SIMPSON, Circuit Judge:
As in N. L. R. B. v. Beckham, Inc., 564 F.2d 190 (5th Cir. 1977), “[t]he sole issue before the Court is whether substantial evidence on the record considered as a whole supports the finding of the National Labor Relations Board that [Petitioner-Cross-Respondent McAx Sign Company, Inc.] manifested an unequivocal intention to be bound by group rather than individual action in collective bargaining, so that [its] refusal to sign the resulting collective bargaining agreement amounted to a refusal to bargain.” We hold that the findings of the administrative law judge, subsequently affirmed by a three member panel of the Board, are supported by substantial evidence and that enforcement of the Board’s remedial order is required.
I. THE FACTS
The administrative law judge’s findings of fact may be summarized as follows.
McAx, an employer engaged in the design, manufacture, and erection of electrical signs, had been a party to three collective bargaining agreements with Local 59 of the International Brotherhood of Electrical Workers (the Union) for periods from June 20, 1968 to June 30, 1971, July 12, 1971, to June 30, 1973, and July 1, 1973 to June 30, 1976. These agreements purported to be between the Union and the “Neon Electrical Sign Companies of Dallas, Texas”, but the contracts were signed by the individual companies, including McAx.1 Although the contracts themselves support the inference that each was negotiated by the employers as a unit, the only direct evidence of this practice in the record pertains to the 1973 negotiations.
The contract negotiated in 1973 provided that it would continue in effect until June 30, 1976, and thereafter on a year-to-year basis unless one of the parties gave written notice of its desire to modify or terminate the agreement sixty days prior to the renewal date. On April 30, 1976, McAx and two other companies, Heath and Company and J. F. Zimmerman & Sons, each submitted proposals to the Union. A negotiating meeting was scheduled for May 18.
Present at the May 18, 1976 meeting were McAx president Donald Simpson, representatives from Heath and Company, J. F. Zimmerman & Sons, and the A. B. C. Sign Company, all signatories to the 1973 agreement, and Herbert Hicks, representing the Union. The parties met and negotiated every Tuesday for the following five weeks. Minutes of these meetings reflect that at several points during the negotiations, the employers took time out to caucus and to consolidate their proposals into a single set. By the end of the meeting on June 22, 1976, most of the differences between the employers and the Union had [65]*65been resolved except for a dispute as to an hourly wage increase. Hicks suggested that a mediator be obtained for the next meeting. The following day, however, the representative of Heath and Company requested a special meeting. All parties, with the exception of McAx, agreed to meet on Monday, June 28; Simpson, McAx’s president, informed the Union that he could not attend the meeting because he had already made a business commitment for that day. On June 28, in Simpson’s absence, the parties agreed to a wage increase of ten cents per hour more than had been agreed to earlier.
On July 2, 1976, in accordance with past practice, Union Business Manager James Foreman mailed to each employer a copy of the changes agreed to. Thereafter, each employer, except for McAx, acknowledged that the changes set forth in Foreman’s letter were those agreed to in the negotiations. Hicks telephoned Simpson on July 12, but was unable to reach him. On July 22, Foreman informed Simpson by letter that the rate of pay of journeymen had been changed effective July 1 and asked that McAx comply with the terms of the new contract if it had not done so already.
McAx did not respond to the July 22 letter. Hicks made several additional unsuccessful calls on successive days, leaving his name and telephone number for Simpson to call, but no response was forthcoming. Hicks finally reached Simpson on July 29. At that time, Simpson told Hicks that he had not had a chance to review the changes mailed to him 27 days earlier, but that he would do so and call Hicks the next day. When he did not do so, Hicks hand delivered a copy of the new contract on July 30.
On August 2, Simpson informed the Union in writing that he would not sign the new contract for the stated reason that the hourly wage provisions were contrary to McAx’s fiscal interests.
On the basis of these facts, the administrative law judge found a refusal to bargain in violation of the National Labor Relations Act:
In summary, in light of a bargaining history which was to all outward appearances on a group basis, including the use of an association name, with all the contractors cosigning the same contract, plus the fact that the negotiations revealed a group approach to bargaining, the conclusion is warranted, and I find, that [McAx] had manifested an intention to be bound by group rather than individual action and that its refusal to sign the agreement agreed to by the group on June 28 was a refusal to bargain within the meaning of Section 8(a)(1) and (5) of the Act [29 U.S.C. §§ 158(a)(1) and (a)(5)].2
The Board affirmed the findings of the administrative law judge and adopted his recommended order requiring McAx to execute and honor the agreement reached on [66]*66June 28, 1976, and to make its employees whole for any loss of earnings or other benefits they may have suffered by reason of McAx’s refusal to sign.
