Maryland Casualty Co. v. East Baltimore Driving Ass'n

108 A. 517, 135 Md. 105, 1919 Md. LEXIS 130
CourtCourt of Appeals of Maryland
DecidedNovember 13, 1919
StatusPublished
Cited by4 cases

This text of 108 A. 517 (Maryland Casualty Co. v. East Baltimore Driving Ass'n) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Casualty Co. v. East Baltimore Driving Ass'n, 108 A. 517, 135 Md. 105, 1919 Md. LEXIS 130 (Md. 1919).

Opinion

Urner, J.,

delivered the opinion of the Court.

The Maryland Casualty Company, as surety for Pinning and Company, a firm of contractors, executed a bond to the East Baltimore Driving Association, Incorporated, to “indemnify the obligee against any loss or damage directly arising by reason of the failure of the principal to faithfully perform” the written contract to which the bond refers and which it describes as providing “for clearing site and furnishing fence posts on eighty acres of land at Benjies Station, Maryland.” In the contract itself the work to be performed by Pinning and Company, party of the first part, for the East Baltimore Driving Association, party of the second part, is *107 thus specified: “To cut down all trees now on the 80 acres of land to be used by tbe party of the second part for a race course, except such trees that the said party of the second part mia,y designate that they desire to remain standing. To cut down all brush on said acres and to either remove same or burn, tbis to be left to the discretion of the said party of the first part. To take out of said acres of land all- stumps, and to remove them from the said land, and to burn all leaves. And all timber cut down to be the property of the party of the first part,. To- furnish on the said land 6,000 fence posts from materials now on the land, 3,000 posts to be 7 foot long and 3,000 to be 11 foot long.” It was provided that twelve acres of the ground should be cleared in thirty, and the remainder of the tract in sixty, working days. The amount agreed to be paid for tbe entire work Was $1,800, of which one-half was payable when half of the work was done, and the balance when it was fully completed.

The pending suit on the contractors’ bond was brought to recover damages occasioned by their failure to finish the work which the contract required them to perform. It was alleged in the declaration that the work was begun hut was after-wards abandoned and left to a large extent unfinished. The bill of particulars as to the damages claimed for the breach of the contract contained four items, three of which were estimates of the cost of completing the work, which in fact has never been resumed by anyone, and the fourth item was: “To amount of lumber, wood and trees removed from said property in direct violation of the contract and which, under the contract, were to be left on the premises and used as fence posts and posts — $2,000.”

Issue was joined in the case on pleas filed separately by Pinning and Company and the Maryland Casualty Company, and the trial resulted in a verdict and judgment in favor of the plaintiff for $1,500. The pleas of the Casualty Company, which is the only appellant, make defense on the ground that the plaintiff corporation did not on its part,perform the contract or comply with requirements of the bond which were *108 therein made conditions precedent to its enforcement. It is averred in the pleas that while the contractors performed more than onedia.lf of the work to he done under the contract and thus became entitled to he paid one>-half of the stipulated sum of $1,800, yet no part of the amountso- earned was paid except the sum of $200, and that the plaintiff failed to deliver to the Casualty Company, as required by the bond, a written statement of the contractors’ default within ten days after* it came to the plaintiff’s knowledge. There were other pleas of the same defendant., denying that the plaintiff sustained any loss on account of the alleged breach, or that any default oecurred on the part of the contractors. •

The record contains five hills of exceptions. E'rom the first it appears that, after proving the contract and the bond and offering testimony tending to show that the contractors abandoned the work when much less than half of it was completed, and that they furnished no posts as required by the contract, the plaintiff called a witness who testified that he had exa-m- ■ ined the land in question and the timber on it before and since it was partially cleared by Pinning and Company, that he. was a general contractor and builder, had been raised on a farm and had done considerable work in clearing timber land, and that in the spring of 1917, when operations were in progress under this contract, he bought posts of the kind it. specifies for fifty cents apiece in Baltimore City, about thirteen miles distant from the land on which the work was being conducted. The witness was then asked what three thousand posts seven feet long, cut on the land in 1911, were worth. ' An objection to this question was overruled, and the witness answered that he wlould say they were worth about twenty-five cents each. The second exception was taken to a similar ruling on a question asked the same witness as to the value of eleven foot posts cut on the land at the period mentioned, and to,, which he replied that they were worth about thirty cents apiece. .

The two exceptions just noted were based partly on the theory that the witness was not qualified to estimate - the *109 values to which he testified. This is not a valid objection. The proof to which we have referred as to the experience and knowledge of the witness was sufficient to support the ruling of the trial Coiirt that he was qualified to express an opinion on .the subject of the inquiry. The same observation applies to the admission, as against the third exception, of the testimony of the architect, who planned and superintended the work tmder the’ contract, as to the value of the posts to be furnished by the; contractors out of the timber on the land to be cleared. It was testified by this witness- that he had been an architect and engineer for about forty years and that he was familiar with the values which he was asked to estimate. H'e stated that the posts, of the two sizes designated, were worth fifty and sixty-five cents apiece, respectively.

A moré important question raised on the three exceptions we have considered'is' whether any evidence, as to the value of the posts is admissible in view of the fact that-the plaintiff did not proceed to have the work completed, and did not thus demonstrate, or otherwise prove, the extent to which the posts could not be supplied from the trees remaining on the property. This is a fundamental question in the case. ■ . It .ip not only raised in reference to the admissibility of the evidence on which the plaintiff’s recovery was. based, but- it is involved in' some of the prayers which are presently to be discussed. The- contention, is that the plaintiff can. recover only for actual losses sustained as the result of the. failure of .the contractors .to finish the work, and that evidence as to the value of the posts was “irrelevant unless plaintiff further showed that it had actually purchased the posts, and was compelled to clo so in order to complete the contract, because there was insufficient or no timber on the land from which, posts could he fabricated.” , .

No effort was made to prove any loss except that which is claimed to have resulted from the breach of the provision as to the posts. The claims in the bill of particulars for the cost of completing the work were abandoned, the plaintiff, pqt baring in fact proceeded with the project, and the only testi *110

Free access — add to your briefcase to read the full text and ask questions with AI

Related

St. Paul Fire & Marine Insurance v. Molloy
433 A.2d 1135 (Court of Appeals of Maryland, 1981)
Canaras v. Lift Truck Services, Inc.
322 A.2d 866 (Court of Appeals of Maryland, 1974)
Food Fair Stores, Inc. v. Blumberg
200 A.2d 166 (Court of Appeals of Maryland, 1964)
Lancaster v. Celanese Corp. of America
163 A. 209 (Court of Appeals of Maryland, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
108 A. 517, 135 Md. 105, 1919 Md. LEXIS 130, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-casualty-co-v-east-baltimore-driving-assn-md-1919.