Matl Construction Company F/K/A Stewart-Matl, Ltd. And Travelers Casualty and Surety Company of America v. Jim Connelly Masonry, Inc.

CourtCourt of Appeals of Texas
DecidedJuly 31, 2009
Docket03-08-00559-CV
StatusPublished

This text of Matl Construction Company F/K/A Stewart-Matl, Ltd. And Travelers Casualty and Surety Company of America v. Jim Connelly Masonry, Inc. (Matl Construction Company F/K/A Stewart-Matl, Ltd. And Travelers Casualty and Surety Company of America v. Jim Connelly Masonry, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Matl Construction Company F/K/A Stewart-Matl, Ltd. And Travelers Casualty and Surety Company of America v. Jim Connelly Masonry, Inc., (Tex. Ct. App. 2009).

Opinion

TEXAS COURT OF APPEALS, THIRD DISTRICT, AT AUSTIN

NO. 03-08-00559-CV

Matl Construction Company f/k/a Stewart-Matl, Ltd.; and Travelers Casualty and Surety Company of America, Appellants

v.

Jim Connelly Masonry, Inc., Appellee

FROM THE DISTRICT COURT OF BASTROP COUNTY, 335TH JUDICIAL DISTRICT NO. 26,611, HONORABLE TERRY L. FLENNIKEN, JUDGE PRESIDING

MEMORANDUM OPINION

Matl Construction Company f/k/a Stewart-Matl, Ltd. (“Matl”), and its surety,

Travelers Casualty and Surety Company of America (collectively, “appellants”) appeal an

interlocutory district court order denying their motion to compel arbitration of claims asserted

against them by Jim Connelly Masonry, Inc. (“JCM”). See Tex. Civ. Prac. & Rem. Code Ann.

§ 171.098(a)(1) (West 2005).1 In three issues, appellants contend that the district court was required

1 Under the Texas General Arbitration Act (TAA), a party may challenge an order denying arbitration through interlocutory appeal. See Tex. Civ. Prac. & Rem. Code Ann. § 171.098(a)(1) (West 2005). Under the Federal Arbitration Act (FAA), by contrast, a party can seek relief from denial of arbitration solely through mandamus. In re Poly-America, L.P., 262 S.W.3d 337, 345 (Tex. 2008) (orig. proceeding). Appellants have sought relief from the district court’s order solely through this interlocutory appeal. This choice of appellate remedy presumes that the TAA governs the arbitrability of JCM’s claims. See In re D. Wilson Constr. Co., 196 S.W.3d 774, 778-80 (Tex. 2006); but see Act of May 27, 2009, 81st Leg., ch. __, § ___, R.S., 2009 Tex. Gen. Laws ___ (effective Sept. 1, 2009). The FAA and TAA are not mutually exclusive; if FAA applies, that does not necessarily mean that the TAA does not. D. Wilson Constr. Co., 196 S.W.3d at 779-80. to compel arbitration because a valid arbitration agreement exists that encompasses JCM’s claims.

We agree, and will reverse the district court’s order and remand for further proceedings consistent

with this opinion.

Matl was the general contractor for the Bastrop County Law Enforcement Center

Addition Project. JCM was selected by Matl to install all masonry work on the project. Disputes

arose, and JCM eventually sued Matl and Travelers, Matl’s surety, on its performance bond. JCM

sought recovery from Matl of $271,508.18, which it alleged to be the value of labor, equipment, and

materials it had furnished on the project and for which it had not been compensated. In seeking this

recovery, JCM pleaded theories of “oral contract” and quantum meruit. JCM also asserted a claim

against Matl for conversion, alleging that when Matl gave notice “that it was terminating the

Subcontract,” it ordered JCM off the job site and “did in fact deny [JCM] entry onto the Project to

remove equipment owned by Plaintiff on the Project.” JCM also asserted a claim against Matl and

Travelers, jointly and severally, on the performance bond.

Appellants moved to compel arbitration based on an arbitration clause contained

in what they asserted was a written subcontract with JCM. An evidentiary hearing was held, after

The FAA preempts the TAA only to the extent the TAA is inconsistent with it. Id. To determine whether the TAA is contrary to the FAA in a particular case, the court considers a four-factor test: the FAA preempts the TAA only if: “(1) the agreement is in writing, (2) it involves interstate commerce, (3) it can withstand scrutiny under traditional contract defenses [under state law], and (4) state law affects the enforceability of the agreement.” Id. (quoting In re Nexion Health at Humble, Inc., 173 S.W.3d 67, 69 (Tex. 2005) (per curiam)). Here, no party has contended that the TAA is preempted by the FAA or is otherwise inapplicable. See id. We conclude that we have subject-matter jurisdiction over this appeal.

2 which the district court took the matter under advisement and ultimately denied appellants’ motion.

This appeal followed.

