Matter of Schmidt v. . Berger

116 N.E. 882, 221 N.Y. 26, 1917 N.Y. LEXIS 1263
CourtNew York Court of Appeals
DecidedMay 8, 1917
StatusPublished
Cited by5 cases

This text of 116 N.E. 882 (Matter of Schmidt v. . Berger) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matter of Schmidt v. . Berger, 116 N.E. 882, 221 N.Y. 26, 1917 N.Y. LEXIS 1263 (N.Y. 1917).

Opinion

Chase, J.

The appellant Berger is the owner of an apartment house at 108-10 West One Hundred and Eleventh street, New York city. The claimant was employed by her as a superintendent of the building and incidental to that employment he made ordinary repairs on such building. While so employed he found that a basement door “bound at the top” and did not open or shut freely. He mounted a stepladder and while standing thereon commenced with a carpenter’s tool called a “ plane ” to cut away a part of the door and thus prevent such binding, and while so engaged fell off the stepladder and broke his arm. The industrial commission gave him an award and the Appellate Division of the Supreme Court has affirmed the same, although two of the justices did not concur in the decision.

The employment of claimant is conceded, and it is also conceded that the injury was accidental, and arose out of and in the course of his employment. He was not, however, engaged in a hazardous employment within the meaning of the Workmen’s Compensation Law, carried on by the defendant Berger for pecuniary gain, at least he was not so employed at the time he was injured. (Matter of Sheridan v. Groll Construction Co., 218 N. Y. 633.)

It is urged in behalf of the claimant that he was engaged in a hazardous employment enumerated in *28 group 42 of section 2 of the Workmen’s Compensation Law. If so, the work that he was engaged in at the time of the accident must be included in the words “structural carpentry” or “ construction, repair and demolition of buildings.” The words quoted when read and construed in connection with the other parts of said group 42 do not include the work being done by the claimant as stated.

The words “structural carpentry” must be construed together and cannot be separated. They do not include an isolated act in planing wood. (See Matter of Heitz v. Ruppert, 218 N. Y. 148, 151.) Neither was the act of the claimant in planing the top of the door included within the words “ construction, repair and demolition of buildings.” (Matter of Bargey v. Massaro Macaroni Co., 218 N. Y. 410, 413.)

The order of the Appellate Division should be reversed and the claim dismissed, with costs in this court and in the Appellate Division to the appellants against the state industrial commission.

Hiscock, Oh. J., Hogan, Oardozo, Pound, McLaughlin and Andrews, JJ., concur.

Order reversed, etc. •

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Sommerville
167 Misc. 89 (New York Court of Special Session, 1938)
Claim of Alterman v. A. I. Namm & Son
190 A.D. 76 (Appellate Division of the Supreme Court of New York, 1919)
Claim of Geller v. Republic Novelty Works
180 A.D. 762 (Appellate Division of the Supreme Court of New York, 1917)
Claim of Solomon v. Bonis
181 A.D. 672 (Appellate Division of the Supreme Court of New York, 1917)
Matter of Kammer v. . Hawk
117 N.E. 576 (New York Court of Appeals, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
116 N.E. 882, 221 N.Y. 26, 1917 N.Y. LEXIS 1263, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matter-of-schmidt-v-berger-ny-1917.