Martin v. Winston

23 S.E.2d 873, 181 Va. 94, 1943 Va. LEXIS 156
CourtSupreme Court of Virginia
DecidedJanuary 18, 1943
DocketRecord No. 2574
StatusPublished
Cited by17 cases

This text of 23 S.E.2d 873 (Martin v. Winston) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Martin v. Winston, 23 S.E.2d 873, 181 Va. 94, 1943 Va. LEXIS 156 (Va. 1943).

Opinion

Eggleston, J.,

delivered the opinion of the court.

This is a writ of error reviewing a judgment setting aside and annulling an arbitration award because the lower court was of opinion that it was void for uncertainty. The pertinent facts are largely found in a number of documents which have been certified to us, some of which, as we shall presently see, the defendant in error contends are not properly a part of the record. We think it will be conducive both to clarity and brevity to state the facts and proceedings in the court below as deduced from these documents, before setting forth our reasons for concluding that those challenged are properly a part of the record.

[99]*99On November 15, 1938, Russell B. Martin and others, partners trading as Martin Brothers, of whom we shall speak as the contractors, entered into a written contract with Elizabeth B. Winston, to whom we shall refer as the owner, to furnish the necessary materials and construct for her a residence near Winston station, in Culpeper county, Virginia, in accordance with certain plans and specifications prepared by an architect. The work was to commence within three days of the date of the contract and the building was to be substantially completed within five months of the commencement of the work. The original contract price of $23,000 was by reason of additional items increased to the amount of $23,500.20. Payments were to be made as the work progressed.

After the building had been, as the contractors claim, substantially completed and the owner had made partial payments amounting to $19,351.80, a controversy arose between the parties as to whether the work had been done in accordance with the terms of the contract, the plans and specifications. Thereupon the parties entered into a written contract, dated April 22, 1940, whereby they agreed that in accordance with the provisions of chapter 257 of the Code of Virginia (sec. 6159 ff.), “all matters in controversy between them growing out of said contract, and any claim that the same has or has not been performed according to” the “true intent and meaning” of the contract, were submitted to the arbitrament and award of two arbitrators, who in turn were authorized and empowered to select a third. The arbitration contract further provided that within fifteen days after its date “each party shall serve upon the other party, or their counsel, a statement in writing of their respective demands, either under the contract, or resulting from the violation thereof, or failure to comply therewith; and each party receiving such notice shall within 20 days thereafter furnish the opposing party in like manner a concise statement in writing of their reply to the other side.”

[100]*100Provisions were made in the contract for hearings before the arbitrators and for the introduction of evidence and exhibits. It was further provided that the arbitrators “shall decide by majority vote any and all issues presented to them within the scope of the controversy, including complying with any award made. The award shall be made in writing, and shall be signed by all or by a majority of the arbitrators, and shall be made within a period of thirty days from the closing of the proceedings.”

An order was entered in the court below reciting the execution of the arbitration agreement and directing that the parties should “submit to the award” which should be made pursuant thereto.

In compliance with the arbitration agreement the contractors served upon the owner a statement of their claims. In substance it set out that the contractors had agreed to furnish the materials and construct the building in accordance with the plans and specifications, for the original sum of $23,000; that this amount had been increased by reason of “extras” less “deductions” to the net total of $23,455.05; that the contractors had fully performed the contract and were entitled to receive from the owner the full amount of the contract price; and that from time to time the owner had paid them the total amount of $19,351.80, leaving a balance due of $4,103.25 with interest.

In reply the owner served upon the contractors a statement of her claim in which she set out that the original contract price was $23,000, and that this had been increased by “extras” to $23,500.20.1 But she listed numerous instances wherein she claimed that the building did not meet the terms of the plans and specifications. Later we shall deal with this statement more in detail. Suffice it here to say that in the first section she claimed that the departures from the plans and specifications were such that the contractors should be [101]*101required to remove the structure in its entirety, to restore her property to its former condition, and to refund to her the $19,351.80 which she had paid to the contractors, plus alleged incurred expenses of $3,588.60, or a total of $22,940.40.

