Masterson v. F. W. Heitman & Co.

77 S.W. 983, 33 Tex. Civ. App. 464, 1903 Tex. App. LEXIS 531
CourtCourt of Appeals of Texas
DecidedNovember 11, 1903
StatusPublished
Cited by1 cases

This text of 77 S.W. 983 (Masterson v. F. W. Heitman & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Masterson v. F. W. Heitman & Co., 77 S.W. 983, 33 Tex. Civ. App. 464, 1903 Tex. App. LEXIS 531 (Tex. Ct. App. 1903).

Opinions

PLEASANTS, Associate Justice.

Appellees brought this suit against appellant to recover the sums of $146 and $550, alleged to be the unpaid balances of the agreed purchase price of two pumps, with the necessary fittings and appliances, sold by them to appellant, and the further sum of $1410.62, alleged to be the reasonable value of certain goods, wares and merchandise sold and delivered by them to the appellant.

The answer of defendant admitted the balances claimed as due on the purchase price of the two pumping plants, and also admitted the correctness of the larger portion of the open account, but as to certain items in said account, which were specified in the answer, denied that same were purchased or received by defendant. The answer further averred that the pumping plant was purchased by defendant under a contract with the plaintiffs whereby they undertook to install said plant on defendant’s farm in Bexar County, and have the same ready for operation by the 1st clay of May, 1901, but that plaintiffs failed to comply with their said contract and did not construct the plant within the specified time, and in fact never fully completed the construction of same; that the defendant had to complete the construction of said plant at his own cost and expense in the sum of $300; that by reason of plaintiff’s delay in constructing said plant defendant lost the crop upon his *465 said farm, which was of the value of $15,000, and defendant prayed for judgment against the plaintiffs for the value of said crop and for the sum of $300 expended by him in completing the construction of said pumping plant. To this answer the plaintiffs by supplemental petition replied as follows:

1. They denied that the defendant had sustained any loss or damage by reason of any of the matters alleged by him.

2. They pleaded to the effect, in substance, that the delay was caused by defendant’s failure to perform his part of the contract, especially in failing to furnish the foundation for the pump, as in duty bound to do.

3. They further pleaded to the effect, in substance, that if defendant had sustained any loss by reason of any breach on plaintiffs’ part, the damaging consequences could and would have been averted by ordinary care on defendant’s part, as in duty bound, so far as might be by ordinary effort and moderate expense; and further, that the claim for damages set up was fictitious and without merit, and was asserted merely as a pretense for avoiding payment of the plaintiffs’ just demand, and as an excuse for delay in the payment thereof.

The trial in the court below by a jury resulted in a verdict in favor of the plaintiffs for the full amount claimed by them.

The record discloses the following facts: The appellant, being the owner of a farm in Bexar County which he desired to irrigate, procured an engineer to make a topographical survey of said farm, run the levels and prepare the plans for an irrigation plant. After the completion of these plans appellant with a map or sketch of same went to appellees, who were engaged in the business of selling and installing pumps and other machinery for the operation of irrigating plants, and requested them to give him an estimate of the cost of installing a pump of sufficient capacity to furnish the. water required by the irrigation plans. Appellant explained to appellees that unless the pump could be installed and put in operation by the 1st of May, 1901, he did not desire to purchase same. Appellees would not make a contract to furnish the pump by the 1st of May until they had sent a telegram to the factory to find if a pump sufficient for the work could be procured at once. After learning that such pump could be procured they agreed with appellant to furnish him with same, and have it installed and in operation by the 1st of May, 1901. The price agreed upon for the pump and necessary fittings and the cost of installing same was $1000. When this agreement was made appellant explained to the agent of appellees, with whom the contract was made, that he intended to use the boiler in use in a gin which he had on his farm to supply the power for running the pump, and that he had on his farm the necessary piping for conveying the steam from.the boiler to the pump; that appellant would have all the hauling done, furnish all the unskilled labor necessary for work of installing the pump, and furnish the material for the foundation, and these items were not included in making the estimate of the cost *466 of the pumping plant. Appellant lives in the city of Galveston, and the farm on which the pumping plant was to be installed was near the town of Lacoste, in Bexar County. Appellees’ place of business is at Houston, Harris County.

On the day after this contract was made appellees telephoned appellant at Galveston asking permission to substitute for the pump contracted for one that would cost $100 more. In response to this request appellant met appellees’ agent in Houston, and after consulting with him in the matter agreed to the substitution. Some days after this appellees’ agent requested appellant to sign a written order for the machinery. This order, so far as it bears upon the issues of this ease, was as follows:

“April 6, 1901.—F. W. Heitman & Co., Houston, Texas: You will please order for the undersigned, shipped to Lacoste, on or about April 10, 1901, one 8x12x12x10 Worthington compound duplex pump, with 00 feet of suction and discharge pipe and the necessary fittings, you to furnish a man to superintend erection and setting of pump; 1 to furnish all foundations and common labor and necessary pipe to make steam connection, which is to be connected by you. Pump guaranteed to have a capacity of 1200 gal. per minute against a 73-foot head, with a GO h. p. boiler. Pump 'to be erected by May 1. Cash with order, $550; note due Nov. 1, 1901, $550. (Signed) Branch'T. Masterson.”

Appellees fully understood at the time the contract was made that the pump was wanted to furnish. water for the purpose of irrigating appellant’s crop, and that the crop would need the water by the 1st of May. Appellees ordered the pump shipped at once and it reached appeliant’§ farm on April 26th. Nothing further was done by appellees in the performance of their, contract until May 1st, when they telephoned the Alamo Iron, Works at San Antonio and arranged with that company to have the pump installed. On May 3d the Alamo Iron Works sent a man to the farm to take the measurements for the suction and discharge pipe for the pump. This piping was sent out to the farm on May 13th. On May 11th appellees addressed the following letter to appellant’s manager on the farm:

“May 11, 1901.—Mr. Max Reicherzer, Lacoste, Texas: Dear Sir.—■ We have arranged with the Alamo Iron Works to attend to the setting of the pump sold Mr. Masterson. When you have the material for the foundation and the mason ready, please communicate with them and they will send a man there to superintend the setting of the pump. Mr. Masterson called on us yesterday and is very anxious to get the pump started, and the only delay that can be caused now will be by you not having the material ready. Please take this up with the Alamo Iron Works, who will superintend the erection of the engine. F. W. Heitman & Co.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Masterson v. F. W. Heitmann & Co.
87 S.W. 227 (Court of Appeals of Texas, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
77 S.W. 983, 33 Tex. Civ. App. 464, 1903 Tex. App. LEXIS 531, Counsel Stack Legal Research, https://law.counselstack.com/opinion/masterson-v-f-w-heitman-co-texapp-1903.