Maryland Attorney General Opinion 99OAG171

CourtMaryland Attorney General Reports
DecidedDecember 5, 2014
Docket99OAG171
StatusPublished

This text of Maryland Attorney General Opinion 99OAG171 (Maryland Attorney General Opinion 99OAG171) is published on Counsel Stack Legal Research, covering Maryland Attorney General Reports primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Maryland Attorney General Opinion 99OAG171, (Md. 2014).

Opinion

Gen. 171] 171

PROCUREMENT PUBLIC ETHICS LAW – APPLICABILITY OF PROCUREMENT CONFLICT OF INTEREST PROVISIONS TO PUBLIC-PRIVATE PARTNERSHIPS AND OTHER ALTERNATIVE PROJECT DELIVERY METHODS December 5, 2014

Michael W. Lord Executive Director State Ethics Commission

On behalf of the State of Maryland Ethics Commission, you ask whether public-private partnerships, “design/build” contracts, and certain other methods of obtaining goods and services are subject to the provision of the State Ethics Law that protects against conflicts of interest in the procurement process. See Md. Code Ann., Gen. Prov. (“GP”) § 5-508. We conclude that they are, but where the restrictions of the Ethics Law conflict with statutory provisions specific to the type of procurement, the more specific provisions will control. Thus, as to public-private partnerships (“P3s”), where the provisions of Title 10A of the State Finance and Procurement Article expressly allow the government and potential offerors to discuss project specifications, those provisions will prevail over the provisions of GP § 5-508 that would otherwise prohibit such discussions. As to the other project delivery methods included within your request, we also conclude that GP § 5-508 applies, but where the statutory or regulatory provisions applicable to those methods allow coordination between the government and private parties that the Ethics Laws would otherwise prohibit, those specific provisions would prevail. I Background A. The Evolution of the Traditional Procurement Process 1. Traditional Competitive Procurement The development of public facilities or infrastructure has traditionally followed a familiar “design/bid/build” project delivery method in which each component of the project is separately procured and each component is substantially 172 [99 Op. Att’y

completed before the next begins. For example, the development of a new State office facility might begin with a competitive process for design services to be provided by an architectural or engineering firm. The State drafts specifications, incorporates those specifications into a competitive solicitation, and firms submit competing proposals to provide those services. The State then evaluates the proposals, selects the successful proposer, and awards the contract. Once the successful architectural or engineering firm has completed designs for the project, those designs form the basis of the procurement for the second stage of the process. Ordinarily, this second stage is also a competitive sealed bid process, though designed to obtain the services of a contractor that would provide the labor, materials, and services necessary to build what the architects and engineers designed. The solicitation in the second stage unfolds much like the first: The State provides specifi- cations, advertises the opportunity to submit bids, and then reviews the bid proposals for responsiveness. The State selects the most favorable bid, awards the contract, and construction presumably gets underway. After the construction is complete, the State might proceed with a third or fourth stage to procure building operation or maintenance services. Each stage of the traditional design/bid/build process is separately solicited, separately contracted, and separately ap- proved. The separation of each stage is designed to foster competition among firms so that the State obtains the necessary goods or services at the lowest possible cost, thereby ensuring that the procurement, among other things, “get[s] the maximum benefit from the purchasing power of the State.” Md. Code Ann., State Fin. & Proc. (“SFP”) § 11-201(a)(7); see also Blind Indus. and Servs. of Maryland v. Maryland Dep’t of Gen. Servs., 371 Md. 221, 236 (2002). This has been the standard procurement model since the adoption of the Maryland procurement law in 1980. See 1980 Md. Laws, ch. 775. The competitive sealed bid process is the preferred source selection method. See SFP § 13-102(a). Its focus on obtaining the lowest price for goods and services is well suited to acquiring office supplies, consumer products, or other goods and services where the primary factor for an award is price. Competitive sealed bidding, however, may not always be the best method for delivering large public works projects, and, in fact, can cause problems on highly complex projects. For example, it might be more efficient to use a procurement method that allows for the Gen. 171] 173