II. THE ISSUES RAISED
McAx raises two primary objections to the conclusions of the administrative law judge, both of which are without merit.
First, McAx contends that, in affirming the administrative law judge’s finding of an unequivocal intention to be bound by group action, the Board deviated from the legal standard that it announced in Van Eerden Co., 154 NLRB 496, 499 (1965). Hence, it argues, enforcement should be denied under National Fresh Fruit and Vegetable Co. v. N. L. R. B., 565 F.2d 1331, 1336 (5th Cir. 1978) and N. L. R. B. v. Hi-Way Billboards, Inc., 500 F.2d 181, 184 (5th Cir. 1974). In Van Eerden, Co., the Board stated:
When employers have banded together informally to bargain, without expressly documenting their relationship to each other or to the union involved, we have often inferred the presence of the requisite intention from the facts that the employers have participated for a meaningful period of time in joint bargaining negotiations and have adopted substantially uniform contracts resulting therefrom. The ultimate question in these cases, however, is the actual intent of the parties, since multi-employer bargaining is a voluntary arrangement, dependent upon the real consent of the participants to bind themselves to each other for bargaining purposes.
Free access — add to your briefcase to read the full text and ask questions with AI
SIMPSON, Circuit Judge:
As in N. L. R. B. v. Beckham, Inc., 564 F.2d 190 (5th Cir. 1977), “[t]he sole issue before the Court is whether substantial evidence on the record considered as a whole supports the finding of the National Labor Relations Board that [Petitioner-Cross-Respondent McAx Sign Company, Inc.] manifested an unequivocal intention to be bound by group rather than individual action in collective bargaining, so that [its] refusal to sign the resulting collective bargaining agreement amounted to a refusal to bargain.” We hold that the findings of the administrative law judge, subsequently affirmed by a three member panel of the Board, are supported by substantial evidence and that enforcement of the Board’s remedial order is required.
I. THE FACTS
The administrative law judge’s findings of fact may be summarized as follows.
McAx, an employer engaged in the design, manufacture, and erection of electrical signs, had been a party to three collective bargaining agreements with Local 59 of the International Brotherhood of Electrical Workers (the Union) for periods from June 20, 1968 to June 30, 1971, July 12, 1971, to June 30, 1973, and July 1, 1973 to June 30, 1976. These agreements purported to be between the Union and the “Neon Electrical Sign Companies of Dallas, Texas”, but the contracts were signed by the individual companies, including McAx.1 Although the contracts themselves support the inference that each was negotiated by the employers as a unit, the only direct evidence of this practice in the record pertains to the 1973 negotiations.
The contract negotiated in 1973 provided that it would continue in effect until June 30, 1976, and thereafter on a year-to-year basis unless one of the parties gave written notice of its desire to modify or terminate the agreement sixty days prior to the renewal date. On April 30, 1976, McAx and two other companies, Heath and Company and J. F. Zimmerman & Sons, each submitted proposals to the Union. A negotiating meeting was scheduled for May 18.
Present at the May 18, 1976 meeting were McAx president Donald Simpson, representatives from Heath and Company, J. F. Zimmerman & Sons, and the A. B. C. Sign Company, all signatories to the 1973 agreement, and Herbert Hicks, representing the Union. The parties met and negotiated every Tuesday for the following five weeks. Minutes of these meetings reflect that at several points during the negotiations, the employers took time out to caucus and to consolidate their proposals into a single set. By the end of the meeting on June 22, 1976, most of the differences between the employers and the Union had [65]*65been resolved except for a dispute as to an hourly wage increase. Hicks suggested that a mediator be obtained for the next meeting. The following day, however, the representative of Heath and Company requested a special meeting. All parties, with the exception of McAx, agreed to meet on Monday, June 28; Simpson, McAx’s president, informed the Union that he could not attend the meeting because he had already made a business commitment for that day. On June 28, in Simpson’s absence, the parties agreed to a wage increase of ten cents per hour more than had been agreed to earlier.
On July 2, 1976, in accordance with past practice, Union Business Manager James Foreman mailed to each employer a copy of the changes agreed to. Thereafter, each employer, except for McAx, acknowledged that the changes set forth in Foreman’s letter were those agreed to in the negotiations. Hicks telephoned Simpson on July 12, but was unable to reach him. On July 22, Foreman informed Simpson by letter that the rate of pay of journeymen had been changed effective July 1 and asked that McAx comply with the terms of the new contract if it had not done so already.
