Mathis v. Palo Alto County Board of Supervisors

927 N.W.2d 191
CourtSupreme Court of Iowa
DecidedMay 3, 2019
Docket18-1431
StatusPublished
Cited by3 cases

This text of 927 N.W.2d 191 (Mathis v. Palo Alto County Board of Supervisors) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mathis v. Palo Alto County Board of Supervisors, 927 N.W.2d 191 (iowa 2019).

Opinion

MANSFIELD, Justice.

In this case we are called upon to review the decisions of a county board of supervisors approving a wind energy ordinance and a specific wind energy project. Although the challengers raise a number of well-presented arguments, in the end we conclude they were matters for the board of supervisors-not the courts-to resolve. We therefore affirm the judgment of the district court granting summary judgment and dismissing the plaintiffs' claims.

I. Background Facts and Proceedings.

In late July 2015, the development manager for a renewable energy company asked Joseph Neary, the Palo Alto County planning and zoning administrator, about Palo Alto County's zoning ordinances relating to wind energy turbines. Approximately four months later, Mark Zaccone of another company, Invenergy, L.L.C., contacted Neary with the same inquiry. Invenergy is the parent company of Palo Alto Wind Energy, L.L.C. (PAWE). Invenergy was interested in developing a 340-megawatt, 170-turbine wind energy project in Palo Alto County that would be owned and operated by MidAmerican Energy Company (MidAmerican).

At that time, there were only a few wind turbines in Palo Alto County. The existing ordinance, which had been modified most recently in 2003, contained only a single paragraph devoted to wind turbines. The members of the Palo Alto County Planning *194 and Zoning Commission believed that a more detailed ordinance was needed.

During the first half of 2016, County Attorney Peter Hart worked on drafting a new zoning ordinance, modeling his efforts on ordinances from other Iowa counties. Invenergy personnel interacted with Hart and offered suggestions during the drafting process. However, Invenergy and MidAmerican were not satisfied with the final draft that emerged from the Commission meeting on August 11. On August 26, they sent strongly worded written comments to each member of the Palo Alto County Board of Supervisors, explaining that "nearly all of these revisions are necessary in order to establish a wind ordinance that will actually allow a wind project to be developed."

Among other things, Invenergy and MidAmerican urged the Board to reconsider the Commission's proposed 2640-foot setback for wind turbines from permanent residential dwellings. They said such a setback "would make developing a Wind Energy Conversion System in the County practically impossible." They pointed out that other counties have generally implemented a 1000- to 1320-foot setback, and a setback greater than 1500 feet "would make it virtually impossible for Invenergy to move forward with the proposed project and may very well deter other wind development within the County." Invenergy and MidAmerican also proposed that the Board modify a proposed 2640-foot setback from cemeteries in favor of a 1000-foot setback.

In addition, Invenergy and MidAmerican urged the Board to remove a provision from the ordinance that prohibited the occurrence of any shadow flicker on an existing residential structure, explaining that shadow flicker (i.e., the shadows cast by a rotating turbine within a residence) "is an unavoidable consequence of having an operational Wind Energy Conversion System in the County." Invenergy and MidAmerican proposed instead a provision that

no non-participating Permanent Residential Dwelling will experience more than 30 hours per year of shadow flicker under planned operating conditions. If an owner of a non-participating Permanent Residential Dwelling experiences more than 50 hours of shadow flicker per year under ... normal operating conditions, then the Owner/Developer shall be obligated to mitigate such shadow flicker to comply with the terms of this ordinance.

Other modifications were also sought. In conclusion, their letter made it clear that without a number of these requested changes, the 340-megawatt wind project would not go forward.

In September, the Board approved a modified wind energy ordinance that incorporated a number of Invenergy and MidAmerican's demands, including a minimum setback of 1500 feet from residences. However, the Board did not adopt everything Invenergy and MidAmerican had requested. For shadow flicker, the ordinance imposed a mitigation obligation whenever thirty hours per year (not fifty) of shadow flicker occurred. The ordinance also established a 1500-foot setback (not 1000) from cemeteries.

Three public readings of the ordinance occurred on September 13, September 20, and September 27. At the final public reading on September 27, the Board unanimously passed and approved the "Wind Energy Conversion Systems Ordinance" (Ordinance) for Palo Alto County.

Nearly one year later, on August 31, 2017, Invenergy and its subsidiary PAWE submitted an application for site plan review and approval. The application requested approval for the 340-megawatt *195 wind energy project, including 199 potential turbine locations.

The Board held an informational meeting on the application on September 21 and a public hearing on October 5. The project was discussed as well at other public Board meetings in September and October. The Board also received correspondence from the Iowa Department of Natural Resources and the state archaeologist who made recommendations for reducing or avoiding environmental or cultural harms the project could cause. In addition, the Board received a report from acoustician Richard James of E-Coustic Solutions contending the sound volume produced by the wind energy project would at times exceed fifty decibels in violation of the ordinance.

On October 24, the Board held a further meeting and received additional oral and written comments, including remarks by plaintiff Stephen Mathis. At the conclusion of the meeting, the Board granted conditional approval to PAWE's application by a 3-2 vote.

At the time of the approval, PAWE and not MidAmerican owned the project. However, MidAmerican acknowledged that it "intend[ed] to acquire, but ha[d] not yet acquired, the Project from PAWE based on and subject to certain development milestones pursuant to a purchase agreement executed by PAWE and MidAmerican." MidAmerican was not then legally obligated to acquire the project and could have terminated the asset purchase agreement for its convenience.

On November 22, the plaintiffs filed a petition for declaratory and injunctive relief and for a writ of certiorari against the Board in the Iowa District Court for Palo Alto County. As amended, the petition sought (1) a declaration that the ordinance was arbitrary, capricious, unreasonable, void, and unenforceable; and (2) a writ determining that the approval of PAWE's application should be set aside as illegal, arbitrary, capricious, unreasonable, and void. PAWE and MidAmerican were granted leave to intervene as defendants.

On June 8, 2018, PAWE and MidAmerican filed a motion for summary judgment seeking to dismiss the plaintiffs' claims. On June 11, the Board joined in PAWE and MidAmerican's motion. On July 25, the district court entered an order sustaining the motion for summary judgment. The plaintiffs appealed, and we retained the appeal.

II. Standard of Review.

"We review summary judgment rulings for correction of errors at law."

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
927 N.W.2d 191, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mathis-v-palo-alto-county-board-of-supervisors-iowa-2019.