Mathieu v. Venture Stores, Inc.

494 N.E.2d 806, 144 Ill. App. 3d 783, 98 Ill. Dec. 684, 1986 Ill. App. LEXIS 2404
CourtAppellate Court of Illinois
DecidedJune 6, 1986
Docket84-2783
StatusPublished
Cited by15 cases

This text of 494 N.E.2d 806 (Mathieu v. Venture Stores, Inc.) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mathieu v. Venture Stores, Inc., 494 N.E.2d 806, 144 Ill. App. 3d 783, 98 Ill. Dec. 684, 1986 Ill. App. LEXIS 2404 (Ill. Ct. App. 1986).

Opinion

JUSTICE LORENZ

delivered the opinion of the court:

This appeal arises out of plaintiff Robert Mathieu’s suit under the Structural Work Act (Ill. Rev. Stat. 1985, ch. 48, par. 60 et seq.) for injuries he sustained while working on the construction of a Venture store in Norridge on May 17, 1977. Plaintiff sued Venture Stores, Incorporated (the owner), W. E. O’Neil Construction Company (the general contractor), and Hastings & Chivetta (the architects). Venture and O’Neil filed cross-claims against each other for indemnification. Both defendants also filed third-party complaints seeking indemnification from subcontractors North American Masonry and Precast Erectors, Incorporated, and Hufschmidt Engineering Company.

The jury found for Hastings & Chivetta on plaintiff’s claim, and it is not a party to this appeal. However, the jury found for plaintiff as against Venture and O’Neil, awarding $450,000. The trial court directed verdicts for O’Neil on Venture’s indemnity claim and for Venture on O’Neil’s indemnity claim. The court also directed verdicts for Hufschmidt and North American on O’Neil’s third-party indemnity claims. In bifurcated deliberations the jury then found for Hufschmidt but against North American on Venture’s third-party indemnity claims.

On appeal, Venture contends: (1) the evidence did not establish its liability to the plaintiff; (2) the court erred in .directing a verdict for O’Neil on Venture’s counterclaim for indemnity; (3) the jury verdict for Hufschmidt on Venture’s third-party indemnity claims was contrary to the manifest weight of the evidence; (4) Venture was prejudiced by evidence that Hufschmidt was out-of-business; (5) the court erred in not excusing for cause a juror when that juror learned that he was a defendant in a civil suit; (6) it was error to allow the jury to take notes during opening argument; (7) certain evidentiary errors by the trial court prejudiced Venture; (8) a jury verdict instruction was improperly phrased. North American contends: (9) the court should have granted its motion for a directed verdict on Venture’s third-party indemnity claim. O’Neil contends: (10) the court erred in striking the defense of comparative fault from O’Neil’s answer; (11) the court erred in directing verdicts for Venture, North American, and Hufschmidt on O’Neil’s indemnity claims; (12) the jury award was excessive. Finally, Venture, North American and O’Neil all contend: (13) that the court erred in severing, for separate jury consideration, the third-party indemnity claims.

We affirm.

The plaintiff, a North American employee, was injured while attempting to install a 3,000-pound precast concrete panel. A crane attached to the panel was disconnected because the prior installation of a canopy prevented using the crane in the final stages of the panel’s installation. A second device not used to temporarily secure the panel was a pole brace and deadman (a cylindrical 3- to 4-foot hole filled with concrete used to anchor the pole brace attached to the panel). Instead a C-clamp was used to secure the panel. As plaintiff was working on a ladder against the panel, the panel began to fall over, forcing him to jump from the ladder.

John Strong, a graduate engineer, was, in May 1977, vice-president of engineering and construction for Venture. He was also the director of Venture’s design and construction department, with a staff that included a construction superintendent, Carl Teare. They solicited proposals from three architectural firms and selected Hastings & Chivetta. A general construction contract was then entered into between Venture and W. E. O’Neil Construction Company.

The O’Neil contract required O’Neil to submit to Venture a construction schedule. This would show starting and completion dates for various stages of construction, including installation of precast concrete and structural steel. Venture had the power to suggest schedule revisions, although it often would accede to the opinion of O’Neil, which had the responsibility for compliance. Venture also had the right, with just grounds, to disapprove the scheduling. Approval of the schedule would have been by Carl Teare or Strong, or both of them. Although Strong could not specifically recall if he approved the schedule submitted by O’Neil, he assumed that it was approved.