McAx did not respond to the July 22 letter. Hicks made several additional unsuccessful calls on successive days, leaving his name and telephone number for Simpson to call, but no response was forthcoming. Hicks finally reached Simpson on July 29. At that time, Simpson told Hicks that he had not had a chance to review the changes mailed to him 27 days earlier, but that he would do so and call Hicks the next day. When he did not do so, Hicks hand delivered a copy of the new contract on July 30.
On August 2, Simpson informed the Union in writing that he would not sign the new contract for the stated reason that the hourly wage provisions were contrary to McAx’s fiscal interests.
On the basis of these facts, the administrative law judge found a refusal to bargain in violation of the National Labor Relations Act:
In summary, in light of a bargaining history which was to all outward appearances on a group basis, including the use of an association name, with all the contractors cosigning the same contract, plus the fact that the negotiations revealed a group approach to bargaining, the conclusion is warranted, and I find, that [McAx] had manifested an intention to be bound by group rather than individual action and that its refusal to sign the agreement agreed to by the group on June 28 was a refusal to bargain within the meaning of Section 8(a)(1) and (5) of the Act [29 U.S.C. §§ 158(a)(1) and (a)(5)].2
The Board affirmed the findings of the administrative law judge and adopted his recommended order requiring McAx to execute and honor the agreement reached on [66]*66June 28, 1976, and to make its employees whole for any loss of earnings or other benefits they may have suffered by reason of McAx’s refusal to sign.
II. THE ISSUES RAISED
McAx raises two primary objections to the conclusions of the administrative law judge, both of which are without merit.
First, McAx contends that, in affirming the administrative law judge’s finding of an unequivocal intention to be bound by group action, the Board deviated from the legal standard that it announced in Van Eerden Co., 154 NLRB 496, 499 (1965). Hence, it argues, enforcement should be denied under National Fresh Fruit and Vegetable Co. v. N. L. R. B., 565 F.2d 1331, 1336 (5th Cir. 1978) and N. L. R. B. v. Hi-Way Billboards, Inc., 500 F.2d 181, 184 (5th Cir. 1974). In Van Eerden, Co., the Board stated:
When employers have banded together informally to bargain, without expressly documenting their relationship to each other or to the union involved, we have often inferred the presence of the requisite intention from the facts that the employers have participated for a meaningful period of time in joint bargaining negotiations and have adopted substantially uniform contracts resulting therefrom. The ultimate question in these cases, however, is the actual intent of the parties, since multi-employer bargaining is a voluntary arrangement, dependent upon the real consent of the participants to bind themselves to each other for bargaining purposes. And where there is specific evidence, beyond the mere circumstances of joint negotiations and uniformity of contracts, indicating that the parties did not intend to accept the obligations and benefits of multi-employer bargaining, that evidence must be equally considered in determining the basic issue.
We find no departure from these principles in this case. It is well established that the requisite intent may be inferred from a prior history of multi-employer bargaining and the adoption of uniform contracts. See, e. g., N. L. R. B. v. Johnson Sheet Metal, Inc., 442 F.2d 1056, 1060 (10th Cir. 1971); N. L. R. B. v. Southwestern Colorado Contractors Ass’n, 379 F.2d 360, 364 (10th Cir. 1967); Bennett Stone Co., 139 N.L.R.B. 1422 (1962).3 In this case, the prior dealings of the parties and the course of conduct during the 1976 negotiations amply supported an inference of unequivocal intent to be bound by group action. Furthermore, the administrative law judge did not deviate from the rule of Van Eerden that evidence “indicating that the parties did not intend to accept the obligations and benefits of multi-employer bargaining . must be equally considered in determining the basic issue”.4
The evidence presented by McAx to negate the inference of unequivocal intention was weighed and rejected by the administrative law judge. McAx argued first that the unilateral decision by three of the four employers to request modification of the 1973 contract on April 30,1976, is incon[67]*67sistent with a group approach to bargaining. The administrative law judge found, however, that the subsequent approach to the negotiations as a group, including the preparation of a consolidated employer proposal, negated the inference urged by McAx. McAx also relied upon the fact that Simpson ultimately refused to sign the agreement. In response, the administrative law judge found that McAx’s “reasons for rejecting the contract as set forth in its August 2 letter are clearly a belated attempt to avoid the legal consequences of its past conduct”. These inferences drawn by the administrative law judge are supported by substantial evidence in the record and may not be disturbed by this Court. See Universal Camera Corp. v. N. L. R. B., 340 U.S. 474, 71 S.Ct. 456, 95 L.Ed. 456 (1951); N. L. R. B. v. Allis-Chalmers Corp., 563 F.2d 674 (5th Cir. 1977).
