo.) 1086; Kelley v. Bell, 172 Ind. 590, 88 N. E. 58; Jacobs v. State, 127 Ind. 77, 26 N. E. 675; Wallace v. Kirtley, 98 Ind. 485; Bake v. Smiley, 84 Ind. 212.

In support of their third cause of action, plaintiffs state that the work upon which plaintiffs bid was described in the “Proposal” for work, as follows:

Further, “That the work (to be) performed under said Item consisted in the main of the excavation of approximately four and one-half miles of canal leading to the Columbus Hydro-Electric Power Station located about two miles north of the city of Columbus, and the excavation of the site of said Power Station and Sub-Station, and the tail-race or discharge canal leading from the Power House site approximately 1,000 feet to the south.

“That the soil, materials, terrain and nature of the work at various points of said canal, Power Station site and tail-race varied materially in character, and required the use of different machinery and methods in the excavation of same.
“That the cost of the excavation varied more than 100 per cent, at various locations in the work.
“That the excavation as originally proposed and described in Item 1 of Schedule'VIII of the ‘Proposal’ or ‘Bid Form’ prepared by the defendant and its engineers, was not di[287]*287vided by locations or the total yardage involved, to permit a separate bid upon the amount of work at different locations requiring different methods with differing costs, and the plaintiffs in bidding upon said Item were required to determine the total amount • of yardage of each class or kind of work, and submit an average bid price, in consideration of the amount of yardage of differing materials and work involved, for all of the excavation contemplated under the Item. * * *
“That the tail-race and discharge canal proposed under the drawings and specifications upon which the plaintiffs’ bid or proposal for Item 1 was submitted, was provided to be approximately 773 feet in length and 155 feet in width, and the Power Station for which a site was to be excavated was approximately 48 feet by 164 feet in dimensions.
“That after the execution of the Agreement hereinbefore referred to, being section ‘E’ of the Contract Documents, the engineers, exercising purported authority under the Contract Documents, changed the drawings and specifications fixing the location of the Power Station to a point approximately 198 feet north from the location as provided for under the original drawings and specifications, and changed the drawings and specifications to' provide for a tail-race or discharge canal 192 feet in width, and extensive additional cuts in that vicinity.
“That the changes as above described necessitated the excavation of approximately 198 feet in length of additional tail-race or discharge canal at the north end of same, and an excavation of the site of the Power Station at a point approximately 198 feet north of the point where it was originally located, and extensive additional excavations at that point.
“That the engineers directed the plaintiffs to complete the work in accordance with the changes made in the "drawings and specifications, and the plaintiffs completed the work in accordance with same.”

Plaintiffs allege that because of the increased quantity and adverse qualities of the soil involved the change oper[288]*288ated to plaintiffs’ damage in the sum of $29,000. Plaintiffs, however, were paid at the rate of 9 cents a cubic yard for all additional excavations by them made, which said amount was accepted by them. It is obvious that plaintiffs’ rights in the premises are necessarily measured by the terms of their contract, if its provisions were drawn with the instant situation in contemplation of the parties thereto. This contract is specific in its terms and constitutes a bound volume of some 98 pages. The following excerpts therefrom are applicable to the present controversy, viz.:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Parsons Construction Co. v. Metropolitan Utilities District
104 N.W.2d 272 (Nebraska Supreme Court, 1960)

Cite This Page — Counsel Stack

Bluebook (online)
281 N.W. 31, 135 Neb. 284, 1938 Neb. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/george-w-condon-co-v-loup-river-public-power-district-neb-1938.