BREYER, Circuit Judge.

Massachusetts objects to a particular rate-setting practice used by the Western Massachusetts Electric Company. The practice falls within the regulatory jurisdiction, not of Massachusetts, but of the Federal Energy Regulatory Commission; it is embodied in a private utility agreement, which FERC has approved. Massachusetts told the utility to seek FERC’s approval to change the rule. The utility filed a notice of change with FERC, in accordance with the procedures contained in § 205 of the Federal Power Act, 16 U.S.C. § 824d. FERC rejected the proposed change, because it believed that this particular statutory provision governs changes that the utility itself proposes, not those that a state regulator requires it to propose. If Massachusetts objects to the rule, says FERC, it should file a complaint in accordance with a different statutory procedure, namely, that contained in § 206 of the Federal Power Act, 16 U.S.C. § 824e. Massa[887]*887chusetts appeals FERC’s decision. We find that FERC was right.

The procedural dichotomy here involved — between §§ 205 and 206 — is often found in statutory schemes of public útility rate regulation — regulation that typically consists of a public commission’s review of a private utility’s rates and practices to determine whether they are reasonable. Both state and federal regulatory statutes often provide two different “tracks” for review. The first allows the commission, acting either on its own initiative or after a complaint, to change existing utility rate practices. To do so, the commission or the complainant must prove that the practices are unreasonable. The existing rates stay in effect while the proceedings take place; and, typically, the utility has no obligation to give customer refunds, even if the rates are found unreasonably high. The second track allows the commission to review changes that the utility intends to make. Typically, the commission may suspend the proposed change for a few months; then, if the proceedings are not yet finished, the change takes effect, subject to a refund obligation if the change is found unreasonable. See, e.g., 15 U.S.C. §§ 717c-717d (natural gas); 49 U.S.C. §§ 10704, 10708 (rail carriers with market dominance); Ill.Stat. ch. 111⅔, §§ 36, 41; Mass.Gen.Laws ch. 164, §§ 93-94; N.H.Stat. §§ 378:7, 8; Ohio Code §§ 4909.15, 4909.18; 66 Pa.C.S.A. §§ 1308-09, R.I.Gen.Laws §§ 39-3-11,-12.

The first of these tracks is here found in § 206 of the Federal Power Act. It states that

[wjhenever the Commission, after a hearing had upon its own motion or upon complaint, shall find that any rate ... or ... any rule, ... practice, or contract affecting such rate ... is ... unreasonable ..., the Commission shall determine the ... reasonable rate, ... practice, or contract ... and shall fix the same by order.

16 U.S.C. § 824e(a). The second of these tracks is here found in § 205 of the Federal Power Act. It states that

every public utility shall file with the Commission ... schedules showing all rates and ... practices ... and ... contracts which ... relate to such rates____ [N]o change shall be made ... except after sixty days’ notice____ Such notice shall be given by filing with the Commission ... new schedules____ Whenever any such new schedule is filed the Commission shall have authority ... to enter upon a hearing concerning the lawfulness [of the changes] ...; and, pending such hearing and the decision thereon, the Commission ... may suspend the ... [new] schedule ... [for no longer than] five months ---- If ... an order [has not been] made at [the end of] ... five months, [the changes] ... shall go into effect ..., but in case of a proposed increased rate or charge, the Commission ... [may require a refund of any] portion of such increased rate[ ] ... as by its decision shall be found not justified. At any hearing involving [a rate increase], the burden [of proving an increase] just and reasonable shall be upon the public utility____

16 U.S.C. § 824d(c)-(e). In essence, FERC says that Massachusetts should use the first track to obtain review of the utility’s contractual rate rule; Massachusetts in “ordering] the Company to petition FERC for an amendment” essentially tried to use the second track by telling the utility to file a “new schedule” containing the changes it desired.

The specific narrow statutory question before us is whether § 205 applies to this type of regulator-compelled rate change. Do the § 205 statutory words “change,” “such new schedule,” and so forth, include this type of change or “new schedule?” The words of the statute do not themselves resolve the problem, for one might read them either as including or excluding the type of “utility-proposed” change here at issue. FERC says that they do not include [888]*888this type of change. We are fully aware of the special attention that a court should pay to an agency’s interpretation of its own authorizing statute, NLRB v. Hendricks County Rural Electric Membership Corp., 454 U.S. 170, 177, 102 S.Ct. 216, 222, 70 L.Ed.2d 323 (1981); Ford Motor Credit Co. v. Milhollin, 444 U.S. 555, 565, 100 S.Ct. 790, 796, 63 L.Ed.2d 22 (1980); Ford Motor Co. v. NLRB, 441 U.S. 488, 495, 99 S.Ct. 1842, 1848, 60 L.Ed.2d 420 (1979); NLRB v. Bell Aerospace Co., 416 U.S. 267, 274-75, 94 S.Ct. 1757, 1761-1762, 40 L.Ed.2d 134 (1974), particularly when the subject matter is one of proper procedure necessary to facilitate the agency’s work, see Oldham v. Secretary of Health and Human Services, 718 F.2d 507, 510 (1st Cir.1983). And here there is more than sufficient support for FERC’s interpretation.

For one thing, FERC’s interpretation is more consistent with the purposes of the entire procedural scheme. Like most traditional regulatory schemes, the two provisions together allow the utility the choice among various reasonable rate practices. Unless the Commission can prove that an existing rate practice is unreasonable, the utility’s previously filed rate practice may remain in effect. Similarly, the utility may change any rate practice so long as it can prove that the proposed change is reasonable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
729 F.2d 886, Counsel Stack Legal Research, https://law.counselstack.com/opinion/massachusetts-v-united-states-ca5-1984.