construction firm to be involved early in the process so that it can coordinate with the design team to resolve constructability issues before construction begins. It might also be preferable to contract with a firm that is capable of providing both design and construction services at a combined lower cost than if those contracts were separately awarded and administered. And, because the stages of the competitive sealed bid procurement process occur in series, with each stage unfolding only after the previous one is complete, the ultimate delivery of the project can take a considerable period of time. 2. Alternative Project Delivery Methods In response to some of the limitations of traditional procurement, State agencies have been authorized to employ various other methods of project delivery, such as competitive sealed proposals, design/build projects, “construction management at risk” contracts, and public-private partnerships. Although these approaches to government contracting take many different forms, they all permit agencies to better meet the needs of the State by providing greater flexibility, potential cost savings, and faster project completion. One such alternative project deliver method is “design/build.” Under the design/build method, a single con- tractor performs both the design and construction elements of a public infrastructure project. See SFP § 3-602(g)(1) (describing “design/build” contracts as those that involve “a single soli- citation to design and build the facility”); COMAR 21.05.11.01B(1) (defining a design/build contract as “a project delivery method in which a single entity is contractually responsible for both design and construction of a project”). For example, the State might solicit proposals for an office building, but instead of first soliciting and completing the design for the building, and then soliciting and conducting construction, the design/build approach includes both services under a single solicitation. Both functions are thus performed by one contractor. The use of the design/build project delivery method is specifically permitted by, and governed by, the procurement regulations. See generally COMAR 21.05.11; see also SFP §§ 12-101 (authorizing the Board of Public Works to adopt procurement regulations); 3-602(g) (specifically authorizing capital project funding for “alternative construction methods” such as “design/build” contracts). 174 [99 Op. Att’y

The “fast track” approach is another alternative project delivery model. Unlike the design/build method, which con- solidates the design and construction functions into one procurement and one contractor, the fast track approach preserves the separation between the two procurement stages and project functions, but permits “design and construction [to be] implemented concurrently.” SFP § 3-602(g)(2); see also COMAR 23.03.01.01B(17) (procurement regulations governing public school construction; explaining that, under the “fast track” approach, “portions of a project begin construction while other portions of the project are still in the design phase”). This approach might allow, for example, site work to commence and a building’s foundation to be poured before the design for the remainder of the building is fully complete.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Immigration & Naturalization Service v. Chadha
462 U.S. 919 (Supreme Court, 1983)
Nationwide Mutual Insurance v. United States Fidelity & Guaranty Co.
550 A.2d 69 (Court of Appeals of Maryland, 1988)
Blind Industries & Services v. Maryland Department of General Services
808 A.2d 782 (Court of Appeals of Maryland, 2002)
Government Employees Insurance v. Insurance Commissioner
630 A.2d 713 (Court of Appeals of Maryland, 1993)
McGarvey v. State
533 A.2d 690 (Court of Appeals of Maryland, 1987)
A. S. Abell Publishing Co. v. Mezzanote
464 A.2d 1068 (Court of Appeals of Maryland, 1983)
Carroll County Ethics Commission v. Lennon
703 A.2d 1338 (Court of Special Appeals of Maryland, 1998)
Lockshin v. Semsker
987 A.2d 18 (Court of Appeals of Maryland, 2010)
Anderson v. Council of Unit Owners of Gables on Tuckerman Condominium
948 A.2d 11 (Court of Appeals of Maryland, 2008)
Farmers & Merchants National Bank v. Schlossberg
507 A.2d 172 (Court of Appeals of Maryland, 1986)
Napata v. University of Maryland Medical System Corp.
12 A.3d 144 (Court of Appeals of Maryland, 2011)
State Center, LLC v. Lexington Charles Ltd. Partnership
92 A.3d 400 (Court of Appeals of Maryland, 2014)
Maryland Pavement Co. v. Mahool
72 A. 833 (Court of Appeals of Maryland, 1909)
Chesapeake & Ohio Canal Co. v. Baltimore & Ohio Rail Road
4 G. & J. 1 (Court of Appeals of Maryland, 1832)

Cite This Page — Counsel Stack

Bluebook (online)
Maryland Attorney General Opinion 99OAG171, Counsel Stack Legal Research, https://law.counselstack.com/opinion/maryland-attorney-general-opinion-99oag171-mdag-2014.