In finding the requisite “unequivocal intention” the administrative law judge noted that, in spite of many opportunities to do so, McAx never expressed an intention not to be bound by collective action. We agree that under the facts of this case McAx’s failure to reserve the right to dissent supports a clear inference of intent to be bound by group action. Cf. N. L. R. B. v. Southwestern Colorado Contractors Ass’n, supra, 379 F.2d at 364.
So far as the record discloses, the first time that McAx took the position that it was not bound by group action was on October 1, 1976, in response to a complaint filed against it by the regional office of the N.L.R.B. pursuant to charges filed by the Union after Simpson refused to sign the contract.
Without a single indication to the contrary, the activities of Simpson, McAx’s chief executive officer and designated bargaining agent in the ongoing multi-employer contract negotiations with the Union, all point inexorably and inescapably to the conclusion that his belated disclaimer to be bound by the joint negotiations was no more than an afterthought, perhaps as a result of consultation with counsel. Simpson attended and participated in the first six negotiating sessions — on May 18, May 25, June 1, June 8, June 15, and June 22, 1976 — without caveat. He did not attend the critical and final session of June 28, 1976, as he explained to Union representative Hicks, because “I made some commitments with out of town people that makes it impossible for me to attend . . .” In the three weeks following the June 28 session, Simpson was twice informed of the terms agreed upon at that session, by letters from Union Business Agent Foreman dated July 2 and 22, 1976; he did not respond to these letters or return any of the repeated telephone calls made to him by Foreman and Hicks. When Hicks was finally able to reach Simpson by telephone on July 29, Simpson stated only that he had not yet had a chance to review the changes.5 On August 2, in explaining his reasons for refusing to sign the contract, Simpson wrote:
After long and careful review, we find that to become a party to the agreement in question would seriously impair our opportunity for healthy fiscal operation and would severely restrict our company’s future.
For these reasons, I cannot enter into and sign this agreement for McAx Sign Company, Inc.
The Board has repeatedly held that withdrawal from a multi-employer bargaining unit is untimely if attempted after the [68]*68commencement of negotiations. See, e. g., N. L. R. B. v. Tulsa Sheet Metal Works, Inc., 367 F.2d 55, 57 (10th Cir. 1966); N. L. R. B. v. Sheridan Creations, Inc., 357 F.2d 245 (2d Cir. 1966), cert. denied, 385 U.S. 1005, 87 S.Ct. 711, 17 L.Ed.2d 544; N. L. R. B. v. Sklar, 316 F.2d 145 (6th Cir. 1963). This rule is intended to minimize disruption of the bargaining process by preventing an employer from using the threat of withdrawal from negotiations as a “bargaining lever”. N. L. R. B. v. Sheridan Creations, Inc., supra, 357 F.2d at 248. In light of the administrative law judge’s findings in this case, to accept McAx’s ultimate refusal to sign a collective bargaining agreement not to its liking as proof that it never intended to be bound by group action would thwart the rule governing withdrawal from multiemployer bargaining units.
McAx also argues that the Board deviated from the rule that unequivocal intent must be manifested “from the outset”, Joseph McDaniel, 226 NLRB No. 120, enforced sub nom. N. L. R. B. v. Beckham, Inc., supra, because it relied upon evidence that the employers’ individual proposals were consolidated after negotiations commenced. This argument assumes that the submission of individual proposals before or at the commencement of negotiations is consistent only with an intent to bargain individually, an assumption which we reject. The submission of individual proposals in this case was an ambiguous act because it was not accompanied by any express statement of intent. Its meaning thus had to be inferred from the surrounding circumstances. Here, as the administrative law judge noted, the three individual proposals were made after a history of multi-employer bargaining and served merely as a starting point for an eventual consolidation to facilitate bargaining as a unit. Under these circumstances, the Board was justified in basing its finding of intent from the outset in part upon conduct which occurred during the negotiations.
Substantial evidence in the record supports the finding of both the administrative law judge and the Board that McAx indicated from the outset an unequivocal intention to be bound by group rather than individual action. McAx is thus bound by the contract negotiated by the group.
McAx’s petition for review is denied; the order of the National Labor Relations Board is ordered
ENFORCED.