Matson Navigation Co. v. United Engineering Works

213 F. 293, 129 C.C.A. 639, 1914 U.S. App. LEXIS 1880
CourtCourt of Appeals for the Ninth Circuit
DecidedMarch 9, 1914
DocketNo. 2251
StatusPublished
Cited by6 cases

This text of 213 F. 293 (Matson Navigation Co. v. United Engineering Works) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matson Navigation Co. v. United Engineering Works, 213 F. 293, 129 C.C.A. 639, 1914 U.S. App. LEXIS 1880 (9th Cir. 1914).

Opinion

WOEVERTON, District Judge.

This is a libel in admiralty. The United Engineering Works is the libelant and the Matson Navigation Company the respondent. For convenience, the parties will be referred to hereinafter as the United or libelant, and the Matson Com-, pany or respondent.

The Matson Company is the _ owner of the American steamer Hilonian, and the libel charges that, between the months of July and December, 1909, the libelant, at the special instance and request of respondent, furnished certain materials and performed certain labor upon the Hilonian, as set forth in Schedules 1, 2, and 3 annexed to the libel, and that the charges extended in said schedules are just and reasonable. These amount to

$30,018 83 Schedule 1
170 06 “ 2.
766 96 “ 3
Total....................................................$30,955 85
Against which is a credit........................................ 520 01
Leaving a balance due of .. $30,435 84

For a second cause it is alleged that further materials were furnished and labor done and performed upon said steamer as particularized and set forth in Schedules 4, 5, 6, 7, 8, 9, and 10 annexed to the libel. The demands under these several schedules are as follows:

Schedule 4. $ 616 88
“ 5. • 190 00
“ 6. 140 00
“ ■ 7. , 140 .00
“ 8.. 1,350 00
“ 9.. 1,140 00
“ 10 ..,725 00
Total......................................................$4,301 88

The answer to the first cause of libel admits that the libelant furnished certain materials and performed certain work upon the Hilonian ; but, as it pertains to the matters and things set forth in Schedule 1, it is alleged that the materials and labor .were furnished and performed under an express contract for a consideration of $11,749, but:

“That during the progress of said work it was mutually agreed that certain omissions, modifications, and changes in said specifications and the work to be performed under said contract should be made, and the same were made and omitted without an agreement between the parties as to the value of said omissions, changes and modifications.”

And:

“That certain work and materials were also furnished to said steamer by said libelant during said period of time * * * in addition to the work and materials called for by said contract, and for which no price was agreed upon other than that the same would be compensated for at its just and reasonable value.”

It is then further alleged that certain work and materials were omitted of the value of $1,398.25, and additional work and materials [295]*295were furnished of the value of $8,280.50, leaving due the libelant upon the contract and for work and materials furnished the sum of $18,631.25.

As it relates to Schedules 2 and 3 it is stated that the United did furnish certain materials and supplies an$ perform certain work “without any agreement as to the price,” but that the same was of nO' greater value than $937.07, which is the aggregate of the two Schedules 2 and 3. The right, however, is reserved to respondent of proving at the trial that such materials and services were worth less than that sum.

The answer to the second cause of libel admits liability as to each of Schedules 4, 5, 6, 7, 8, 9, and 10, except two items contained in Schedule 4, namely, to “Remetal horse shoes,” etc., $146.88, and to “Grind off I. P. piston rod,” etc., one-half of same $25, and two items of Schedule 9, being “Enlarged casing $60,” and “Made new top for breeching,” etc., $180.

As a separate answer to both causes of action a credit of $535.76 is claimed.

An analysis of the pleadings reduces the issues practically to a controversy touching Schedule 1 and two items each in Schedules 4 and 9. The respondent reserved the right to show that the work and materials performed and furnished as stated in Schedules 2 and 3 were worth less than the amount charged, but no proof was offered to the purpose, so that these schedules may be eliminated from further inquiry. _ _ ■

_ _ The libelant, both in the pleadings and at the trial, has proceeded upon the theory that the work done and materials furnished for the repairs upon the Hilonian were done and furnished under a time and material contract; the respondent tacitly agreeing to pay what the same was reasonably worth. The respondent has contended and is contending that the parties dealt with each other under an express contract, but that in its observance certain changes were made, by mutual agreement, by way of omissions, modifications, and additional services to be rendered, and that, in so far as other work was done and materials furnished instead of such as were stipulated for in.the specifications, it was agreed that one should be in compensation for the other, and the additional services were rendered without any agreement as to the value thereof. Its theory, therefore, of the situation is that the integrity of the contract has not been overthrown by the omissions, modifications, and changes made, and that libelant was bound to its performance for the consideration therein named; otherwise it is conceded that the libelant is entitled to pay for the extra services rendered and materials furnished upon a quantum meruit basis.

The libelant, of course, has the burden of proof of establishing in the first instance that it is entitled to recover under the'theory it has adopted, which involves proof of the work done and materials furnished the Hilonian, together with their reasonable value, for it is upon this basis it must recover, if at all. The respondent, on the other hand, has the burden of proving that the contract was duly en[296]*296tered into between the parties, and not only this, but that it has so continued in its integrity, notwithstanding the changes and modifications imposed upon it in its treatment by the parties, as to be susceptible of enforcement. Under this theory, there necessarily must be an identification of th§ work done and materials supplied that are properly referable to the contract and a segregation therefrom of the time and material obligations. In this way only can we hope to arrive at a true understanding of the correlative engagements and ultimate liabilities of the parties.

[1] It will be convenient to inquire, first, whether any contract was entered into between the parties touching the repairs on the Hilonian, and, if so, what its nature was. In this connection, we will also ascertain what Putzar’s true relations were to the parties concerned.

Carl E. Klitgaard was chief engineer upon the Hilonian, and as such he prepared, at the instance of the Matson Company, certain specifications for repairs designed to be made upon the vessel. The specifications contained 15 different items, with a statement at the bottom that time would be an important factor in awarding the contract, and fixing a limit of 26 days from August 23, 1909, for doing the work. With these in hand, the Matson Company advertised for bids. The United, among others, submitted a bid of $11,999. This was rejected, and bids were again called for.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Morris v. United States
12 F.2d 727 (Ninth Circuit, 1926)
State v. Brassfield
197 P. 559 (Idaho Supreme Court, 1921)
Loveman, Joseph Loeb v. McQueen
82 So. 530 (Supreme Court of Alabama, 1919)

Cite This Page — Counsel Stack

Bluebook (online)
213 F. 293, 129 C.C.A. 639, 1914 U.S. App. LEXIS 1880, Counsel Stack Legal Research, https://law.counselstack.com/opinion/matson-navigation-co-v-united-engineering-works-ca9-1914.