In the second section of her statement the owner alleged that should her first claim be denied and should the arbitrators find that the building could be made to conform to the plans and specifications, then she should be paid the necessary costs of making the required changes, which she stated would amount to $24,013.06, plus “liquidated damages” of $22,940.40, with the result that the contractors would owe her the net amount of $23,734.83.

The contractors filed a reply to tbe owner’s statement in which they admitted a few minor deviations from the plans and specifications, but denied the owner’s principal contentions.

After these written statements had been served, the arbitrators held numerous hearings extending over a period of approximately six months, at which a large volume of testimony was taken and numerous exhibits were introduced and considered.

On December 21, 1940, and within the time required by the arbitration agreement, the arbitrators filed in the clerk’s office of the lower court their award in which they disallowed the owner’s “claims and demands”, as set out by her, stating that these did not “represent justifiable charges against the contractor because of differences arising out of this contract.” But the arbitrators allowed the owner certain stated items amounting in all to $3,759.57, which sum was awarded to her “in consideration of the omissions, deviations, and defective workmanship in the performance of the contract”.

On December 30, 1940, and after the expiration of the time fixed in the arbitration agreement for filing the award, the arbitrators filed an addendum to their award in which they stated that, “It is the decision of the arbitrators that Miss Winston shall pay to Martin Brothers the balance due [102]*102on the contract after deductions allowed in the report” theretofore filed.

Pursuant to an order of the court a rule was issued from the clerk’s office, directed to and summoning the owner to appear before the lower court, at a stated date, to show cause “why the award of the arbitrators, according to the true intent and meaning thereof, when read in connection with the addendum, should not be enforced as a judgment of the court.”

In response to this summons the owner appeared by counsel and filed an answer in which she asked that the original award be set aside on the ground, among others, that it was uncertain and void, and that the addendum be rejected because it was filed too late.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anthony Wayne Edmonds v. Commonwealth of Virginia
Court of Appeals of Virginia, 2022
Darrell Thomas Ellis v. Talisha Danet Sutton-Ellis
Court of Appeals of Virginia, 2021
Virginia Eastern Co. v. N. C. Monroe Construction Co.
56 Va. Cir. 220 (Salem County Circuit Court, 2001)
Nicholson v. Nicholson
463 S.E.2d 334 (Court of Appeals of Virginia, 1995)
Griswold v. Com.
453 S.E.2d 287 (Court of Appeals of Virginia, 1995)
Griswold v. Commonwealth
453 S.E.2d 287 (Court of Appeals of Virginia, 1995)
Mueller v. Commonwealth
426 S.E.2d 339 (Court of Appeals of Virginia, 1993)
Trustees of Asbury United Methodist Church v. Taylor & Parrish, Inc.
33 Va. Cir. 532 (Chesterfield County Circuit Court, 1992)
Rosenstiel v. Fair
23 Va. Cir. 331 (Virginia Circuit Court, 1991)
Home Oil Co. of Hot Springs v. Home Oil Co.
393 S.E.2d 188 (Supreme Court of Virginia, 1990)
Ford v. Ross Bros. Builders, Inc.
19 Va. Cir. 423 (Stafford County Circuit Court, 1990)
Rural Water District No. 6 v. Ziegler Corp.
677 P.2d 573 (Court of Appeals of Kansas, 1984)
Hudson v. State
388 So. 2d 577 (District Court of Appeal of Florida, 1980)
Labor Relations Board v. Sociedad Mario Mercado e Hijos
74 P.R. 376 (Supreme Court of Puerto Rico, 1953)
Junta de Relaciones del Trabajo v. Sociedad Mario Mercado e Hijos
74 P.R. Dec. 403 (Supreme Court of Puerto Rico, 1953)
Martin v. Winston
40 S.E.2d 247 (Supreme Court of Virginia, 1946)

Cite This Page — Counsel Stack

Bluebook (online)
23 S.E.2d 873, 181 Va. 94, 1943 Va. LEXIS 156, Counsel Stack Legal Research, https://law.counselstack.com/opinion/martin-v-winston-va-1943.