Maryland Casualty Co. v. Morgan County Court

59 F.2d 414, 1931 U.S. App. LEXIS 4063
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 19, 1931
DocketNo. 3167
StatusPublished

This text of 59 F.2d 414 (Maryland Casualty Co. v. Morgan County Court) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. Morgan County Court, 59 F.2d 414, 1931 U.S. App. LEXIS 4063 (4th Cir. 1931).

Opinions

NORTHCOTT, Circuit Judge.

This is a suit in equity brought by appellant, surety, upon a performance bond given by W. J. and J. T. Gephart, contractors, to the county court of Morgan county, W. Va., for the construction of a certain highway in said county, against all known creditors of said Gepharts furnishing labor and material upon said contract and against the county court of Morgan county.

On the 12th day of Juno, 1922, W. J. and J. T. Gephart were awarded a contract for tho construction of a certain highway in Morgan county, W. Va., known ns the “Paw Paw Great Caeapon Road,” said road being in two sections; the “Paw Paw” road being about three miles of macadam; and tho “Great Caeapon” road-being about five miles of grading and draining.

Tho bond secured not only the performance of the contract, but contained covenants to pay all and every person furnishing material or performing' labor in and about tho construction of said contract.

On the 2d day of November, 1923, W. J. and J. T. Gephart became Insolvent and subsequently adjudged bankrupt for acts done as of said dato. At said time tho Morgan county contracts were not completed, and tho Gepharts owed to various creditors the approximate sum of $11,500 for labor and materials used upon said road. Maryland Casualty Company advanced tho money for the past-duo pay roll owing’ by the Gepharts, taking assignments from, the laborers and a deed of trust from Gepharts. On or about the 9th day of November, 1923, the Gep-harts abandoned all work upon the highway, and Maryland Casualty Company completed the road at an approximate expense of $16,-500, exclusive of creditors’ claims.

Thei'o were various matters in controversy between the county court and tho casualty company, and the cause was referred by tho judge below to a special master, who reported that tho casually company was entitled to recover from tho county court Hie sum of $23,297.38, with interest from April 1, 1926, the dato of the filing' of said report.

The only creditor whose claim had not been settled was appellee R, E. Eeller, trading as Standard Concrete Pipe Company, and the casualty company contested this claim on the ground that the said Gepharts had unduly extended credit to Feller.

Tho master in his report found against Feller and in favor of the casualty company. On exceptions to the master’s report, the judge below set aside the findings of the master; found that the county court of Morgan county owed the casualty company nothing, and gave R. F. Feller judgment against the casualty company in the sum of $1,002.33, with interest from April 1, 1926, from which action of the court below the casualty company brought this appeal.

It is contended on behalf of the county court that the casualty company did not take over the completion of the road work when the Gepharts, as contractors, abandoned their contract, and that there was no formal notice of abandonment, and that the casualty company look over the contract of the Gep-harts as assignee and not as surety, and therefore In all respects stood in the shoes of the Gepharts with regard to all transactions of the county court.

The specifications under which the contract was let contained the following provisions: “If the Contractor * * * shall discontinue the prosecution of the work, or if the Contractor shall become insolvent or declared bankrupt, or commit any act of bankruptcy or insolvency * * * or shall make an assignment for the benefit of creditors, or from any other cause whatsoever shall not carry on the work in an acceptable manner, the Engineer shall give notice in writing to tho Contractor and his Surety, of such delay, neglect or default, specifying the samo, and if the Contractor, within a period of ten (10) days after such notice shall not proceed in accordance therewith, then the County Court shall, upon written certificate from the Engineer of the fact of such delay, neglect or default and the Contractor’s failure to comply with such notice, have full power and authority, without violating the contract, to take the prosecution of the work out of the hands of such Contractor, to appropriate or use any or all materials and equipment on the ground as may he suitable and acceptable and may enter into an agreement for the completion of said contract according to the terms and provisions thereof, or use such other methods as in his opinion shall be required for the completion of said contract in an acceptable manner. * * * ”

It is admitted that default of the contractors was not formally made, and it seems clear that the county court did have the privilege and the right to designate who should [416]*416undertake the completion of the work, yet it is also true that the casualty company only entered into undertaking to complete the contract because of the bond it had given and the force of its obligation as surety. "As was ably said by Judge Parker of this court in Lacy v. Maryland Casualty Co., 32 F.(2d) 48, 53: “The point is made that there was no default under the contract, and that consequently the right of subrogation on the part of the casualty company did not arise. It is true that the work under the contract was not interrupted and no notice of default was given to the casualty company, but it appears that on May 24, 1923, the contractor had become insolvent and was unable to proceed with his contract and that the company, without waiting for notice, advanced the funds to carry on the work, notified the highway commission that it was doing so, and eventually took the contract over. There can be no question that the company did this, not as a volunteer, but because of legal necessity, i. e., because it had guaranteed the performance of the contract and the contractor was financially unable to perform it. Under the principles laid down in the Prairie State Bank Case [164 U. S. 227, 17 S. Ct. 142, 41 L. Ed. 412] and Henningsen Case [208 U. S. 404, 28 S. Ct. 389, 52 L. Ed. 547], therefore, ■it is clear that the right of subrogation arose. Being compelled because of its contract to advance money to prevent a breach of the contract of the principal, the surety is in no different position, we think, from what it would oeeupy if it had made the advancement after breach or had performed the contract itself. It is the payment under necessity because of the contract of suretyship, and not the breach of the principal's contract, which entitles the surety to subrogation.”

We do not think, however, in view of our conclusion as to other questions involved, that it is necessary to decide the question as to whether the casualty company completed the contract as assignees.

It was contended by the county court, and clearly proven, as we see it, by the evidence, that the contractors, either by a mistake or carelessness, almost amounting to fraud, were clearly overpaid in the estimates given them by the engineers, an amount in excess of' the sum claimed by the surety. These overpayments would, as we see it, be properly chargeable against the retained percentage due contractors, and the balance of such wrongful overpayment would be a proper charge against the bond.

This overpayment was brought about through what was a wrong system of measurement of the work done, and wrong estimates given by the engineer. The court below found the mistakes to be so gross as to practically amount to fraud.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Camden v. Stuart
144 U.S. 104 (Supreme Court, 1892)
Prairie State Bank v. United States
164 U.S. 227 (Supreme Court, 1896)
Guaranty Co. v. Pressed Brick Co.
191 U.S. 416 (Supreme Court, 1903)
Illinois Surety Co. v. John Davis Co.
244 U.S. 376 (Supreme Court, 1917)
Maryland Casualty Co. v. Ohio River Gravel Co.
20 F.2d 514 (Fourth Circuit, 1927)
Pickens County v. National Surety Co.
13 F.2d 758 (Fourth Circuit, 1926)
Lacy v. Maryland Casualty Co.
32 F.2d 48 (Fourth Circuit, 1929)
American Bonding Co. v. United States
233 F. 364 (Third Circuit, 1916)
National Surety Co. v. Lincoln County
238 F. 705 (Ninth Circuit, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
59 F.2d 414, 1931 U.S. App. LEXIS 4063, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-morgan-county-court-ca4-1931.