Maun v. United States

347 F.2d 970
CourtCourt of Appeals for the Ninth Circuit
DecidedMay 20, 1965
DocketNos. 19373, 19374
StatusPublished
Cited by23 cases

This text of 347 F.2d 970 (Maun v. United States) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maun v. United States, 347 F.2d 970 (9th Cir. 1965).

Opinion

HAMLEY, Circuit Judge:

This is an interlocutory appeal from an order entered in consolidated condemnation proceedings brought by the United States to acquire electric transmission line easements in Woodside, California and adjacent unincorporated areas in San Mateo County. The appellants are the Town of Woodside, County of San Mateo, and certain of the affected landowners, all of whom are defendants in the condemnation proceedings.

On May 13, 1960, Congress authorized an Atomic Energy Commission (AEC) research project known as the Stanford Linear Accelerator Center (SLAC). 74 Stat. 120. The sum of $114,000,000 was subsequently authorized for the construction of this plant. Act of September 26, 1961. 75 Stat. 676. This AEC project is intended and designed for basic research in high energy physics and not as a plant for the production of electrical energy by nuclear means.

One of the essential requisites of the project is the availability of a sufficient quantity of conventionally generated electricity to operate the complex equipment. AEC plans to obtain a part of this supply from the United States Bureau of Reclamation, delivery to be made over lines to be constructed by Pacific Gas and Electric Company (P. G. & E.). The balance of the required electric [972]*972energy is to be generated by P. G. & E. and transmitted to SLAC over the same lines.

In January, 1963, AEC and P. G. & E. entered into a contract designed to effectuate this plan. The contract provides that P. G. & E. would obtain such permits as were necessary, and that the contract would be filed subject to the approval of the California Public Utilities Commission.

In fulfillment of its obligations under this contract, P. G. & E., in June, 1963, applied to the planning commissions of Woodside and the county for the necessary use permits. In these applications the company proposed a tie line from its main Monte Vista-Jefferson transmission line to SLAC. This tie line would consist of two three-cable 220,000 volt circuits suspended from standard towers to be located on a one-hundred foot strip of land cleared of trees and vegetation. The proposed route runs first through unincorporated county territory, then through Woodside, and again through unincorporated territory to its terminus.

At least as early as 1950, San Mateo County had a zoning ordinance which required a public utility to secure a conditional use permit from its planning commission and board of supervisors if it sought to construct power transmission lines. Upon its incorporation in 1956, Woodside continued the county pattern of regulation. In 1958, the town adopted a zoning ordinance prescribing the same regulatory procedure.

Upon filing its application, P. G. & E. was met with demands from the county and town that the line be placed underground as a condition to the issuance of the necessary use permits. P. G. & E. and AEC took the position that an underground transmission line would not be as serviceable or desirable from a service point of view and that it would entail a substantial additional cost over and above the estimated cost of an overhead line. Several conferences were then had but no agreement was reached.

On March 7, 1964, the chairman of AEC notified the County of San Mateo and Woodside that, although AEC was willing to attempt to find a mutually agreeable solution, time was of the essence since SLAC was nearing completion. The chairman advised the county and town that if P. G. & E. was unable to obtain the necessary use permits, AEC would be forced, in the national interest, to intervene directly by instituting eminent domain proceedings and to construct its own line.

In spite of this warning, Woodside and the county subsequently denied use permits to build an overhead transmission line, as applied for by P. G. & E. Contemporaneously with this action, Wood-side adopted an ordinance prohibiting construction of an overhead electrical transmission line of fifty thousand volts or greater capacity. Woodside followed this with a general ordinance prohibiting the overhead installation of transmission, distribution or communication lines. The County of San Mateo did not enact ordinances of this kind.

On March 24, 1964, at the request of AEC, the United States Attorney filed on behalf of the United States in the district court a complaint in condemnation. In essence, the Government sought to condemn a one hundred foot wide perpetual and assignable easement over approximately 4.92 acres of land located within the boundaries of Woodside. The county, town and several individual property owners were named defendants.

This complaint was followed by a declaration of taking on April 30, 1964. Also on April 30, 1964, the United States filed a second complaint in condemnation against the State of California, County of San Mateo and several individual property owners. In tin's proceeding the Government sought to acquire a similar easement consisting of approximately 24.57 acres located within the county but outside the boundaries of Woodside. On the same day a declaration of taking was entered in this second condemnation suit.

Being aware that certain objections would be interposed, counsel for the Government, concurrently with the filing of the declarations of taking, requested [973]*973of the court that the Government be granted modified orders of posse: sion limited to permission to c. nduct field surveys and design inspections. The district court granted this request and also granted the Government’s further request that all objections a: d motions filed in both cases be consolidated and heard at one time.

The various defendants filed answers, motions to dismiss and, in the first proceeding, a motion for summary judgment. The Government thereupon filed a motion to strike defendants’ motions to dismiss and for summary judgment, and all of the objections and alleged defenses raised in the answers.

Resisting the Government’s motion, defendants contended at the hearing in the district court that section 271 of the Atomic Energy Act of 1954 (Act), 68 Stat. 960, 42 U.S.C. § 2018 (1958), deprived the Government of authority to condemn the tracts in question for the purposes and uses intended. Section 271 reads:

“Nothing in this chapter shall be construed to affect the authority or regulations of any Federal, State, or local agency with respect to the generation, sale, or transmission of electric power.”

Following this hearing the district court, on June 12, 1964, entered an order granting the Government’s motion. The court struck defendants’ motions to dismiss, and motion for summary judgment, on the ground that Rule 71A(e), Federal Rules of Civil Procedure, precludes any pleading or motion by a defendant in a condemnation proceeding other than an answer. It struck all objections and alleged defenses in defendants’ answers on the ground that:

“ * * * Congress did not intend 42 U.S.C. 2018 [Section 271 of the Act], upon which defendants ground their defenses, to prevent the A.E.C. from condemning the easement in question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Boeing Company v. Maziar Movassaghi
768 F.3d 832 (Ninth Circuit, 2014)
United States v. Sawyer
Ninth Circuit, 2008
Long Island Lighting Co. v. County of Suffolk
628 F. Supp. 654 (E.D. New York, 1986)
Geophysical Corp. of Alaska v. Andrus
453 F. Supp. 361 (D. Alaska, 1978)
State of Vermont v. Brinegar
379 F. Supp. 606 (D. Vermont, 1974)
United States v. 687.30 Acres of Land
319 F. Supp. 128 (D. Nebraska, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
347 F.2d 970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maun-v-united-states-ca9-1965.