McBride Electric Co. v. United States

51 Ct. Cl. 448, 1916 U.S. Ct. Cl. LEXIS 18, 1916 WL 1098
CourtUnited States Court of Claims
DecidedJune 19, 1916
DocketNo. 32465
StatusPublished
Cited by5 cases

This text of 51 Ct. Cl. 448 (McBride Electric Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
McBride Electric Co. v. United States, 51 Ct. Cl. 448, 1916 U.S. Ct. Cl. LEXIS 18, 1916 WL 1098 (cc 1916).

Opinion

Downet, Judge,

delivered the opinion of the court:

This action is upon a contract entered into on the 8th day of July, 1907, between the plaintiff and the United States for the construction of a system of electric lighting on the Government reservation at Columbus Barracks, Ohio. The work was completed and the contractor was paid the contract price in full without deduction. The action is for the recovery of certain amounts alleged to be due principally on account of changes made in portions of the system, entailing upon the contractor, as it is alleged, additional expense for labor and material.

The specifications include both an outside system of lighting, designed also to be connected with the interior system in the various buildings, and also inside systems for the buildings themselves. The specifications as to the outside system were [451]*451in the alternative, contemplating either an underground or an overhead system. The contract with the plaintiff was for the underground system, and at about the same time a contract was entered into with another concern for the installation of the interior systems in the various buildings.

Plaintiff’s first contention is for the recovery of $1,534.68, alleged to be the cost of extra labor and material necessary in the installation of conduits and electric wiring from the points where the service wires entered the various buildings to the main-line switches- where located by the other contractor. The theory of the plaintiff is that the main-line switches should have been located immediately at the points where the service wires entered the various buildings, and that having been located at various points more or less remote therefrom, and having been required by the officer in charge to carry the service wires through proper conduits to the main-line switches as located, it is entitled to extra compensation for the expense incurred in carrying the lines from the points where the switches should have been located to the points where they actually were located. The contention of the plaintiff, as far as its theory is concerned, seems to be correct. The specifications required the plaintiff contractor to carry the service lines to the main-line switch in each building, but they also provided that in case the underground system of distribution was used the main-line switches would be placed in the basements of the buildings and as close to the service entrance as possible. It appears, however, that the controversy as between the contractor and the officer in charge with reference to this plaintiff’s obligations under the contract arose at a time when the outside conduits and service lines had been brought to the various buildings and before they had been brought inside thereof.

There is an attempt made to prove the expense incurred by the contractor for labor and material necessary to carry the service lines to the points in the buildings where the mainline switches were actually located, but a careful examination of the testimony with reference to the submitted detailed statement of expense shows that it is a statement of the expense necessarily incurred in carrying the lines from the point immediately outside of buildings, where they were [452]*452when the controversy arose, to the main-line switches as located. It is plainly apparent that it was incumbent upon this contractor to carry the service lines inside the buildings and to the main-line switches located as near to the points of entrance as practicable. How much of the expense shown to have been incurred by the contractor in carrying the lines from the outside point to the switches as located was incurred in carrying the lines from the outside point to the points near the entrance where the switches should have been located is not shown. The evidence does not show, except by one general statement of minimum and maximum distance, how far the switches in the various buildings were located away from the point of entrance of the lines, and it does not show what expense was incurred by the contractor in carrying the lines from the points where the switches should have been located to the points where they were located, nor does it show the reasonable value of such service. Plaintiff has evidently left the court in a position where it must estimate for itself, or guess, if it is to determine the amount of the expense shown which it is entitled to recover for that part of the work for which the plaintiff might be held to be entitled to compensation, and this we can not do. It was incumbent upon the plaintiff to show by satisfactory evidence the amount it was entitled to recover on this account, and not having done so there can upon this item be no finding in its favor.

The plaintiff next seeks recovery, as alleged in its petition, of $4,947, but, as shown in the evidence, of a lesser sum, for the furnishing of extra labor and material in connection with the draining of the conduit system. The theory is that the officer in charge departed from the specifications and made changes in the method of draining the conduit system which entailed upon the contractor this additional expense.

For the purposes of this question we quote the general provisions of the specifications under subhead “Drains” as follows:

“Drains.—All transformer manholes and all low points of conduit system shall be connected to the surface drain (not sewer) where directed by the officer in charge.
[453]*453“All the conduit system shall be given a sufficient slope toward the west and south from numbers 26, 14, and 8 to the lowest points in the rear of numbers 59, 52, and 46 where the manholes shall be connected to the surface drains where directed, or carried to an outlet above ground so as to drain all manholes and conduits. Outlets above ground should be protected by iron grating set in brick heading.”

It seems to be the theory of the plaintiff that the first paragraph quoted prescribed the contemplated drainage system, and that thereunder it was not only the duty but the right of the contractor to drain each manhole by an individual drain to the nearest point in the surface drain. This surface drain was not in fact a drain upon the surface of the ground, but it was an underground drainage system called a surface drain, because it collected and carried off surface waters and waters from the roofs of the various buildings. The plans for the underground electric system, which were submitted to bidders, and which became a part of the contract entered into by the plaintiff, contained nothing with reference to the location or the depth of this surface-drainage system, and it does not appear that any representations of any kind were made to the contractor with reference thereto. It does appear that the surface drain, at points near to manholes in the conduit system, was in almost all cases at a higher elevation than the bottoms of the manholes. The specifications clearly contemplated that the conduits, which were to carry the wires in the underground system, should leave the manholes 8 inches above the bottom thereof, and that the drain should leave from the bottom of the manholes. It is plainly apparent that a drain leaving the manhole otherwise than from the bottom could not perform its proper office, and it is equally apparent that the purpose of the drainage system contemplated in connection with the underground conduit system was to properly drain the conduit system in all its parts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Walnut Creek Electric v. Reynolds Construction Co.
263 Cal. App. 2d 511 (California Court of Appeal, 1968)
Oltedale v. United States
39 F. Supp. 998 (D. Rhode Island, 1941)
Penn Bridge Co. v. United States
59 Ct. Cl. 892 (Court of Claims, 1924)
In re the Appeal of Lord
25 Haw. 76 (Hawaii Supreme Court, 1919)
Brinck v. United States
53 Ct. Cl. 170 (Court of Claims, 1918)

Cite This Page — Counsel Stack

Bluebook (online)
51 Ct. Cl. 448, 1916 U.S. Ct. Cl. LEXIS 18, 1916 WL 1098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mcbride-electric-co-v-united-states-cc-1916.