As the parties seeking to compel arbitration, appellants had the initial burden of

establishing (1) the existence of a valid arbitration agreement; (2) that encompasses JCM’s claims.

See In re Oakwood Mobile Homes, Inc., 987 S.W.2d 571, 573 (Tex. 1999); Tex. Civ. Prac. & Rem.

Code Ann. § 171.021 (West 2005). Whether a valid arbitration agreement exists is a function of

state contract law. See J. M. Davidson, Inc. v. Webster, 128 S.W.3d 223, 227 (Tex. 2003).

In their first two issues, appellants contend that the record establishes, as a matter of

law, that a valid arbitration agreement exists. The material facts bearing upon this determination are

undisputed. Before JCM began work on the project, Matl sent JCM a document titled “Subcontract.”

The Subcontract provides that, effective March 31, 2006, JCM agreed to perform masonry work

on the project in “strict accordance with the Plans and Specifications, Addenda and Revisions

and the Drawings and Details dated November, 2005.” In exchange, it was agreed that JCM would

be paid the total sum of $475,017, subject to additions and deductions permitted elsewhere in the

Subcontract. The Subcontract also includes five attachments: “Subcontractor General Conditions”

(Ex. A), “Subcontractor Special Conditions” (Ex. B), an “Application for Payment” form for

JCM’s use in requesting payment from Matl as its work was completed (Ex. C), “Jobsite Safety

Requirements” (Ex. D), and Matl’s sales and use tax exemption certification for the masonry (Ex. E).

Paragraph 23 of the thirty-nine paragraph Subcontractor General Conditions (Ex. A) provides:

23. MEDIATION AND ARBITRATION: If a dispute arises out of or relates to this Contract, or the breach thereof, and if said dispute cannot be settled through

3 negotiation, at the election of Stewart-Matl,[2] the parties agree first to try in good faith to settle the dispute by mediation under the Commercial Mediation Rules of the American Arbitration Association, before resorting to arbitration, litigation or some other dispute resolution procedure as provided herein.

If mediation has proven unsuccessful in resolving the dispute, then, upon the demand of Stewart-Matl, whether made before or after the institution of any judicial proceeding, any controversy or claim whatsoever arising out of or relating to this Contract, or the breach thereof, shall be settled by binding arbitration in accordance with the Commercial Arbitration Rules of the American Arbitration Association, and judgment upon the award rendered by the arbitration(s) may be entered in any court having jurisdiction thereof.

The Subcontract contains two sets of signature lines, one for a representative of JCM, and the

other for a representative of Matl. When Matl sent the proposed Subcontract to JCM, both sets

of signature lines were left blank.

On May 1, 2006, Jim Connelly, JCM’s president, signed the Subcontract on JCM’s

behalf3—with the notation, “w/ attachment”—and returned the document to Matl. With the copy

of the Subcontract JCM transmitted back to Matl, it included a one-page document on JCM

letterhead (the “Attachment”), which stated:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Grigson v. Creative Artists Agency, L.L.C.
210 F.3d 524 (Fifth Circuit, 2000)
J.M. Davidson, Inc. v. Webster
128 S.W.3d 223 (Texas Supreme Court, 2003)
In Re D. Wilson Const. Co.
196 S.W.3d 774 (Texas Supreme Court, 2006)
Fiess v. State Farm Lloyds
202 S.W.3d 744 (Texas Supreme Court, 2006)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
In Re U.S. Home Corp.
236 S.W.3d 761 (Texas Supreme Court, 2007)
In Re Poly-America, L.P.
262 S.W.3d 337 (Texas Supreme Court, 2008)
In Re Nexion Health at Humble, Inc.
173 S.W.3d 67 (Texas Supreme Court, 2005)
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
In Re Oakwood Mobile Homes, Inc.
987 S.W.2d 571 (Texas Supreme Court, 1999)
American Employers' Insurance v. Aiken
942 S.W.2d 156 (Court of Appeals of Texas, 1997)
Hearthshire Braeswood Plaza Ltd. Partners v. Bill Kelly Co.
849 S.W.2d 380 (Court of Appeals of Texas, 1993)
In Re Firstmerit Bank, N.A.
52 S.W.3d 749 (Texas Supreme Court, 2001)
Harco Energy, Inc. v. Re-Entry People, Inc.
23 S.W.3d 389 (Court of Appeals of Texas, 2000)
Federal Sign v. Texas Southern University
951 S.W.2d 401 (Texas Supreme Court, 1997)
Meyer v. WMCO-GP, LLC
211 S.W.3d 302 (Texas Supreme Court, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Matl Construction Company F/K/A Stewart-Matl, Ltd. And Travelers Casualty and Surety Company of America v. Jim Connelly Masonry, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/matl-construction-company-fka-stewart-matl-ltd-and-texapp-2009.