According to Strong the decision to include the four precast concrete panels by the main entryway was that of Venture’s and the architect’s. He could not recall whether he knew in 1977 that the precast concrete panels were to be installed after the canopy. However he conceded that this quite possibly would have been included in O’Neil’s master schedule. He also testified that he could have determined the -method of installing these panels by looking at the architects’ plans. Strong also testified that Venture could have required O’Neil to install the precast concrete panels before the canopy was on. Strong, who was at the job site an average of once a week during the foundation phase and once a month thereafter, stated that he may have been present when the precast concrete panels were being positioned.

Strong also testified that under the O’Neil contract Venture retained the right to review and reject O’Neil’s subcontractors or even to hire subcontractors and assign them to O’Neil. O’Neil was required to comply with all Federal, State, and local safety rules. Venture retained the right to terminate O’Neil if it disregarded rules or failed to properly supervise the work. The contract also gave Venture the right to terminate O’Neil for failure to comply with the sequencing schedule.

According to Strong the duties of Venture’s construction superintendent, Carl Teare, were supervising compliance with the budget, schedule, and quality levels. In a deposition he had testified more broadly that Teare was to supervise the construction of the building. Strong also conceded that Teare’s quality-compliance monitoring duties would include safety. Teare was to bring unsafe practices to the attention of the general contractor, O’Neil, and also could stop any unsafe actions. Teare also conducted job meetings with O’Neil’s representative to discuss scheduling problems. On occasion Strong attended these meetings. Both Strong and Teare, as agents of Venture, “most probably” had the authority to stop any unsafe work.

Anthony Chivetta, a partner in the architectural firm of Hastings & Chivetta, testified that Venture had requested that they include the precast concrete slabs in their plans.

Thomas Blazek, general manager of Hufschmidt Engineering in 1977, testified that his firm was the supplier of the precast concrete panels. Before Venture hired its general contractor, O’Neil, Hufschmidt had already begun production of the panels, pursuant to an oral agreement with Carl Teare of Venture. Carl Teare also requested that Hufschmidt select North American as subcontractor for erection of the panels, and Blazek agreed to this.

Subsequently, the actual contracts between O’Neil and Venture, O’Neil and Hufschmidt, and Hufschmidt and North American were executed. The O’Neil-Hufschmidt contract specified that Hufschmidt was to supply the materials and labor to erect the panels, although provision was also made for subletting part of the work with O’Neil’s permission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

People v. Vazquez
2026 IL App (2d) 240561-U (Appellate Court of Illinois, 2026)
Tsai v. Karlik
2021 IL App (1st) 182200-U (Appellate Court of Illinois, 2021)
Anderson v. Alberto-Culver USA, Inc.
Appellate Court of Illinois, 2003
Barton v. Chicago & North Western Transportation Co.
757 N.E.2d 533 (Appellate Court of Illinois, 2001)
People v. Rivera
621 N.E.2d 179 (Appellate Court of Illinois, 1993)
General Tire & Rubber Co. v. Industrial Commission
582 N.E.2d 744 (Appellate Court of Illinois, 1991)
Dubrovich v. Commonwealth Edison Co.
568 N.E.2d 285 (Appellate Court of Illinois, 1991)
Mondelli v. Checker Taxi Co.
554 N.E.2d 266 (Appellate Court of Illinois, 1990)
Overbeck v. Jon Construction, Inc.
540 N.E.2d 969 (Appellate Court of Illinois, 1989)
Soderquist v. St. Charles Mall Associates, Ltd.
532 N.E.2d 903 (Appellate Court of Illinois, 1988)
Brazier v. Kontos
513 N.E.2d 152 (Appellate Court of Illinois, 1987)
Dillon v. U. S. Steel Corp.
511 N.E.2d 1349 (Appellate Court of Illinois, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
494 N.E.2d 806, 144 Ill. App. 3d 783, 98 Ill. Dec. 684, 1986 Ill. App. LEXIS 2404, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mathieu-v-venture-stores-inc-illappct-1986.